Title: Open access challenges
1Open access challenges way forward
- S.K. Chatterjee
- Deputy Chief (RA),CERC
- 7th July, 2009
2In this presentation..
- Open Access Status
- Challenges in Implementation of Open Access
- Way Forward
3Open access Status
4Short term Inter-State Open Access
5Status of Open Access at Distribution Level
6Comparison of cost of power through Intra-State
Open Access and Distribution Utility -
Illustrative Cases for a typical 5MW at 11kv/33kv
consumer
7Comparison of cost of power through Intra-State
Open Access and Distribution Utility -
Illustrative Cases
Tariff for an embedded consumer of 5MW at 11 KV
(33 KV in some cases). Effective Open Access
Charges for consumer of 5MW at 11 KV (33 KV in
some cases) in addition with a assumption of
power purchase cost of 4 Rs./KwH.
8OPEN ACCESS CHARGES
- Transmission Charges
- Wheeling Charges
- Imbalance (UI) Charges
- Reactive Energy Charges
- Surcharge
- Interconnection Charges
- Operating Charges ( SLDC charges)
- Connectivity Charges..etc.
9STATUS OF OPEN ACCESS IN DISTRIBUTION(As on
31.05.2009)
- Total OA Applications received 193
- OA Capacity Applied for 18189.11 MW
- Total OA Applications approved 132.00 (68)
- OA Capacity Approved 15152.89 MW(83)
- OA Transaction Implemented 1626.29 MW (9)
10OPEN ACCESS Challenges AND way forward
11CHALLENGES IN OPEN ACCESS
- Segregation/Unbundling of transmission and
trading. - Independent functioning and capacity building of
SLDCs. - Issues of standby charges.
- Open Access Charges and Cross Subsidy Surcharge
- Adequate metering, billing, balancing and
settlement mechanism - Resistance of incumbent licensees / Role of SLDCs
- State Governments issuing orders under Sec 11
12WAY FORWARDIN Open Access
13SEGREGATION OF TRANSMISSION AND TRADING
ASSESSMENT OF PRESENT SITUATION
- EA 2003 debars transmission companies from
trading to - bring about neutrality in transmission business
and - make discoms responsible for planning and
procurement of power - SEBs have been reorganized in several States but
not in true spirit - TRANSCOs, divested of trading responsibilities
but another trading arm created to perpetuate
single buyer model. - In many States a holding company continues to
oversee the subsidiaries created for transmission
(controlling SLDCs) , distribution, trading etc. - The conflict of interest sought to be removed
through the provision of law continues to haunt
and frustrate efforts at non discriminatory Open
Access. - Major Role of State Govt. for overcoming these
constraints
Way Forward.
14INDEPENDENT FUNCTIONING OF SLDCs (FOR
Recommendations)
- SLDC not to report to transmission or trading
licensee. - Reporting requirements could be lines of
reporting pattern for State Electoral Officer
under Election Commission. - Operation of SLDC an appropriate reporting
system - in terms of administrative control and recording
of confidential remarks - with STU - as a subsidiary of transmission
utility as stop-gap arrangement - by a separate entity as soon as possible
- Urgent need of delegation of financial powers to
SLDCs . CERC to make regulations for RLDCs to
ensure recovery of not only operating and capital
servicing costs but also generation of adequate
surplus to provide equity for future investments.
Same to be adopted by SERCs for SLDCs. - State Governments be advised to phase out single
buyer model
Way Forward.
15CAPACITY BUILDING OF SLDCs (FOR
Recommendations)
- Requirement of deploying personnel with certain
pre-defined minimum qualifications and
certification of competence in Load Despatch
Centres to be incorporated in the Grid Code - A model scheme for technological upgradation of
SLDCs recommended. - Recommendations of the Committee constituted by
MoP regarding staffing pattern, organisation
structure and necessary incentives for attracting
qualified personnel in Load Despatch Centres,
endorsed.
Way Forward.
16STANDBY CHARGES (FOR Recommendations)
- Standby arrangement for open access consumers
- by levying retail tariff as applicable for
respective consumer categories only for the
period during which such standby support is
requested.. - No fixed demand charges should be levied on open
access consumer during the period when no standby
support is availed - The charges for Standby power support should
comprise only energy charge. - The demand charge for six weeks may be uniformly
spread across the year. - Beyond duration of six weeks, the open access
consumer will have to avail regular supply from
concerned distribution license
Way Forward.
17METERING, BILLING, BALANCING AND SETTLEMENT
MECHANISM (FOR Recommendations based on
internal TF report)
- All open access schedules must be specified in
MW (not in energy terms). - All open access customers should have meters
which record energy for each 15-minute time
block. - All Special Energy Meters for intra-State
entities should be installed by the State
Transmission Utility. - Uniform mechanism for settlement on lines of
inter-state scheme preferable. However, SERCs
may adopt alternative mechanisms.
Way Forward.
18CROSS SUBSIDY SURCHARGE (FOR Recommendations)
- The cross-subsidy surcharge needs to be
calculated as per the formula given in the Tariff
Policy unless there are valid reasons for
deviation. - Note Chhattisgarh ERC has adopted average cost
method by recording reasons as follows
Agricultural consumers and the BPL consumers in
the State are highly subsidized as compared to
the industrial and commercial consumers who are
cross-subsidizing them. The formula in the Tariff
Policy thus does not reflect the real position
and hence has not been adopted by the
Commission.
Way Forward.
19CERC Orders on Denial of Open Access
Way Forward.
20Case I
- In the matter of non approval of Open Access
communicated by Southern Regional Load Despatch
Centre on ground of non- receipt of consent from
SLDC-OPTCL for transmission of power generated by
Nava Bharat Ventures Ltd through M/s. Reliance
Energy Trading Ltd, to the distribution utilities
in Andhra Pradesh
- Commissions observations
- There is no transmission constraint or congestion
as accepted by Orissa State Load Despatch Centre. - The requirements of procuring and erecting PLCC
and other communication equipment have already
been complied with by the petitioner. - Neither Orissa Grid Code nor the Orissa State
Electricity Regulatory Commission orders put any
restriction in granting open access. - Commission did not find any justification for
denial of open access on the ground of lack of
facilities for real time monitoring.
Ruling
Commission directed that open access shall be
allowed as required by RETL since there are no
transmission constraints and surplus transmission
capacity is available on the intra-State
transmission system
Way Forward.
21Case II
- In the matter of petition for direction to RRVPNL
to pass order on concurrence as per the Central
Electricity Regulatory Commission (Open Access in
inter-State Transmission) Regulations, 2008.
Commissions Ruling
The Commission concluded that the objections on
the basis of which open access was denied were
not germane to the issue at hand and held that
action of RRVPNL was unfair and illegal. The
Commission observed that such action appeared to
be an attempt to create a situation whereby GFL
was forced to sell its output within the State,
which was against the intent and content of the
Electricity Act, 2003.
Taking a stern view of denial of open access by
Rajasthan SLDCs, CERC issued show cause notices
to Rajasthan SLDC and Rajasthan Rajya Vidyut
Prasaran Nigam Ltd. (RRVPNL) to explain why
action should not be initiated against them for
violating the CERCs regulations on open access
in inter-State transmission. The complaint was
filed by Gujarat Flurochemicals Ltd. (GFL), a
company that owns wind generation facility in the
Jaisalmer district of Rajasthan.
Way Forward.
22Case III
- M/s Viswanath Sugar Ltd. (VSL), M/s Ugar Sugar
Ltd. and M/s Shree Dhoodhaganga filed petition
their petitions stating that open access was not
granted by WRLDC.
VSL had executed a PPA initially with KPTCL to
supply power to HESCOM. As per PPA, in the event
of any payment default by HESCOM for a continuous
period of three months, VSL can sell power to
third parties. HESCOM has defaulted payment for
more than 3 months. Further, VSL entered into a
PPA Tata Power Trading Company Limited for sale
of 7.5 MW of power on round-the-clock basis and
for that Tata Power Trading sought open access
which was denied by KPTCL on ground of its
previous PPA with VSL.
Commissions Ruling
The Commission observed that as an independent
operator and statutory body under the Electricity
Act, 2003, SLDC should consider the applications
for open access in an impartial manner and in
line with provisions of Electricity Act, 2003 and
the open access regulations. Any denial of open
access on considerations other than those
prescribed under the law and taken note of in the
above analysis, will attract the penal provisions
of the Electricity Act, 2003.
Way Forward.
23State govt. orders under section 11 of EA 2003
Way Forward.
24Section 11 of Electricity Act
- 11. Directions to generating companies.-
- (1) The Appropriate Government may specify that
a generating company shall, in extraordinary
circumstances, operate and maintain any
generating station in accordance with the
directions of the Government. -
- Explanation.- For the purpose of this section,
the expression extraordinary circumstances mean
circumstances arising out of threat to security
of State, Public order or natural calamity or
such other circumstances arising in the public
order or natural calamity or such other
circumstances arising in the public interest. -
- (2) The Appropriate Commission may offset the
adverse financial impact of the directions
referred to in sub-section (1) on any generating
company in such manner as it considers
appropriate,
Way Forward.
25Orders under sec 11
- Karnataka and Tamil Nadu have issued orders under
Section 11 of the Act - requiring generators to sell power only within
the state at a specified rate and denying open
access - State of Karnataka has, in fact, passed generator
specific orders in terms of which they have
specified the price at which generators can sell
power to distribution utilities - The States of Andhra Pradesh, Rajasthan and
Maharashtra have also imposed restrictions on the
right to open access
Way Forward.
26Effects
- requiring private generators to compulsorily sell
power to state distribution utilities and not
other third parties - fixing the price at which power can be sold
through executive diktat - imposing restrictions on the right of third party
sale and - denial of open access.
Orders issued under Section 11 are subjudice
Way Forward.
27THANK you