Title: ICBS Reengineering Project


1
ICBS Re-engineering Project
ICBS-R Update National Cache Managers Virtual
Meeting March 12, 2009
2
ICBS-R update
  • Key focus areas for this year
  • Implementation progress plans
  • Issues

3
Key focus areas
  • Emphasis is on rolling out the application to the
    remaining caches
  • Increase our capacity for user support
  • Phase 2 ROSS-ICBS interface work
  • FBMS enhancements to ICBS

4
Rolling out the application
  • Six caches are operational
  • Some of the remaining caches are more complex,
    and will need more prep work with team to make
    sure system works well for them. For example
  • Remote returns/refurb operations
  • Larger and more spread-out footprint

5
Rolling out the application (cont.)
  • FBMS is an issue for the BLM caches
  • Lack of FS or BLM network will be an issue for
    the Alaska State Cache (SFS)
  • Plan to bring in outside consultant for best
    approach (to connect their WLAN to NITC)
  • Plan to send SME Wireless Team reps to
    LaGrandes new facility
  • To design new WLAN
  • Consult with Howard on zones/locations

6
Increase capacity for support
  • Getting all team SMEs more proficient in the
    system
  • Training more Helpdesk personnel on ICBS
  • Two were at NCK during their go live week
  • Knowledge transfer from the Sterling Team to
    Helpdesk
  • Developing quick reference guides for users
  • Investigating software for remote scan gun
    upgrades, imaging and diagnostics

7
Phase 2 ROSS-ICBS interface work
  • Will encompass
  • Incidents, orders, issues, etc.
  • Resuming design/development work with ROSS Team
    this month
  • Testing and deployment this fall/winter
  • Deployment timing dependant on ICBS and ROSS
    schedules

8
FBMS enhancements to ICBS
  • Required for BLM caches to go live
  • Work will include
  • Changes to screens and reports
  • Interface with FBMS for file transfers
  • Preliminary design has been completed
  • Need BLM funding to begin development -
    hopefully in April

9
Implementation progress plans
  • Implementation Strategy
  • Pre-Implementation (1-5 days) Consultation
    phase-Sterling and Govt Team
  • Data Collection (2 weeks) Cache responsibility
  • Data load and test (3-4 days) Sterling
    responsibility with caches input
  • Training and Go-live (2 weeks) Govt and
    Sterling team

10
Issues
  • System Security Plan requirements
  • Annual security training on file for each user
  • Signed Rules of Behavior agreement for each user
  • Implement a scan gun checkout system
  • Change board
  • Working on agency Software Configuration Mgt.
    Plan
  • Once finalized, will enlist Steering Group to
    recruit members and launch the board

11
  • Questions?

12