CNS 3153 Legal Issues In Construction Chapter 8 Delays - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

CNS 3153 Legal Issues In Construction Chapter 8 Delays

Description:

Kingston subcontracted the manufacturing of the transformers to Power Energy Industries ('PEI' ... Six out of 11 transformers failed these tests. ... – PowerPoint PPT presentation

Number of Views:269
Avg rating:3.0/5.0
Slides: 23
Provided by: gary8
Category:

less

Transcript and Presenter's Notes

Title: CNS 3153 Legal Issues In Construction Chapter 8 Delays


1
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Morse/Diesel, Inc. v. Trinity Industries, Inc.
    Mosher Steel Co., and Aetna Insurance Co.,67 F.3d
    435, 1995 U.S. App. LEXIS 27614 (2d Cir. Sept.
    26, 1995).
  •  Morse/Diesel, Inc. ("Morse/Diesel") was the
    general contractor for the construction of the
    Marriott Marquis Hotel in Manhattan's Times
    Square. In August, 1982, Morse/Diesel entered
    into a subcontract with Mosher Steel Company, a
    division of Trinity Industries, Inc. ("Trinity")
    to fabricate and erect the steel members
    necessary for hotel construction within 13
    months, excluding inclement weather. In fact, the
    job took 20 months, from January, 1983 until
    September, 1984. Morse/Diesel sued Trinity and
    Trinity's bonding company, Aetna Insurance
    Company, for damages in the amount of 37 million
    arising from the cost of an acceleration program
    designed to recapture the delay, as well as
    losses suffered by the hotel's owner, the
    architect and other subcontractors. Trinity
    counterclaimed for its own damages arising from
    additional work and delay in completing the
    subcontract.
  • Responsibility for the delay surfaced as the
    central question in the trial court litigation.
    Morse/Diesel blamed Trinity, producing evidence
    of fabrication errors, shipping mishaps, crane
    failures, and so on. In support of its
    counterclaim for increased cost and delay,
    Trinity alleged that the project's architect,
    John Portman Associates, and structural
    engineer, Weidlinger Associates, made unwarranted
    demands regarding the installation of certain
    special steel trusses, known as Vierendeel
    trusses, and the use of additional bracing during
    erection. Following six and a half weeks of
    trial, the jury substantially agreed with
    Morse/Diesel and awarded the company almost 26
    million in damages, to which the court added an
    additional 27 million in prejudgment interest.
    Trinity appealed.

2
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • On appeal, Trinity argued, inter alia, that the
    trial court's treatment of various clauses
    regarding delay unfairly precluded Trinity from
    presenting its counterclaim to the jury. Schedule
    B, paragraph 53, of Trinity's subcontract
    provided
  • Should the Subcontractor be obstructed or
    delayed in the commencement, prosecution or
    completion of the work, without fault on his
    part, by action or inaction on the part of the
    Owner, Architect, Engineer or Contract, or by
    changes in the work, the Subcontractor shall be
    entitled to include as cost the cost of labor,
    materials, equipment, supplies and other
    resultant costs occasioned by such delays and
    changes notwithstanding any other provision
    contained in this agreement. (Emphasis added).
  • However, two other provisions in Trinity's
    subcontract contained no-damage-for delay
    clauses. Should the subcontract be obstructed
    or delayed in the commencement, prosecution or
    completion of the work . . . then he shall be
    entitled to an extension of time . . . the
    subcontractor expressly agrees not to make, and
    hereby waives, any claim for damages, including
    those resulting from increased supervision, labor
    or material costs, on account of any delay,
    obstruction or hindrance for any cause whatsoever
    . . . and agrees that the sole right and remedy
    therefor shall be an extension of time.General
    Conditions, Article 16-G (emphasis added). And
    Article 3.4 of the subcontract provides, in part
    All loss or damage arising from any of the Work
    through unforeseen or unusual obstructions,
    difficulties or delays which may be encountered
    in the prosecution of same or through the action
    of the elements shall be borne by the
    Subcontractor.

3
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Against this contractual backdrop, Trinity
    requested a jury instruction that it could
    recover damages under paragraph 53 for costs
    associated with delays caused by others. The
    trial court denied the request and instructed the
    jury that Trinity's "claim for damages on account
    of delays allegedly caused by Morse/Diesel and
    its subcontractors" was an "area of ambiguity" in
    the subcontract, citing Article 16-G of the
    General Conditions and Article 3.4 of the
    subcontract. She then noted Trinity's contention
    that these two provisions have been negated by
    paragraph 53. In the face of such apparent
    ambiguity, Judge Preska instructed that it was
    the jury's job to interpret the allegedly
    ambiguous subcontract.
  • The Court of Appeals for the Second Circuit held
    the jury instructions to be fatally flawed
    because the subcontract contained no ambiguity.
    The Court initially noted that under New York
    law, a written contract is to be interpreted so
    as to give effect to the intention of the parties
    as expressed in the unequivocal language of the
    subcontract. It then found that the
    "notwithstanding" clause of paragraph 53 relieved
    any tension among the three contract provisions
    addressing delay. More specifically, the court
    held that paragraph 53 overrode the otherwise
    inconsistent clauses of Article 3.4 and Article
    16-G of the General Conditions.

4
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Accordingly, the Court held that the district
    court erred when it submitted the contract's
    meaning on this point to the jury. The district
    court should have construed the contract
    according to its unambiguous terms, and clearly
    instructed the jury that Trinity had the right
    under paragraph 53 to recover any costs
    occasioned by delays that were not its own fault.
  • Moreover, the Court proceeded to hold that the
    error could not be deemed harmless. The jury
    returned a general verdict. While the jury
    apparently concluded that Trinity was at fault
    for much of the delay and resulting acceleration
    damages, Morse/Diesel did not recover all that it
    sought. Thus, the Court found it very possible
    that the jury believed Morse/Diesel was indeed to
    blame for some of the delay. Finding it
    impossible to isolate the counterclaim for
    retrial, the Court found it necessary to reverse
    the judgment in total and to remand both the
    complaint and the counterclaim for retrial.

5
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Rights and obligations associated with delays
    arise from the implied obligation in every
    contract that each party will not delay, hinder
    or interfere with the performance of the other
    party. Or, more commonly the contract contains
    an explicit obligation to perform by a given date
    or within a specified time frame.

6
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • time is of the essence contractual clause
    that makes time a component of the contractors
    performance obligation.
  • Substantial Completion the work is sufficiently
    complete so that the owner may occupy or utilize
    the facility for its intended use. An owner may
    not assess l.d.s after substantial completion.

7
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Nonexcusable Delays
  • A delay that could have been anticipated or
    avoided. The party that causes a nonexcusable
    delay usually creates an excusable delay for the
    other party.
  • Excusable Delays
  • Generally, when an unanticipated outside force
    delays completion.
  • Design problems
  • Differing site conditions
  • Unusually adverse weather
  • Acts of God

8
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Compensable Delay the contractor is entitled to
    both time and monetary damages.
  • Defective drawings or specs.
  • Failure to provide access
  • Improper site prep.
  • Failure to supply materials or labor
  • Failure to approve shop drawings
  • Failure to coordinate prime contractors
  • Failure to give timely orders for work

9
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Compensable Delays contd.
  • Failure to make timely payments
  • Failure to inspect
  • Suspensions
  • Excessive change orders
  • Failure to accept completed work
  • Acceleration
  • Can a contractor recover damages for delays even
    if they finished the project before the contract
    completion date?

10
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Noncompensable Delay the contractor is entitled
    to a time extension only.
  • Unusually severe weather
  • Acts of God
  • Labor problems

11
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Concurrent Delay
  • When an excusable compensable delay and an
    unexcusable delay occur at the same time or
    overlap in time.
  • The current trend is to use CPM analysis to
    evaluate the delays and apportion damages
    accordingly.

12
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Written Notice the contractor who gives prompt
    written notice of delays increases their
    opportunity to recover damages.
  • Time extensions are almost always granted for
    excusable delays.
  • Recovery of additional costs may be limited by a
    no-damages-for-delay clause.

13
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Exceptions To no-damage-for-delay
  • The delay was not contemplated by the clause in
    the contract (some clauses explicitly list delays
    that fall under the n-d-f-d clause).
  • The delay resulted in an abandonment of the
    contract.
  • The delay was due to fraud, bad faith or an
    arbitrary action.
  • The delay was due to the owner interfering with
    the contractors work.
  • The delay was unreasonable.
  • The contractors work was hindered by the owner
    (hindered vs. actively interfered)

14
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • What costs can the contractor recover?
  • Liquidated damages
  • Labor inefficiency
  • Equipment inefficiency
  • Acceleration and overtime
  • Extended field overhead
  • Home office overhead
  • Escalated material and labor costs
  • Legal fees
  • Interest
  • Loss of profits
  • Loss of bonding capacity

15
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Owner Damages
  • Most often owner damages are fixed in the
    contract as liquidated damages.
  • If the liquidated damages do not reasonably
    approximate foreseeable actual damages, but
    appear to act as a penalty, the provision will
    likely be unenforceable. Under such
    circumstances, the owner will have to prove their
    actual damages in order to recover.
  • Can liquidated damages work in favor of the
    contractor?

16
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Delay Claims Analysis
  • Detailed documentation is essential to recovering
    the maximum amount possible.
  • Proper scheduling techniques are imperative in
    evaluating delay impacts.
  • Seek expert advice if necessary.

17
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • Kingston Constructors, Inc. v. Washington
    Metropolitan Area Transit Auhority,1996 U.S.
    Dist. LEXIS 8427 (D.D.C. June 6, 1996).
  •  The defendant Washington Metropolitan Area
    Transit Authority ("WMATA") contracted with
    plaintiff Kingston Contractors, Inc. ("Kingston")
    to remove and destroy existing electrical
    transformers in WMATA's rapid transit rail
    system, and procure and install replacement
    transformers. The contract contained a liquidated
    damages provision which provided for 1000 for
    each calendar day of delay beyond a specified
    completion date.
  • Kingston subcontracted the manufacturing of the
    transformers to Power Energy Industries ("PEI").
    Contractually required pre-installation testing
    of the manufactured units revealed that they
    contained misplaced insulation which caused a
    short circuit defect. In addition, when the first
    unit was installed, it functioned for only a few
    minutes before failing and releasing a cloud of
    smoke.
  • In an attempt to assure that the transformers
    would still be capable of performing as required,
    the parties then subjected the transformers to
    additional tests, beyond those required in the
    contract. Six out of 11 transformers failed these
    tests. WMATA also rejected another solution
    proposed by Kingston, because WMATA thought that
    the proposed solution might compromise the
    structural integrity of the transformers and
    shorten their useful lives.

18
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • When two transformers failed another round of
    tests, WMATA rejected the entire lot of 22
    transformers that had already been manufactured,
    stating that it had completely lost confidence in
    the ability of the PEI transformers to function
    as required. Kingston was forced to reprocure the
    transformers, at substantial additional cost.
    Also because of the reprocurement, Kingston was
    unable to finish on time and, as a result,
    incurred liquidated damages costs.
  • Kingston asked the Board to grant it a time
    extension and an equitable adjustment in the
    amount of the contract. The Board granted an
    equitable adjustment for costs and delays
    associated with the additional extra-contractual
    testing, and reduced the amount of liquidated
    damages from 1000 per day to 500 per day.
    Kingston then appealed to the district court,
    challenging, inter alia, the Board's decision to
    reduce the liquidated damages. Kingston claimed
    that the Board's only alternative was to declare
    the clause unenforceable.

19
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • The Board had found that, in determining the
    1000 liquidated damages figure, WMATA had
    included a 500 contingency for the possible
    assessment of Environmental Protection Agency
    penalties associated with the work, even though
    WMATA already knew that the EPA was not going to
    assess such penalties. Citing the general rule
    that a liquidated damages provision which is an
    unreasonable approximation of damages must be
    stricken as an unenforceable penalty, the
    district court agreed with Kingston that WMATA
    had acted unreasonably in setting the liquidated
    damages amount, and that the Board had erred in
    reducing the liquidated damages amount rather
    than striking the clause altogether.
  • The court disagreed, however, with Kingston's
    assertion that striking the damages clause was
    the only course of action open to the Board.
    Rather, the court held that actual damages should
    be awarded instead of liquidated damages, and it
    remanded the case for a determination of the
    amount of such damages. The case may have been a
    Pyrrhic victory for Kingston, since WMATA claimed
    that its actual damages were more than 1000 per
    day.

20
CNS 3153Legal Issues In ConstructionChapter 8
Delays
  • The court disagreed, however, with Kingston's
    assertion that striking the damages clause was
    the only course of action open to the Board.
    Rather, the court held that actual damages should
    be awarded instead of liquidated damages, and it
    remanded the case for a determination of the
    amount of such damages. The case may have been a
    Pyrrhic victory for Kingston, since WMATA claimed
    that its actual damages were more than 1000 per
    day.

21
CNS 3153Legal Issues In ConstructionChapter 8
Delays
22
CNS 3153Legal Issues In ConstructionChapter 8
Delays
Write a Comment
User Comments (0)
About PowerShow.com