Title: Cyclone and Dryer Liner Upgrades
1Cyclone and DryerLiner Upgrades
- Dennis Todd
- President, Wear-Concepts, Inc
2- Introduction
- Granulated blast furnace grinding system in
Midwest U.S. - Had been online 6 months, OEM material in dryer
shaft and cyclone showed constant wear and
needed continual repair during first year of
operation - In 2002 system required liner replacements and
repairs were requested
3- Flash Dryerand Shaft
- Design Polysius
- Year of Manufacture 2001
- Nominal Diameter 1200 mm
- Height 25700 mm
- Feed moisture content max 12
- Residual moisture content 2.5 4
- Throughput Rate 77 t/h
- Collecting System Cyclone
Figure 1. Portion of unit
4Flash Dryer
Figure 2. Upper Duct
Figure 3. Lower Duct
5- High-Efficiency Cyclone
- Polysius
- Unit upstream of cyclone flash dryer
- Dimensions 7740 mm
- Nominal Diameter of Cyclone 3310 mm
- Diameter of Dip Pipe 1740 mm
- Length of Dip Pipe 1895 mm
Figure 4. Polysius High-Efficiency Cyclone
6Problem Overview
7Figure 5. OEM Refractorylining wear
Figure 6. OEM original wearback after 3 months
- At one point, 50 of liner was missing
- Large scale system handled a velocity of 18 22
m/s up the shaft - Numerous repairs had been attempted
- Any new solution needed to greatly reduce
downtime
8The Challenge
9- Wear-Concepts and customer jointly agreed that
old lining would need to be completely removed - Dryer shaft stood 7 stories tall and inside main
body of dryer shaft was only 1.21 meters feet
wide - Only three week window in January to repair with
average outside temperature of only -12 C
Figure 7. Major wear throughout.
Figure 8. Inside dryer shaft.
10The Solution
11- Wear-Concepts has extensive experience with wear
problems and had upgraded similar slag
grinding system one year earlier - Factors to consider outside temps temperature
differences in dryer shaft (275 C at bottom
of shaft and 65 C in cyclone) velocity of
material flow up the shaft and at upper elbow. - Turn-key solution would require complete
tear-out of all existing lining material and
hex expanded material underneath. - Full install of Wear-Con WC90 alumina weldable
ceramic tiles throughout vertical portion of
dryer shaft and major wear areas of cyclone - Elbow at top of shaft 1 (2.54 cm) thick WC700
Chrome Carbide
12The Task
13- Scaffolding was constructed to move workers
through the narrow, 7 story shaft - Old liner and expanded hex material had to be
air- hammered and chiseled out
Figure 9. Original liner and expanded metal
removal
14Finally, surface of the walls had to be ground
smooth, then cleaned so that proper adhesion
could be attained
Figure 10. View downdryer shaft
15- Each new brick was spot-welded to the wall and
a ceramic cap was inserted into the weld hole. - The cap was then sealed with Premium Grade
High- Temperature sealant, as were all edges
and joints.
Figure 11. View oftiled shaft
Figure 12. View of access door in shaft
16Impact zone of elbow received 1 (2.54 cm) thick
custom engineered WC700 Chrome Carbide. Liner
designed into three separate removable wear backs
for ease of installation in high- impact zone
Figure 14. Close up of WC700 Liner
Figure 13. Exterior view of WC700 Liner
17The crew then lined the large cylindrical-shaped
cyclone which measured approximately 3310 mm
across and 7240 mm in height
Figure 15. View of inside cyclone
Figure 16. View of cone sectionof cyclone
18All work was completed safely, within budget and
two days ahead of schedule, despite bitter
weather conditions.
19(No Transcript)
20Follow UpImprovementsAug 03 to present
21August 2003
- Original liner in feed inlet chute to flash
dryer wore out in summer of 2003 - WC90 Ceramic Liner installed in bottom and
sides to improve service life
Figures 18. Exterior view offeed inlet chute
Figures 17. WC90 lining andfeed inlet chute
221-1/4 (3.175 cm) brickinstalled - May 2004
- 1-1/4 (3.175 cm) Brick was installed due to
fine particle abrasion. Gap filled in.
Figures 19. Gap in upper corner
Figures 20. Gap repaired
232 (5.08 cm) Brick on WearBack - December 2004
- For added life, 2 (5.08 cm) WC90 Ceramic
brick was installed to replace portions of 1
(2.54 cm) WC700 Chrome Carbide
Figures 21-22. 2 Brick on one section of Wear
Back
24Dip Tube RepairedJanuary 2005
- New Dip Tube was lined inside and out with ½
(1.27 cm) WC90 Ceramic Brick
Figures 23-24. Dip Tube lined
252 (5.08 cm) Brick on Cyclonewall - June 2005
- New isolated wear required installation of 2
(5.08 cm) WC90 Ceramic brick on sections of
cyclone wall
Figures 25-26. 2 (5.08 cm) Brick on Cyclone wall
26- Original manufacturers warranty was 1 year. Only
provided about 6 months of service life. - Our lining was warranted for 2 years, but lasted
3 years - Production at plant has increased 200
- Six times the service life over OEM designed
lining.
27Cyclone and DryerLiner Upgrades
- Dennis Todd
- President, Wear-Concepts, Inc
28- This concludes the presentation.
- Please close this window to return to our main
website.