Title: LAND REFORMS DIVISION
1(No Transcript)
2 A PRESENTATION on DEPARTMENT OF LAND
RESOURCES
3Department of Land Resources(DoLR) Evolution
- 1985 - Creation of the National Wastelands
- Development Board (NWDB) under
the Ministry of Environment Forests
- 1992 - Setting up of the Department of
Wastelands Development (DoWD)
under the Ministry of Rural Development - Transfer of NWDB to DoWD
4Department of Land Resources(DoLR) Evolution
(contd.)
- 1999 - The Department renamed as the
Department - of Land Resources ( DoLR )
-
-
- - Land Reforms Division of MoRD
- transferred to DoLR
- - The following Area Development Programmes
were brought under DoLR - Drought Prone Areas Programme (DPAP)
- Desert Development Programme (DDP)
5Wastelands Development Programmes
- Drought Prone Areas Programme (DPAP)
- Desert Development Programme (DDP)
- Integrated Wastelands Development Programme
(IWDP) - Technology Development, Extension Training
(TDET)
6WASTELANDS ATLAS OF INDIA
- A study on the "Identification of Wastelands in
India" was commissioned by DoLR in collaboration
with the National Remote Sensing Agency (NRSA),
Hyderabad. - The Wastelands Atlas of India (WAI) was released
by the Prime Minister on 22.05.2000. -
- WAI contains maps on a 150,000 scale for
different categories of wastelands in the
districts.
7EXTENT OF WASTELANDS IN INDIA
8WATERSHED DEVELOPMENT PROGRAMMES
- The Hanumantha Rao Committee (1994) recommended
Watershed Approach for implementation of DPAP,
DDP and IWDP - The common Guidelines for implementation of DPAP,
DDP and IWDP were formulated and made effective
from 1.4.1995 - The Committee also identified Blocks based on
scientific parameters for DPAP DDP. - The common Guidelines were revised in 2001 to
infuse greater degree of flexibility and
transparency in implementation and to provide for
effective role to PRIs.
9NEW INITIATIVE HARIYALI
- Following the 73rd 74th Amendment to the
Constitution, the PRIs have been mandated with an
enlarged role in the implementation of
developmental programmes at grass-roots level. - The Guidelines for Watershed Development (2001)
did not provide for a pivotal role to the PRIs. - The new initiative Hariyali is a major step
towards this direction. -
contd/
10NEW INITIATIVE HARIYALI (contd)
- The institutional framework of Watershed
Associations (WA) and Watershed Committees (WC)
were perceived as parallel bodies, with very
little co-ordination between them and the Gram
Sabhas/Gram Panchayats. - To eliminate this plurality/lack of
co-ordination, implementation under Hariyali has
been entrusted to GP and GS in place of WC and WA
respectively.
11NEW INITIATIVE HARIYALI (contd)
- The Hariyali Guidelines suggest that preference
should be given to PRIs for appointment as PIAs.
Failing this a suitable govt. department may be
appointed. Only if both these options are not
possible, ZPs/DRDAs should consider appointing a
reputed NGO. - There are representations from some NGOs that
their role has been diminished in the Hariyali
Guidelines.
12OBJECTIVES OF WATERSHED PROJECTS
- RAISING GROUND-WATER TABLE
- IMPROVING PRODUCTIVITY OF DEGRADED /
WASTELANDS - PREVENTING LAND DEGRADATION
- CONSERVING ECO-FRAGILE LANDS
- INCREASING FUEL, FOOD FODDER
- IMPROVING RURAL ECONOMY
13Activities Undertaken in Watershed Projects
- Land Development including in-situ soil and
moisture conservation measures like contour and
graded bunds fortified by vegetation, bench
terracing in hilly terrain. - Drainage line treatment with a combination of
vegetative and engineering structures. - Development of small water harvesting structures
such as low-cost farm ponds, check-dams and
percolation tanks. - Nursery raising for fodder, timber, fuel wood and
horticultural species.
14Activities undertaken in Watershed Projects
(contd)
- Afforestation including block plantations,
shelter belts, sand dune stabilisation, etc. - Agro-forestry and horticultural development.
- Pasture development either by itself or in
conjunction with plantations. - Setting up revolving fund not exceeding Rs.1 lakh
to be given as seed money to SHGs at a rate not
exceeding Rs.10,000 per SHG for undertaking
income generating activities.
15COVERAGE
- DPAP covers 74.59 mha in 972 Blocks of 182
Districts in 16 States - AP (94) Bihar (30)
- Chhatisgarh (29) Gujarat (67)
- HP (10) Jharkhand (100)
- JK (22) Karnataka (81)
- MP (105) Maharashtra (149)
- Orissa (47) Rajasthan (32)
- Tamil Nadu (80) UP (60)
- Uttaranchal (30) West Bengal (36)
-
-
contd/
16COVERAGE (contd)
- DDP covers 45.79 mha in 235 Blocks of 40
Districts in 7 States - AP (16) Gujarat (52)
- Haryana (44) HP (3)
- JK (12) Karnataka (22)
- Rajasthan (86)
- IWDP covers generally non-DPAP and non-DDP
Blocks. Projects under implementation in 374
Districts.
17Budget (Rs. in Crores)
Proposed
18FUNDING PATTERN
- A cost norm of Rs 6000 per ha is adopted since
1.04.2000. - A watershed of about 500 ha is normally selected
for each project under DPAP and DDP. - DPAP 75 Central Share
- 25 State Share
- DDP 75 Central Share
- 25 State Share
- IWDP 91.66 Central Share
- 8.34 State Share
19PRESENT STATUS OF IWDP
- Since April 1995 till March 2004, 662 (190)
projects for treatment of an area of 50.78 lakh
ha. have been sanctioned. - Hariyali projects
20(No Transcript)
21PROGRESS OF IWDP
22PROGRESS OF IWDP (contd)
23PROGRESS OF IWDP (contd)
24PRESENT STATUS OF DPAP
- Since April 1995 till March 2004, 18803 (2535)
projects for treatment of an area of 94.01 lakh
ha. have been sanctioned. - Hariyali projects
25(No Transcript)
26PROGRESS OF DPAP
27PROGRESS OF DPAP (contd)
28PRESENT STATUS OF DDP
-
- Since April 1995 till March 2004, 9876 (1562)
projects for treatment of an area of 49.38 lakh
ha. have been sanctioned. - Hariyali projects
29(No Transcript)
30PROGRESS OF DDP
31MONITORING MECHANISM FOR IWDP/DPAP/DDP
- A three-tier system of monitoring of projects
adopted - At the Central level, periodic reviews by
Secretary (RD), Programme Divisions and Area
Officers. - At the State level, State Watershed Development
Committee reviews and monitors the programmes. - At District level, Project performance is
monitored by DRDAs/ZPs in co-ordination with the
State Watershed Development Committee. - Monitoring is also done through social audit by
local stakeholders and also by vigilance
committees.
32EVALUATION MECHANISM FOR IWDP/DPAP/DDP
- Mid-term and Final Evaluation of Projects are
conducted by States. - Specific Impact Assessment Studies of completed
projects are conducted by Centre. - Supplementary Observation Mechanism through
District/State Level Institutions is used for
quick feedback on project status. - Evaluation is done by Agencies like Independent
Institutions / Individuals. - Quick Intensive Evaluation of certain Watershed
Projects is undertaken.
33IMPACT ASSESSMENT STUDIES
- MAJOR FINDINGS
- Improvement in ground water level, cultivated
area and productivity of Land - Decrease in soil erosion, runoff loss and silting
of ponds, tanks and dams - Increase in availability of fuel-wood, fodder,
milk production and employment - Improvement in overall socio-economic status of
rural people living in/around watershed areas
34SUCCESS STORIES
- IWDP Project in Kurnool District of Andhra
Pradesh - Project period 1995-96 to 2000-01
- Area Cost 7330 ha. Rs.2.93 crores
- Location Peapully Mandal (13 Micro-watersheds)
in Kurnool District. - Activities
- 65 SHGs and 91 UGs formed in 13 micro-watersheds
- Soil and moisture conservation works
- Water harvesting structures
- Plantations horticulture
- Impact
- The dried wells in the area rejuvenated
- The old and abandoned water supply system
recharged - The drinking water situation markedly improved
- Revolving fund supported the poor families in
establishing own business - Women thrift groups formed and self employment
activities promoted.
35SUCCESS STORIES (Contd.)
- DPAP Project in Khandwa District of Madhya
Pradesh - Project period 1995-96 to 2000-01
- Area 823 ha.
- Location Dantha Village in Khandwa District
- Activities
- Total water management approach adopted through
ridge to valley treatment - A series of drainage-line earthen checks and
continuous contour trenches, field bandhs and
kundis were made which do not allow water to flow
more than 10m. Even if there is a rainfall of
20cm in a day. - Impact
- All the 46 existing dugwells had water throughout
the year and 102 new dugwells were constructed. - The water table rose by 40-60 feet providing
enough water for rabi crop - The water availability in the village increased
from 12.5 hect-metre to 305 hect-metre. - The cultivable area gone up from 300 ha. to 421
ha. and the productivity from 16-17 quintals to
30-35 quintals per ha. - The no. of milch cattle increased by 100.
36ISSUES OF CONCERN
- Delay in execution
- Delay in submission of release proposals
- Maintenance of assets
- Mid-Term Evaluation and Post project Evaluation
37RECENT INITIATIVES
- The Pradhan Mantri Grameen Jal Samvardhan Yojana
(PMGJSY) was announced on 15th August 2002 for
augmentation of water resources in DPAP and DDP
areas . - A mission for development of Bio-fuel has been
launched. The Detailed Project Report (DPR) is
being prepared. - Maru Gaucher Yojana initiated during 2003-04
for the development of traditional pasture (orans
and gauchars) in 10 desert Districts of Western
Rajasthan. Now transferred to Department of
Expenditure. - A Task Force on Integrated Development of Desert
Areas is proposed to be constituted by Department
of Economic Affairs, Ministry of Finance with
DoLR as Nodal Department.
38RECENT INITIATIVES (Contd.)
- Setting up of a Watershed Mission
- The Mohan Dharia Committee (1994) suggested that
all land Development Programmes implemented by
various departments be coordinated. - President, in his address to the Houses of
Parliament on 23rd February 2000, indicated that
these programmes should be under the control of a
single Deptt. i.e. DoLR. - The Standing Committee on Urban and Rural
Development also recommended that programmes
relating to watershed and wastelands development
should be brought under one umbrella. - A Cabinet Note in this regard is lying with the
Cabinet Secretariat since 1st October 2003
39COMPONENTS OF LAND REFORMS
- Abolition of intermediary tenures
- Tenancy Reforms
- Ceiling on ownership of Agricultural Holdings
- Distribution of Ceiling Surplus Land/Government
Wastelands/Bhoodan Land - Prevention of Alienation and Restoration of
Alienated Tribal Land
40ACHIEVEMENTS IN THE FIELD OF LAND REFORMS
- Intermediaries abolished on 150 lakhs acres of
land and ownership rights have been granted to
200 lakh tillers. - 124.22 lakh tenants rights protected over 156.30
lakhs acres of land. - An area of 52.93 lakh acres of ceiling surplus
land distributed to 56.73 lakh rural poor,
51 of which constitute SC/ST beneficiaries.
41ACHIEVEMENTS IN THE FIELD OF LAND REFORMS
(Contd..)
- An area of 147.47 lakh acres of Government
wastelands and 21.75 lakh acres of Bhoodan land
distributed among eligible rural poor - 4.47 lakh acres of alienated land restored to
Scheduled Tribe land owners. - An area of 1633.47 lakh acres have been
consolidated in the country. - 582 districts have been covered under the scheme
of Computerisation of Land Records and it has
been extended to 3142 taluks/tehsils/blocks in
the country.
42COMPUTERISATION OF LAND RECORDS (CLR)
- The Scheme of computerisation of land records
(CLR) was started in 1988-89. - This is a 100 funded scheme being executed by
the State Governments.
43OBJECTIVES
- To provide computerized copies of the Record of
Rights(ROR) other land related information to
the Land owners on demand. - To ensure accuracy, transparency, durable
preservation and speedy dispute resolution. - To facilitate fast and efficient retrieval of
information for decision making. - Focus on effective public delivery of e-services
from the computer centre to implement
e-governance at grass root level.
44COVERAGE UNDER THE SCHEME
- Scheme started during 1988-89 in 8 pilot
districts. - The initial data entry work was carried at
district level. - So far, 582 districts have been covered.
- In 1997-98, the scheme was extended to
Tehsil/Taluk/Block level. - So far, 3142 taluks and 201 sub-divisions have
been covered.
45PRESENT STATUS
- Computerisation of Land Records Project has been
sanctioned in 582 Districts 3142
Tehsils/Taluks/Blocks and 201 Sub-Divisions of
the country. - In 2172 tehsils, computer centres have been set
up and in 1553 tehsils wherein computerized
copies of ROR are being issued to the landowners. - Since inception Rs.300.51 crores has been
released to the States / Union Territories out of
which, Rs.203.01 crores has been utilized so far.
46BHOOMI PROJECT OF KARNATAKA - HIGHLIGHTS
- Facility to Finger print biometrics
authentication to ensure fool proof
authentication system and to enforce the concept
of non-repudiation. - Scan the field mutation order passed by revenue
authorities and the notice served on the public. - Land Records Centre in each taluk office for
public interface. - Synchronizes with the regular fieldwork done by
Village Accountants and Revenue Inspectors. - Provision for interfacing of Touch Screen Kiosks
at taluk office. - Fully online system to carry out mutations on
land records data.
47STRENGTHENING OF REVENUE ADMINISTRATION
UPDATING OF LAND RECORDS
- The scheme was started in 1987-88 with 5050 fund
sharing basis between Centre and the States with
a view to improve the land records and creating
infrastructural facilities to Revenue and Survey
Settlement Department to improve their
efficiency. - Under the scheme, funds are provided for
strengthening of existing infrastructural
facilities and setting up of new survey and
settlement training institutions. - So far Rs. 265.97 crore have been released to
States as Central share out of which Rs. 170
crore have been utilized upto 31st March, 2004.
48LAND ACQUISITION (AMENDMENT) BILL, 2004
- The basic objectives of the LA (Amendment) Bill
are as follows - To simplify and streamline the existing procedure
- Speedy acquisition to avoid cost escalation.
- Liberal compensation.
- Ensure transparency.
- Finality of Award and reduce litigation.
- Transparency and accountability.
49LAND ACQUISITION (AMENDMENT) BILL, 2004 (Contd)
- The LA (Amendment) Bill, 2004 has been approved
by the Group of Ministers and vetted by the
Ministry of Law - Cabinet Note along with draft Bill was submitted
to Cabinet Secretariat on 23-01-2004 for its
consideration. - The Cabinet Secretariat has directed to circulate
the Bill to concerned Ministries and submit the
same after the formation of the 14th Lok Sabha.
50NATIONAL POLICY ON RESETTLEMENT REHABILITATION
- 2003
- The National Policy on Resettlement
Rehabilitation 2003 has been approved by the
Union Cabinet on 15-01-2004 and the same has been
published in the Gazette of India
(Extra-ordinary). - A copy of the Policy has been sent to Central
Ministries/Departments and States for its
implementation.
51Objectives of RR Policy
- Minimize displacement and identify
non-displacing or least displacing
alternatives in consultation with requiring
body. - Holding consultation with the Project Affected
Families (PAFs) while preparing RR
Plan/Scheme. - To ensure protection of the interest of PAFs of
STs and vulnerable sections. - It lays down minimum norms for RR Packages.
52APPLICABILITY/MONETARY BENEFIT OF RR Policy
- The Policy will be applicable to projects
displacing 500 families enmasse in plain areas
and 250 families or more in hilly areas, DDP
blocks, areas mentioned in Schedule V VI of the
Constitution of India. - The Policy would be in the form of broad
guidelines and executive instructions for
guidance of all concerned. - The RR grants and other benefits proposed under
the policy would be minimum and applicable to all
PAFs whether belonging to BPL or non-BPL (except
one-time house construction grant of Rs.25,000/-
only for BPL PAFs). - Tribal families resettled out of the
district/taluk will get higher RR benefits to
the extent of 25 in monetary terms. - There will be Monitoring and Review Committee at
the Project Level to monitor review the
progress of implementation of scheme/plan of RR.
53THANK YOU