Title: CNS 3153 Legal Issues In Construction Chapter 8 Delays
1CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Morse/Diesel, Inc. v. Trinity Industries, Inc.
Mosher Steel Co., and Aetna Insurance Co.,67 F.3d
435, 1995 U.S. App. LEXIS 27614 (2d Cir. Sept.
26, 1995). - Morse/Diesel, Inc. ("Morse/Diesel") was the
general contractor for the construction of the
Marriott Marquis Hotel in Manhattan's Times
Square. In August, 1982, Morse/Diesel entered
into a subcontract with Mosher Steel Company, a
division of Trinity Industries, Inc. ("Trinity")
to fabricate and erect the steel members
necessary for hotel construction within 13
months, excluding inclement weather. In fact, the
job took 20 months, from January, 1983 until
September, 1984. Morse/Diesel sued Trinity and
Trinity's bonding company, Aetna Insurance
Company, for damages in the amount of 37 million
arising from the cost of an acceleration program
designed to recapture the delay, as well as
losses suffered by the hotel's owner, the
architect and other subcontractors. Trinity
counterclaimed for its own damages arising from
additional work and delay in completing the
subcontract. - Responsibility for the delay surfaced as the
central question in the trial court litigation.
Morse/Diesel blamed Trinity, producing evidence
of fabrication errors, shipping mishaps, crane
failures, and so on. In support of its
counterclaim for increased cost and delay,
Trinity alleged that the project's architect,
John Portman Associates, and structural
engineer, Weidlinger Associates, made unwarranted
demands regarding the installation of certain
special steel trusses, known as Vierendeel
trusses, and the use of additional bracing during
erection. Following six and a half weeks of
trial, the jury substantially agreed with
Morse/Diesel and awarded the company almost 26
million in damages, to which the court added an
additional 27 million in prejudgment interest.
Trinity appealed.
2CNS 3153Legal Issues In ConstructionChapter 8
Delays
- On appeal, Trinity argued, inter alia, that the
trial court's treatment of various clauses
regarding delay unfairly precluded Trinity from
presenting its counterclaim to the jury. Schedule
B, paragraph 53, of Trinity's subcontract
provided - Should the Subcontractor be obstructed or
delayed in the commencement, prosecution or
completion of the work, without fault on his
part, by action or inaction on the part of the
Owner, Architect, Engineer or Contract, or by
changes in the work, the Subcontractor shall be
entitled to include as cost the cost of labor,
materials, equipment, supplies and other
resultant costs occasioned by such delays and
changes notwithstanding any other provision
contained in this agreement. (Emphasis added). - However, two other provisions in Trinity's
subcontract contained no-damage-for delay
clauses. Should the subcontract be obstructed
or delayed in the commencement, prosecution or
completion of the work . . . then he shall be
entitled to an extension of time . . . the
subcontractor expressly agrees not to make, and
hereby waives, any claim for damages, including
those resulting from increased supervision, labor
or material costs, on account of any delay,
obstruction or hindrance for any cause whatsoever
. . . and agrees that the sole right and remedy
therefor shall be an extension of time.General
Conditions, Article 16-G (emphasis added). And
Article 3.4 of the subcontract provides, in part
All loss or damage arising from any of the Work
through unforeseen or unusual obstructions,
difficulties or delays which may be encountered
in the prosecution of same or through the action
of the elements shall be borne by the
Subcontractor.
3CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Against this contractual backdrop, Trinity
requested a jury instruction that it could
recover damages under paragraph 53 for costs
associated with delays caused by others. The
trial court denied the request and instructed the
jury that Trinity's "claim for damages on account
of delays allegedly caused by Morse/Diesel and
its subcontractors" was an "area of ambiguity" in
the subcontract, citing Article 16-G of the
General Conditions and Article 3.4 of the
subcontract. She then noted Trinity's contention
that these two provisions have been negated by
paragraph 53. In the face of such apparent
ambiguity, Judge Preska instructed that it was
the jury's job to interpret the allegedly
ambiguous subcontract. - The Court of Appeals for the Second Circuit held
the jury instructions to be fatally flawed
because the subcontract contained no ambiguity.
The Court initially noted that under New York
law, a written contract is to be interpreted so
as to give effect to the intention of the parties
as expressed in the unequivocal language of the
subcontract. It then found that the
"notwithstanding" clause of paragraph 53 relieved
any tension among the three contract provisions
addressing delay. More specifically, the court
held that paragraph 53 overrode the otherwise
inconsistent clauses of Article 3.4 and Article
16-G of the General Conditions.
4CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Accordingly, the Court held that the district
court erred when it submitted the contract's
meaning on this point to the jury. The district
court should have construed the contract
according to its unambiguous terms, and clearly
instructed the jury that Trinity had the right
under paragraph 53 to recover any costs
occasioned by delays that were not its own fault. - Moreover, the Court proceeded to hold that the
error could not be deemed harmless. The jury
returned a general verdict. While the jury
apparently concluded that Trinity was at fault
for much of the delay and resulting acceleration
damages, Morse/Diesel did not recover all that it
sought. Thus, the Court found it very possible
that the jury believed Morse/Diesel was indeed to
blame for some of the delay. Finding it
impossible to isolate the counterclaim for
retrial, the Court found it necessary to reverse
the judgment in total and to remand both the
complaint and the counterclaim for retrial.
5CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Rights and obligations associated with delays
arise from the implied obligation in every
contract that each party will not delay, hinder
or interfere with the performance of the other
party. Or, more commonly the contract contains
an explicit obligation to perform by a given date
or within a specified time frame.
6CNS 3153Legal Issues In ConstructionChapter 8
Delays
- time is of the essence contractual clause
that makes time a component of the contractors
performance obligation. - Substantial Completion the work is sufficiently
complete so that the owner may occupy or utilize
the facility for its intended use. An owner may
not assess l.d.s after substantial completion.
7CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Nonexcusable Delays
- A delay that could have been anticipated or
avoided. The party that causes a nonexcusable
delay usually creates an excusable delay for the
other party. - Excusable Delays
- Generally, when an unanticipated outside force
delays completion. - Design problems
- Differing site conditions
- Unusually adverse weather
- Acts of God
8CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Compensable Delay the contractor is entitled to
both time and monetary damages. - Defective drawings or specs.
- Failure to provide access
- Improper site prep.
- Failure to supply materials or labor
- Failure to approve shop drawings
- Failure to coordinate prime contractors
- Failure to give timely orders for work
9CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Compensable Delays contd.
- Failure to make timely payments
- Failure to inspect
- Suspensions
- Excessive change orders
- Failure to accept completed work
- Acceleration
- Can a contractor recover damages for delays even
if they finished the project before the contract
completion date?
10CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Noncompensable Delay the contractor is entitled
to a time extension only. - Unusually severe weather
- Acts of God
- Labor problems
11CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Concurrent Delay
- When an excusable compensable delay and an
unexcusable delay occur at the same time or
overlap in time. - The current trend is to use CPM analysis to
evaluate the delays and apportion damages
accordingly.
12CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Written Notice the contractor who gives prompt
written notice of delays increases their
opportunity to recover damages. - Time extensions are almost always granted for
excusable delays. - Recovery of additional costs may be limited by a
no-damages-for-delay clause.
13CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Exceptions To no-damage-for-delay
- The delay was not contemplated by the clause in
the contract (some clauses explicitly list delays
that fall under the n-d-f-d clause). - The delay resulted in an abandonment of the
contract. - The delay was due to fraud, bad faith or an
arbitrary action. - The delay was due to the owner interfering with
the contractors work. - The delay was unreasonable.
- The contractors work was hindered by the owner
(hindered vs. actively interfered)
14CNS 3153Legal Issues In ConstructionChapter 8
Delays
- What costs can the contractor recover?
- Liquidated damages
- Labor inefficiency
- Equipment inefficiency
- Acceleration and overtime
- Extended field overhead
- Home office overhead
- Escalated material and labor costs
- Legal fees
- Interest
- Loss of profits
- Loss of bonding capacity
15CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Owner Damages
- Most often owner damages are fixed in the
contract as liquidated damages. - If the liquidated damages do not reasonably
approximate foreseeable actual damages, but
appear to act as a penalty, the provision will
likely be unenforceable. Under such
circumstances, the owner will have to prove their
actual damages in order to recover. - Can liquidated damages work in favor of the
contractor?
16CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Delay Claims Analysis
- Detailed documentation is essential to recovering
the maximum amount possible. - Proper scheduling techniques are imperative in
evaluating delay impacts. - Seek expert advice if necessary.
17CNS 3153Legal Issues In ConstructionChapter 8
Delays
- Kingston Constructors, Inc. v. Washington
Metropolitan Area Transit Auhority,1996 U.S.
Dist. LEXIS 8427 (D.D.C. June 6, 1996). - The defendant Washington Metropolitan Area
Transit Authority ("WMATA") contracted with
plaintiff Kingston Contractors, Inc. ("Kingston")
to remove and destroy existing electrical
transformers in WMATA's rapid transit rail
system, and procure and install replacement
transformers. The contract contained a liquidated
damages provision which provided for 1000 for
each calendar day of delay beyond a specified
completion date. - Kingston subcontracted the manufacturing of the
transformers to Power Energy Industries ("PEI").
Contractually required pre-installation testing
of the manufactured units revealed that they
contained misplaced insulation which caused a
short circuit defect. In addition, when the first
unit was installed, it functioned for only a few
minutes before failing and releasing a cloud of
smoke. - In an attempt to assure that the transformers
would still be capable of performing as required,
the parties then subjected the transformers to
additional tests, beyond those required in the
contract. Six out of 11 transformers failed these
tests. WMATA also rejected another solution
proposed by Kingston, because WMATA thought that
the proposed solution might compromise the
structural integrity of the transformers and
shorten their useful lives.
18CNS 3153Legal Issues In ConstructionChapter 8
Delays
- When two transformers failed another round of
tests, WMATA rejected the entire lot of 22
transformers that had already been manufactured,
stating that it had completely lost confidence in
the ability of the PEI transformers to function
as required. Kingston was forced to reprocure the
transformers, at substantial additional cost.
Also because of the reprocurement, Kingston was
unable to finish on time and, as a result,
incurred liquidated damages costs. - Kingston asked the Board to grant it a time
extension and an equitable adjustment in the
amount of the contract. The Board granted an
equitable adjustment for costs and delays
associated with the additional extra-contractual
testing, and reduced the amount of liquidated
damages from 1000 per day to 500 per day.
Kingston then appealed to the district court,
challenging, inter alia, the Board's decision to
reduce the liquidated damages. Kingston claimed
that the Board's only alternative was to declare
the clause unenforceable.
19CNS 3153Legal Issues In ConstructionChapter 8
Delays
- The Board had found that, in determining the
1000 liquidated damages figure, WMATA had
included a 500 contingency for the possible
assessment of Environmental Protection Agency
penalties associated with the work, even though
WMATA already knew that the EPA was not going to
assess such penalties. Citing the general rule
that a liquidated damages provision which is an
unreasonable approximation of damages must be
stricken as an unenforceable penalty, the
district court agreed with Kingston that WMATA
had acted unreasonably in setting the liquidated
damages amount, and that the Board had erred in
reducing the liquidated damages amount rather
than striking the clause altogether. - The court disagreed, however, with Kingston's
assertion that striking the damages clause was
the only course of action open to the Board.
Rather, the court held that actual damages should
be awarded instead of liquidated damages, and it
remanded the case for a determination of the
amount of such damages. The case may have been a
Pyrrhic victory for Kingston, since WMATA claimed
that its actual damages were more than 1000 per
day.
20CNS 3153Legal Issues In ConstructionChapter 8
Delays
- The court disagreed, however, with Kingston's
assertion that striking the damages clause was
the only course of action open to the Board.
Rather, the court held that actual damages should
be awarded instead of liquidated damages, and it
remanded the case for a determination of the
amount of such damages. The case may have been a
Pyrrhic victory for Kingston, since WMATA claimed
that its actual damages were more than 1000 per
day.
21CNS 3153Legal Issues In ConstructionChapter 8
Delays
22CNS 3153Legal Issues In ConstructionChapter 8
Delays