Title: Real Options, Risk Governance, and Value-at-Risk (VAR)
1Real Options, Risk Governance, and Value-at-Risk
(VAR)
2What is a real option?
- Real options exist when managers can influence
the size and risk of a projects cash flows by
taking different actions during the projects
life in response to changing market conditions. - Alert managers always look for real options in
projects. - Smarter managers try to create real options.
3Introduction to Real Options
- Alternative, yet complementary, approach to
DCF-based Capital Budgeting. - Many corporate investments (especially
strategic ones) have embedded options. - Overlooking these options can lead to
- under-valuing investment projects.
- Using Real Options approach can improve project
management as well as valuations.
4Types of Real Options
- Abandonment
- Contraction
- Temporary suspension
- Permanent
- Switch / Transition
- Change Product Mix
- Change Input Mix
- Technical Obsolescence
- Wait / Timing
- Resolve Uncertainty
- Identify Demand
- Expansion
- Existing Products
- New Geographic Markets
- Growth
- New Products
- RD
5Four Procedures for Valuing Real Options
- 1.DCF analysis of expected cash flows, ignoring
the option. - 2.Qualitative assessment of the real options
value. - 3.Decision tree analysis.
- 4.Standard model for a corresponding financial
option.
6Analysis of a Real Option Example of a Basic
Project
- Initial cost 70 million, Cost of Capital
10, risk-free rate 6, cash flows occur for 3
years.
Demand Probability Annual cash flow
High 30 45
Average 40 30
Low 30 15
7Approach 1 DCF Analysis (ignoring option)
- E(CF) .3(45).4(30).3(15)
- 30.
- PV of expected CFs (30/1.1) (30/1.12)
(30/1/13) - 74.61 million.
- Expected NPV 74.61 - 70
- 4.61 million
8Procedure 2 Qualitative Assessment
- The value of any real option increases if
- the underlying project is very risky
- there is a long time before you must exercise the
option - This project is risky and has one year before we
must decide, so the option to wait is probably
valuable.
9Procedure 3 Decision Tree Analysis (Implement
only if demand is not low.)
10Projects Expected NPV if Wait
- E(NPV)
- 0.3(35.70)0.4(1.79) 0.3 (0)
- E(NPV) 11.42
11Procedure 4 Use the existing model of a
financial option.
- The option to wait resembles a financial call
option-- we get to buy the project for 70
million in one year if value of project in one
year is greater than 70 million. - This is like a call option with a strike price of
70 million and an expiration date of one year.
12Inputs to Black-Scholes Model for Option to Wait
- X strike price cost to implement project
70 million. - rRF risk-free rate 6.
- t time to maturity 1 year.
- S (or P) current stock price 67.82 see
following spreadsheet. - s2 variance of stock return 14.2 see
following spreadsheet.
13Discounted Cash Flow Valuation and Value-Based
Management
- Link to Real Options Valuation Excel file
- FM 12 Ch 13 Mini Case.xls (Brigham Ehrhardt
file)
14Relation between Financial Options Real Options
Corporate Project Variable Financial Call Option
Expenditures to acquire asset X Exercise Price
PV of acquired asset S Stock Price
Time that decision can be deferred t Time to Expiration
Riskiness of asset s2 Variance of Return
Time value of money r Risk-free Rate
15Calculating the NPV Quotient (NPVq)
- _____ NPVq lt 1.0________NPVq gt 1.0_____
- Negative NPV Positive NPV
- Calls Out-of-Money Calls In-the-Money
16Using Black-Scholes to Price a Real Option
- Identify 5 key Inputs to B-S OPM
- Initial Investment X 100
- Current Assets Worth S 90
- Assets Riskiness s 40
- Deferral Time 3 years
- Risk-free Rate 5
- Note that current NPV -10 but NPVq 1.04
- Using B-S OPM method, the Options worth
- .284 90 25.56 !!
- Above analysis shows that this might be a
promising project in the future (the option to
wait is valuable).
17Tomato Gardens Real Options
Cumul. Variance Out of the Money (NPVq lt 1.0) In the Money (NPVq gt 1.0)
Very Low Exercise Never Exercise Now
Low Doubtful NPVlt0 NPVqlt1 s2 is low. Wait if possible. Otherwise, exercise early.
High Less Promising NPV lt 0 and NPVq lt 1 but s2 is high. Very Promising NPV lt 0 but NPVq gt 1
18Real Option Implementation Issues
- Need to Simplify Complex Projects.
- Difficulties in Estimating Volatility (use
simulation, judgment, coefficient of variation) - Checking Model Validity (distributions, decision
trees). - Interpreting Results
- (sensitivity analysis is a must!)
19Overview of Risk Governance Issues
- Key Risk Management Responsibilities of Senior
Managers / Board Members - Board / Senior Management must approve firms
risk management policies and procedures. - Ensure that operating team has requisite
technical skills to execute the firms policies
and procedures. - Evaluate the performance of the risk management
activity on a periodic basis. - Maintain oversight of the risk management
activity (possibly with a board sub-committee).
20Ways to Measure Manage Risk
- Value-at-Risk (VAR) has become a popular summary
measure of risk. -
- VAR is most useful when measuring market-based
risks of financial companies (less meaningful for
many non-financial companies). - Precursors to VAR (and still in use)
- Maturity Gap
- Duration and the Value of a 1 basis point change
- Convexity plus Duration
- Option-based Measures (delta, gamma, vega).
21Why VAR has Become so Popular
- VAR provides a succinct, dollar-based summary
measure of risk which allows management to
aggregate risks. - Also, traditional risk measures had several
weaknesses - They could not be aggregated over different types
of risk factors/securities. - They do not measure capital at risk.
- They do not facilitate top-down control of risk
exposures. - VAR is easy for senior management to interpret
It measures the maximum dollar amount the firm
can lose over a specified time horizon at a
specified probability level (e.g., the 1-day VAR
with 99 confidence is 5M) - (See Spreadsheet)
22Calculating VAR (Three Methods)
- Can calculate VAR via two types of simulation
methods and one analytic method. - Historical Simulation
- Identify Factors affecting market values of
securities in the portfolio - Simulate future values of these Factors using
Historical Data - Use the simulated Factor values to estimate the
value of the portfolio several times (usually
1,000 or more times) - Create a histogram of the portfolios expected
change in value and identify the relevant
probability level for the VAR calculation (e.g.,
find the change in portfolio that occurs at the
lowest 1 of the distribution).
23Calculating VAR (cont.)
- Monte Carlo Simulation
- Follow the same steps as in the Historical
Simulation method except you use Monte Carlo
techniques to obtain the simulated Factor values
(step 2 of the previous slide). - Analytic Variance-Covariance Method
- Can be simpler to estimate since you dont need
the entire distribution of Factor values (summary
measures will suffice). - Specify Distributions and Payoff Profiles (e.g.,
normal and linear). - Decompose Securities into Simpler
Transactions/Buckets. - Estimate Variances/Covariances of Standard
Transactions - Calculate VAR based on standard definition of
variance.
24Strengths / Weaknesses of the Three VAR Methods
- Historical Simulation does not assume specific
distributions for the securities and uses
real-world data but it requires pricing models
for all instruments and allows limited
sensitivity analysis. - Monte Carlo Simulation makes it easier to do
sensitivity analysis but requires the analyst to
specify asset distributions as well as pricing
models (also, one step removed from real-world
prices). - Analytic Method is intuitively simpler and does
not require any pricing models but it is not
conducive to sensitivity analysis and cannot
handle non-linear payoff profiles such as options.
25Differences in VAR Estimates from the Three
Methods
- Empirical Tests to date, tests of the three
methods suggest that the approaches can yield
similar results when - Portfolio payoffs are linear.
- 95 confidence level is used.
- There are not many large outliers in the
historical data set. - Where Differences can Occur biggest differences
can occur between the 2 simulation approaches and
the analytic method when - Non-linear payoffs are a significant share of the
portfolio and they do not cancel out (e.g., long
a large number of put options). - Large number of outliers in the historical data
set. - 99 or higher confidence level is used.
26Choosing between the Methods
- As in much of life, It Depends!
- If the portfolio has linear (or weakly
non-linear) payoffs, then the Analytic method
might be best. - If the portfolio has strongly non-linear payoffs,
then the two Simulation methods are better. - If stress-testing and sensitivity analysis are
needed, then Monte Carlo Simulation is the
preferred method (however, it can be very complex
to remove all possible arbitrage opportunities
from the simulation).
27Who Should Use VAR?
- Firms that have their values determined primarily
by financial market risks should use VAR (e.g.,
Investment banks, Brokers/Dealers, as well as
CBs and Insurance Cos with active trading
portfolios). - Firms that have their values determined by growth
opportunities or growth options probably should
not use VAR as their primary risk measure - (e.g., high tech or bio tech firms).
- For firms with growth options, a VAR estimate is
typically not relevant because the real value of
these companies comes from non-traded assets
where no-arbitrage arguments typically do not
hold.
28Implementing VAR
- Parameter Selection
- Time Horizon (e.g., 1-day or 10-day VAR)
- Confidence Level (usually 95 or 99)
- Variance-Covariance Data (unstable correlations
vs. 1.0) - Other Important Issues
- Sensitivity Analysis (how sensitive is the VAR
estimate to the data set used in the analysis?) - Scenario Analysis (worst case vs. standard
case) - Stress-testing (how does VAR change as the above
parameters change?) - Back-testing (how good have past VAR estimates
been in relation to actual portfolio changes?)