Shutdown Activities
  • Removing of unused channels from readout
  • Blue modifications, removed capacitor from unused
    channels
  • Fred and New Experts remove boards from the
    platform for modifications
  • Fred and New Experts reinstall boards on the
    platform
  • Some boards do not come back, the recovery work
    hampered by power outages and calorimeter noise
    studies
  • Modifications for 53 MHz readout
  • Fred and New Experts successfully installed 53
    MHz readout on crate 0x50
  • Jameson Olsen upgraded Sequencer and DFE power
    supplies on South and West side of the Platform,
    still North side to be done
  • Upgrade of AFE power supplies has not started yet