Cyclone and Dryer Liner Upgrades - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

Cyclone and Dryer Liner Upgrades

Description:

Had been online 6 months, OEM material in dryer shaft. and cyclone showed constant wear and needed continual. repair during first year of operation ... – PowerPoint PPT presentation

Number of Views:147
Avg rating:3.0/5.0
Slides: 29
Provided by: dexterwi
Category:

less

Transcript and Presenter's Notes

Title: Cyclone and Dryer Liner Upgrades


1
Cyclone and DryerLiner Upgrades
  • Dennis Todd
  • President, Wear-Concepts, Inc

2
  • Introduction
  • Granulated blast furnace grinding system in
    Midwest U.S.
  • Had been online 6 months, OEM material in dryer
    shaft and cyclone showed constant wear and
    needed continual repair during first year of
    operation
  • In 2002 system required liner replacements and
    repairs were requested

3
  • Flash Dryerand Shaft
  • Design Polysius
  • Year of Manufacture 2001
  • Nominal Diameter 1200 mm
  • Height 25700 mm
  • Feed moisture content max 12
  • Residual moisture content 2.5 4
  • Throughput Rate 77 t/h
  • Collecting System Cyclone

Figure 1. Portion of unit
4
Flash Dryer
Figure 2. Upper Duct
Figure 3. Lower Duct
5
  • High-Efficiency Cyclone
  • Polysius
  • Unit upstream of cyclone flash dryer
  • Dimensions 7740 mm
  • Nominal Diameter of Cyclone 3310 mm
  • Diameter of Dip Pipe 1740 mm
  • Length of Dip Pipe 1895 mm

Figure 4. Polysius High-Efficiency Cyclone
6
Problem Overview
7
Figure 5. OEM Refractorylining wear
Figure 6. OEM original wearback after 3 months
  • At one point, 50 of liner was missing
  • Large scale system handled a velocity of 18 22
    m/s up the shaft
  • Numerous repairs had been attempted
  • Any new solution needed to greatly reduce
    downtime

8
The Challenge
9
  • Wear-Concepts and customer jointly agreed that
    old lining would need to be completely removed
  • Dryer shaft stood 7 stories tall and inside main
    body of dryer shaft was only 1.21 meters feet
    wide
  • Only three week window in January to repair with
    average outside temperature of only -12 C

Figure 7. Major wear throughout.
Figure 8. Inside dryer shaft.
10
The Solution
11
  • Wear-Concepts has extensive experience with wear
    problems and had upgraded similar slag
    grinding system one year earlier
  • Factors to consider outside temps temperature
    differences in dryer shaft (275 C at bottom
    of shaft and 65 C in cyclone) velocity of
    material flow up the shaft and at upper elbow.
  • Turn-key solution would require complete
    tear-out of all existing lining material and
    hex expanded material underneath.
  • Full install of Wear-Con WC90 alumina weldable
    ceramic tiles throughout vertical portion of
    dryer shaft and major wear areas of cyclone
  • Elbow at top of shaft 1 (2.54 cm) thick WC700
    Chrome Carbide

12
The Task
13
  • Scaffolding was constructed to move workers
    through the narrow, 7 story shaft
  • Old liner and expanded hex material had to be
    air- hammered and chiseled out

Figure 9. Original liner and expanded metal
removal
14
Finally, surface of the walls had to be ground
smooth, then cleaned so that proper adhesion
could be attained
Figure 10. View downdryer shaft
15
  • Each new brick was spot-welded to the wall and
    a ceramic cap was inserted into the weld hole.
  • The cap was then sealed with Premium Grade
    High- Temperature sealant, as were all edges
    and joints.

Figure 11. View oftiled shaft
Figure 12. View of access door in shaft
16
Impact zone of elbow received 1 (2.54 cm) thick
custom engineered WC700 Chrome Carbide. Liner
designed into three separate removable wear backs
for ease of installation in high- impact zone
Figure 14. Close up of WC700 Liner
Figure 13. Exterior view of WC700 Liner
17
The crew then lined the large cylindrical-shaped
cyclone which measured approximately 3310 mm
across and 7240 mm in height
Figure 15. View of inside cyclone
Figure 16. View of cone sectionof cyclone
18
All work was completed safely, within budget and
two days ahead of schedule, despite bitter
weather conditions.
19
(No Transcript)
20
Follow UpImprovementsAug 03 to present
21
August 2003
  • Original liner in feed inlet chute to flash
    dryer wore out in summer of 2003
  • WC90 Ceramic Liner installed in bottom and
    sides to improve service life

Figures 18. Exterior view offeed inlet chute
Figures 17. WC90 lining andfeed inlet chute
22
1-1/4 (3.175 cm) brickinstalled - May 2004
  • 1-1/4 (3.175 cm) Brick was installed due to
    fine particle abrasion. Gap filled in.

Figures 19. Gap in upper corner
Figures 20. Gap repaired
23
2 (5.08 cm) Brick on WearBack - December 2004
  • For added life, 2 (5.08 cm) WC90 Ceramic
    brick was installed to replace portions of 1
    (2.54 cm) WC700 Chrome Carbide

Figures 21-22. 2 Brick on one section of Wear
Back
24
Dip Tube RepairedJanuary 2005
  • New Dip Tube was lined inside and out with ½
    (1.27 cm) WC90 Ceramic Brick

Figures 23-24. Dip Tube lined
25
2 (5.08 cm) Brick on Cyclonewall - June 2005
  • New isolated wear required installation of 2
    (5.08 cm) WC90 Ceramic brick on sections of
    cyclone wall

Figures 25-26. 2 (5.08 cm) Brick on Cyclone wall
26
  • Original manufacturers warranty was 1 year. Only
    provided about 6 months of service life.
  • Our lining was warranted for 2 years, but lasted
    3 years
  • Production at plant has increased 200
  • Six times the service life over OEM designed
    lining.

27
Cyclone and DryerLiner Upgrades
  • Dennis Todd
  • President, Wear-Concepts, Inc

28
  • This concludes the presentation.
  • Please close this window to return to our main
    website.
Write a Comment
User Comments (0)
About PowerShow.com