WP9 : Cavity BPM spectrometry - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

WP9 : Cavity BPM spectrometry

Description:

Guaranteed funding only for FY07/08 ... Beam position jitter might ruin laserwire system measurements. 1 micron electron beam size ... – PowerPoint PPT presentation

Number of Views:42
Avg rating:3.0/5.0
Slides: 13
Provided by: hepM
Category:
Tags: bpm | cavity | ruin | spectrometry | wp9

less

Transcript and Presenter's Notes

Title: WP9 : Cavity BPM spectrometry


1
WP9 Cavity BPM spectrometry
  • Royal Holloway
  • S. Boogert G. Boorman
  • University College London
  • D. Attree, A. Lyapin, B. Maiheu M. Wing
  • Cambridge University
  • M. Slater, M. Thomson D. Ward

2
Politics and funding
  • Poorly funded by PPARC
  • Guaranteed funding only for FY07/08
  • Enough to complete main project objectives
    including hardware commitments
  • Keep all key staff
  • Beyond FY08
  • Start losing key staff
  • Lose ability to construct new devices such as
    BPMs
  • Overall can bring spectrometer work to a viable
    scientific conclusion end of 2008
  • Without additional funding in 2008
  • Focus more on existing ILC test systems such as
    ATF2
  • BPM work from machine optimisation point of view
    opposed to energy measurement

3
Future of ESA and ATF
  • Complete ESA WP4.2/9 cavity system
  • Currently one dipole and one monopole cavity
    constructed
  • Complete with electronics and digitisation
  • Calibration (2-axis mover system)
  • Complete whole system with 2 additional BPMs
  • Probably same design (manufacturing costs)
  • Triplet tests essential to determine performance
    of BPM design
  • Triplet best configuration for spectrometer tests
  • ATF1/2 program
  • Collaboration with SLAC/KEK has been very
    productive for UK groups.
  • Work on nanoBPM will be wound down
  • Continue some development on ATF2 cavity systems
  • UK leads in processing algorithms and analysis
  • UK in position to provide complete cavity signal
    possessing for ATF2

4
End station A
Old SLAC BPMs
LCABD BPMs
Dipole
  • Must complete energy spectrometer prototype
  • Electronics for one cavity completed
  • Prototype cavities (dipole and reference
    complete)
  • Also simulations well advanced
  • Must mine existing simulations developed within
    task 4.2
  • BDSIM/Geant4
  • Cavity and electronics simulation

5
Cavity construction
Dipole cavity
Reference cavity
  • RF Bench tests of the new cavities next few weeks
  • Beam tests at End Station A in July
  • Second iteration design might be required
  • Modifications might be possible (as more
    detectors are required)
  • Complete system (spectrometer triplet)
  • ATF2 laserwire jitter removal (see later)

6
ATF2 (Cavity BPMs)
C-band ATF2 cavity
  • ATF2 will have a large deployment of cavity BPMs
  • Basic design by A. Lyapin (modified by Y. Honda
    et al.)
  • Essential for ATF2 final focus optimisation
  • Groups relying on beam steering algorithms to
    obtain 35 nm focus spot size
  • Electronics and processing essentially same as
    nanoBPM
  • Must help convert knowledge of ATF-nanoBPM and
    ESA BPMs to normal operation of ATF2
  • ATF2-FF S-band cavities!

20 cavities 50 nm resolution Main beam
steering/alignment diagnostic
7
Turn key diagnostic
Cavity (2.8 GHz)
  • Cavity BPMs intended to be turn key diagnostics.
  • Requires a significant amount of processing
    (unlike button and strip-line BPMs)
  • Two possible methods for readout.
  • Mix to base-band
  • Automatic electronics control, phase etc.
  • Fixed processing scheme
  • Mix to 100 MHz and digitise
  • Further digital signal processing required
  • Very flexible (algorithms can be modified etc)
  • Can be fast

Mixer (IF 20MHz)
100MHz digitiser
I-Q. position/tilt
PC processing
8
RF electronics development
  • Development of printed circuit board mix down
    electronics essential
  • Reduces costs
  • RF component cost
  • Power distribution
  • Form factor
  • Stable solution once proven (less connectors,
    cables etc)
  • Less flexible for future modifications
  • Difficult to change filters/limiters etc
  • Not all components are simple ICs (couplers,
    limiters etc)

WP4.2 electronics
ATF2 electronics
9
Cavity signal processing
Multi-bunch data from nanoBPM
  • Many groups considering FPGA based processing
  • Well suited to the digital signal processing
    problem
  • Commercial options available
  • LBNL and FNAL have board designs
  • Problem is with the firmware/processing
  • Solution also being considered for HOM-BPMs
  • Also well suited for data reduction required for
    full train BPM analysis
  • Collaborations being formed to look at these
    solutions for BPM work

FNAL design VME, ADC/FPGA/DAC board
AO
FPGA
AI
10
Integration with laserwire systems
  • Beam position jitter might ruin laserwire system
    measurements
  • 1 micron electron beam size
  • Subtract beam jitter requires lt100nm resolution
  • Instrument one laserwire IP with two BPM systems.
  • Either side of laserwire systems
  • Existing S-band design quite applicable
  • Calibration and monitoring a problem
  • Triplet formed by laserwire (acts a little like a
    slow BPM)
  • Construct two for next phase of laserwire
    operations?

Existing SL-BPMs in ATF laserwire
Laserwire interaction point
11
Spectrometer simulation studies
  • Simulation work was neglected in favour of BPM
    development work in LCABD1
  • Simulation of BDS from linac exit to interaction
    region
  • Effect of background on spectrometer measurement
  • Beam halo
  • Energy loss due to Synchrotron radiation
  • Tools are complete
  • Geant4 for tracking in dipole field maps
  • BDSIM simulation of whole delivery
  • Must now get results from our tools

12
Summary
  • Limited funds from PPARC/JAI
  • Re-evaluate goals of WP9
  • Complete system at SLAC and operate with a full
    triplet system
  • Develop cheaper mixer electronics
  • Turn key operation of cavity systems
  • FPGA based processing/algorithms
  • Become more involved in ATF2 BPM systems
  • Complete ATF2 BPM system processing/control
  • Bring spectrometer work to a reasonable
    scientific conclusion over next three years
  • Could even reconsider renaming WP9 Cavity Beam
    Position monitors
  • More complete spectrometer tests impossible
    (dependent on funding)
  • Future of ESA facility might be in doubt
  • ATF2 work is important and a natural place for
    high precision BPM work
  • More generally must rely on existing
    cavity/calibration/electronics/processing systems
Write a Comment
User Comments (0)
About PowerShow.com