Title: Wigton Windfarm Ltd.
1Wigton Windfarm Ltd.
- Power Factor and VAR Control Experience
- -Problems and Solutions
- Presented by Francois A. Lee, PE
- Leecorp Ltd ,Wigton consultant
2Background
- Wigton Windfarm started operations in April 2004
- Connected to JPS grid under the terms of the
Power Interchange Agreement (PIA) - Main Project Manager/ Design Engineer/
Contractor RES Ltd. UK - 23 Neg-Micon NM900/52 900KW turbines installed
- Total estimated capacity of wind farm 20.7MW
3Wigton single line Summary
4System description summary
- 23 x NEG Micon NM/52 wind Turbines ,each
turbine generates at 690V,50 hz, and is
transformed up to 24KV by 1000KVA step up
transformers at the base of each turbine. - Turbines located 100M apart are connected to a
common collection point at the substation.The24
KV collection is further transformed up to 69 KV.
5- The point of interconnction with the local
utility (JPS) is at the terminals of the windfarm
power transformer 69KV disconnect switch. - The windfarm main substation is connected to
JPScos substation rated 139/69 KV at Spur Tree
via 11.315 KM of newly built 69 KV overhead lines
6Problems
- Metered MVAR demand indicates significant
consumption by the wind plant up to 8 MVAR.(see
P/Q characteristic) - JPSCO charges for MVAR demand at a rate
equivalent to its industrial customers.
7(No Transcript)
8(No Transcript)
9Solutions
- Consultants hired to look at scenario and
determine strategy for way forward Nov.2004. - Consultants Findings
- - Power Interchange agreements mandates
- Wigton Winfarm must be atleast .9PF
- and simulatenously providing its
- reactive power requirements.
10Consultants Findings contd.
- At 20 MW output there is a shortfall of aprox.
7.8 MVAR inductive -
- Neg-Micon turbines installed are inductive types
and consume 275 KVAr _at_ no load,410 KVAR _at_ full
load. - Neg-Micon turbines installed have capacitive
compensation up to 275 KVAR only. -
11Consultants Findings contd.
- Cabling and transformers add to reactive demand
- Balance of Plant contractor has mandate to
deliver facility that fulfills PIA. - The utilities charge to Wigton for Var support is
in line with PIA - Capacitive compensation of aprox. 8 MVAR is
required at Wigton - Automatically switched banks at the 24 KV
substation point is the likely and cost effective
solution.
12Implementation of solution
- QVARX Canada,specialists at Var compensation at
medium and high voltage - identified as substation Capacitor bank system
designer /supplier - Preliminary harmonic data indicates that tuning
reactors will be required. - Preliminary design done ,meetings convened with
JPS,Wigton ,consultants and design discussed as
per PIA procedures. - QVARX commisioned to and undertakes design and
system study for 24 KV capacitor bank
13System and 24 KV Capacitor Study Highlights
- Study Objectives
- 1- Determine the min. no of switched
- steps and suitable control strategy.
- 2- Determine if harmonic tuning reactors
- are required to avoid harmonic
- resonance problems.
- 3- Examine the potential for switching impact
on - the LV banks when switching in a 24 KV
- capacitor step.
14Study Results and Findings
- A capacitor bank of rating 8 MVAR total is
required to compensate /offset the maximum var
demand of 7.8 MVAR inductive.The capacitor bank
should be split into 3 identical steps of 2.67
MVAR,in order to keep the voltage steps following
bank switching to less than 3 at the 24KV bus.
15Study Results and Findings contd.
- The step 1 bank should remain connected at all
times ,which will be more stable operation when
the wind is very low and as it picks up.This is
because at low wind speeds ,the var demand is
rapidly changing between capacitive and
inductive.The steps 2 and 3 will be switched in
and out as the var demand at the metering point
will vary.It is recommended to control these 2
steps in the capacitor PLC which will allow the
most rapid switching times as opposed to the
standard PF controller. This will keep the
average inductive kvar as low as possible in the
event of sudden wind gusts.
16Study Results and Findings contd.
- The step 3 capacitor will require tuning reactors
to avoid resonance problems with the typical grid
harmonic distortion. The step 1 will be a
combination of 2 tuned banks .One tuned at the
5th harmonic and one tuned at the 7th harmonic.
This bank will be permanently connected. The
steps 2 and 3 banks will each be tuned at the 7th
harmonic.
17Study Results and Findings contd.
- The switching transient modeled results do not
indicate there will be any problems of
interaction on the LV capacitor banks at the
turbines when a 24 KV step is switched on. - The control of all low voltage caps (at turbines)
should be such that they should all be connected
as the MW increases ,and should remain connected
as the 2nd and 3rd steps come on to avoid
fighting between the both capacitor systems.
18Design Study approaches
- Impedance modelling done on 69/24 KV network
using ATPDRAW power simualtion software - Modelling basis
- - 24 kv cables are installed trefoil
- arrangement,direct buried,ground
- resistivity 36 ohm-m assumed
- - cables modeled as series R,L and parallel C
- to ground
- - Cables are modelled as lumped impedances per
identified branch - between two nodes,each node being a junction
box. - -Cable splices are not considered nodes in the
model as the distributed effect of cable
inductance and capacitance over the section does
not have a noticeable impact on the lower order
parallel resonance ,which is the key frequency of
interest. -
19Design Study approaches
- Transformers
- - 69/24 KV, 25 MVA rating,this transformer has
a nameplate impedance of 9.09 at 25 MVA. Load
losses is assumed to be 83 KW at 25 MVA - - 24KV/690V,1000 KVA rating,the turbine
transformer has a nameplate impedance of 5.73 at
1.0MVA. - Turbine Impedance
- - The turbine at 690V is modelled as the
stator subtransient reactance which is assumed at
20. - -Each turbine has LV capacitor bank of 275
KVAR,which is assumed to be fully connected.
20Design Study approaches
- Grid Connection
- - The windfarm is connected to the 69KV grid
via a 25MVA step up transfomer.The 69 KV has a
3phase fault level of between 487 t0 544 MVA with
x/r ratio of 4.8.There are no capacitor banks
directly on the 69 KV network. There is one main
breaker controlling all collector circuits at 24
KV.See appendix 1 for impedance diagram of 69/24
KV network.
21(No Transcript)
22(No Transcript)
23Design Study aproaches
- Total capacitor KVAR size
- - Load flow model without substation
capacitors shows apparent load at 24 KV of 20.8
MW and 6.1 MVAr inductive - - Load flow done with 8 Mvar capacitor bank
shows correction of max.demand vars to 0.3 Mvar
capacitive.
24Design Study aproaches
- Minimum Switch ON Time Delay
- - Capacitors must be discharged via internal
resistors before re-energizing and also
consideration made for rapid wind gusts which
would tend to drive up MVAr demand rapidly hence
minimum switch on time is critical - Mode of switching control
- - 3 options available 1st is basic control
device of PFC which works on separate time delay
setpoints,2nd option is var control within the
capacitor system PLC (programable logic
controller) .This option also has fixed time
delay setpoints for switching on and switching
off however PLC can determine whether it is
necessary to enforce time delays.3rd option is 3
steps connected permanently which is mot
advisable due to voltage increase at low output. - 2nd option of Var control in the PLC chosen .In
this mode the PLC controller will switch off a
step when it detects the load is decreasing and
the metered var is capacitive and exceeds the
MVAr size of one step (2.67 MVAr). As such the
reactive power at the metering point will be
controlled aproximately in he range of 0 vars to
2700 Capacitive ,averaged over 15 min intervals
with the rare possibility of inductive vars up to
2 MVar.
25Design Study aproaches
- Harmonic and transient Analyses
- -The system is modelled in the EMPT
(Electro-Magnetic Transients Program)computer
simulator program.This programme is used to model
the harmonic impedances ,currents and voltages of
electric power systems. - Between Jan 31- Feb.1,2005 recordings were made
at the 24 KV bus,the dominant harmonics were the
5th and the 7th.Voltage distortion at 24 KV is in
the order 2.5 to 3.5 which is acceptable. - Ratings of the Capacitors and tuning reactors
- -The ratings of the capcitor and tuning
reactor components need to be such that the
equipment will withstand the max.level of
harmonic currents as well as fundamental voltage
magnitude without overloading.Measurements on
site of harmonic conditions were used as input
for calcualtions of the required harmonic duties
and equipment ratings.See the single line idagram
of the bank step configurations in the following
slide.
26(No Transcript)
27Final Design and equipment selection
28(No Transcript)
29(No Transcript)
30(No Transcript)
31(No Transcript)
32(No Transcript)
33(No Transcript)
34(No Transcript)
35(No Transcript)
36Site Design and construction phase-Contract
awarded Feb.05-Contract completed
Aug.05-Contractors-QVARX,LEECORP
37(No Transcript)
38(No Transcript)
39Plant Performance data aftercapacitor project
40Performance of compensation system
- Var imports now in the order of 200KVar peak per
mth at peak (20 MW) output - Minimal downtime experienced
- Negligible payments to JPS