Title: HERA Status
1HERA Status
59th Meeting of the Physics Research Committee
May 26th, 2005
2Contents
- Operation of HERA 04/05 with Electrons
- Luminosity Performance
- Major technical Problems
- Polarization
- Improvements
- Schedule 2005
- Conclusions
3Re-Commissioning with Electrons
- HERA electron operation
- More synchrotron radiation (for design currents
26 kW ?36 kW) - Different orbits for e and p in IR
- Successful re-commissioning strategy (Oct.-Dec.
04) - Set up/check HERA-e with positrons
- Move magnets in IR
- Continue with electrons
- Beam-based alignment check of optic and
correction - Start with electrons was smooth ? No big
problems found! - But It was necessary to move H1 by ?x7 mm due
tolimited space in GO magnet on left side - Delay in schedule
- Quadrupole GN NL20 had a burnt coil
- Vacuum leak at GI07 NR
4Trajectories for e-/p and e/p in IR
GM
GM
GM
GM
GG,HG
7.5 mm
GI
-
GO,HO
p beam for e-
p
p-beam for e
e--beam
-
-
GI
GI
e-beam
GJ
-
GJ
BO
e?
Radial orbit shift at IP of 7.5 mm between
electron and positron operation
5Parameters of Run 04/05 with Electrons
Design
2005 with e-
For e- Vacuum, RFFor p Pre-accelerators
Beam-Beam effects
For p Long. instability
Hour glass factor included in design!
6Beam Currents
- Peak currents for run 04/05 with electrons (150
bunches) - Ipmax 102 mA
- Iemax 40 mA
- Proton single bunch current is highWould be 123
mA with 180 bunches! - Electron current was limited first by H1
background (vacuum) - No progress increasing the electron beam current
in the last months?slow conditioning of RF
cavities, transmitter problems and vacuum - Switch to 180 bunches if 40 mA electrons can be
routinely filled but dust trapping probability
will be higher!
7Specific Luminosity
- High specific luminosity with electrons for
2004/05 run Ls 1.8 - 2.2 ?1030
cm-1s-1mA-2 - Specific Luminosity is larger than the design
value of Ls 1.84 ?1030 cm-1s-1mA-2 - One reason for higher specific luminosity
compared to last year with positrons (1.2
-1.6?1030) is the smaller proton emittance and
bunch length - Calculated specific luminosity based on measured
beam parameters can describe the measurements of
H1 and ZEUS sufficiently good
overestimated
8Integrated Luminosity 04/05
- Integrated luminosity is 95.3 pb-1 in 156 days
(start Dec. 17th, 2004) - Best run delivered 1.1 pb-1 within14 hours
- On average 0.61 pb-1/d (number for last year
0.41 pb-1/d) - Mid of May was best so farHERA delivered 1.17
pb-1/d - New record peak luminosity ofL 5.07?1031
cm-2s-1 was achieved - But high proton background and many spikes until
BU SR coil was identified as the culprit? fixed
in April!
9Integrated Luminosity
Luminosity production rate with electrons in 2005
is higher than 2004 for positrons!
(ZEUS)
10HERA e--Lifetime
- Again Sudden lifetime reduction and lifetime
recovery during electron operation - At the same time increased beam loss measured
- Observed for I gt 30 mA since January 05 but
number of events is fortunately rare at the
moment - Theory trapping of positive ionized dust
particles by the negative charged electron beam - Source of dust Ion getter pumps (dipole pumps
were already replaced in shutdown 1997/98) - If the number of bunches is increased, the
probability of dust trapping gets higher
Lifetime event 4.5.2005
11HERA Operational Statistics 2005
Relative large amount of faults is reducing the
efficiency of operation fraction for e- and
p-injection times have decreased, fraction of
luminosity-run increased since 04.
Main problems for faults and delays in 05 were
due to magnet problems, cryogenics, power
supplies, PETRA and problems with the proton
quench protection.
12Major technical problems
- Nov. 2004
- Burnt coil of proton quadrupole magnet GN NL 20
? Coil exchanged - Dec 2004
- GI NR 7 vacuum leak broken feed through of NEG
pump - Jan. 2005
- Ground fault proton quadrupole magnet GN NL 23 ?
Coil exchanged - Feb. 2005
- Cryogenic compressor failure ? quick repair but
p-ring warmed up (1 week) - Apr. 2005
- Periodic p-background spikes? shorted coil of
BU-magnet SR coil exchanged (4 days) - May 2005
- Vacuum leak in p-chamber between GM proton
quadrupoles NR ? welding of seam bad vacuum
(since 1 week)
13GN Magnet Problem
- During recommissioning in Nov. 04 the magnet GN
NL20 failed (cooling problem) - GN magnet vertical focussing low beta quadrupole
for protons 12 magnets - Damaged lower inner coil had to be exchanged (six
days lost) - In January 05 also the magnet GN NL23 failed
with ground fault all four coils were replaced
(1 week) - Possible reason Magnets have been operated with
1638 A during power supply tests in October last
year exceeding the manufacturer limit of 1600 A - Measures
- Current of power supply limited to 1470 A (max.
value for luminosity run) - New coils ordered!
14BU Magnet Problem
- Since January 05 Periodic background spikes in
combination with vertical orbit movements not
all the time - Reason was shorted coil of BU magnet SR April
coil exchanged (4 days) - BU bend the protons upwards at end of straight
sections 18 magnets - Six BU-coils in NL (last shutdown) and one coil
in SL were already exchanged - Candidate for another short BU OL
- Measures
- Measurement of voltage drop of coils
- Exchange of all remaining BU coils in next
shutdown?Shutdown delayed until all ordered
coils are delivered (shutdown starting at
14th Nov. 05)
Collimator beam loss rate
15Polarization
Non-colliding bunches 50
Colliding bunches 40
- Even after long tuning polarization is
dis-appointing low - Colliding bunches reaches 40 only at end of run
(but non-colliding have ?55!) - Influence of beam-beam effect Polarization is
rising due to growth of proton emittance and
declining proton intensity - Energy and harmonic bumps are optimized
- Problem Tunes are not optimal for electrons and
polarization! - Measures
- Electron intensity related effects allows to
decrease the tunes at lower electron
current?But e-background spikes at H1! - Possible solution Mirror tunes? started test
with mirror tunes last week!
Polarisation
History of polarization and single bunch
polarization
16Mirror Tunes
17Improved e--Transfer Efficiency
- Transfer efficiency of El-Weg between PETRA and
HERA-e - HERA I never reached 100
- HERA-II sometimes only 30-40 and
non-reproducible! - Better efficiency ? faster filling, less
radiation during injection process - Measures
- Calculation of a new matched optic for the EL-Weg
adapted for HERA-II injection optic - Installation of 6 beam position monitors in last
summer shutdown - Checked magnet rolls by survey ? ok!
- Measurement of response matrix of the EL-Weg ?
large error in optics - Measurement of quadrupole calibration curve ?
calibration wrong!
- Now
- Transfer efficiency gt70
- Efficiency more stable than before
- Remaining losses PETRA extraction
18Improvement Proton Tune Controller
- Energy ramp of protons is demanding
- Induced eddy currents in super- conductors ? Time
varying dipole and sextupole fields - Tunes near coupling resonance
- Control of beam parameters is done manually by
operators watching beam signals and turning
knobs needs much experience! - Nevertheless p-beam often get lost
- Measure
- Semi-automatic control of tunes was developed
ramping between 70 GeV and 920 GeV and electron
refill are now far easier than before! - Coupling and chromaticity control under
development
19Longitudinal Multi-Bunch Feedback
Schematic principle
- Proton-bunch lengthening due to longitudinal
coherent multi-bunch instability - Longer bunches ? smaller specific luminosity
(Hour glass effect) - Happens during proton ramping
- Measure
- Installation of an longitudinal multi-bunch
feedback system for protrons - Status Feedback cavity arrived first
measurements done - Installation in next shutdown
- Goal Reduction of bunch length at 920 GeV from
1.6 ns to 0.7 ns (FWHM) realistic?
Feedback Cavity
20Schedule 2005
- Schedule
- Start of luminosity operation 17th Dec. 04
- Start of shutdown 14th
Nov. 05 - End of shutdown End of
Jan. 06 - Luminosity operation 2nd week
in Feb. 06 - Expectations for integrated luminosity
- Until now Li 95 pb-1 in 156 days
- Conservative assumption Average increase of 0.61
pb-1/d - This includes hardware faults, maintenance days,
- 176 days remaining ? Additional 107 pb-1
- Lower bound for 2005 Li ? 200 pb-1 ?
- Can be even more, if hardware problems happen not
so frequentlyand electron current can be
increased! - Plans for hardware changes in the shutdown
- Exchange of all remaining BU coils
- Installation of the longitudinal proton feedback
cavity
21Conclusions
- High luminosity production with electrons
performanceof HERA has greatly improved - Integrated luminosity up to now with electrons
has alreadyexceeded the value with positrons of
year 2004 - Background conditions are usually good after
sourceof p-background spikes has been found but
there was againa vacuum leak in north! - Polarization with max. 40 disappointing ?
investigation of mirror-tunes has started - Availability of HERA components and operational
efficiencyis still too low - HERA will continue luminosity operation until
wintershutdown (14th Nov. 2005 Jan./Feb. 2006)