Title: REGULATORY ASSET BASE VALUATION USING ODRC Meralco Experience
1REGULATORY ASSET BASE VALUATION USING ODRC
Meralco Experience
2Presentation Outline
- ODRC Background
- Asset Accounting
- Replacement Costs
- Optimization
- Depreciation
- Results of Meralcos ODRC Valuation
3Conceptual Framework
Optimized Depreciated Replacement Cost (ODRC) is
calculated based on the gross current replacement
cost of assets that are adjusted for over-design,
over-capacity and/or redundancy, less an
allowance for depreciation.
4Typical Entries in the ODRC Register
5Asset Accounting
6Asset Accounting Tools
- Fixed Asset Register (FAR)
- Automated Mapping/Facilities Management (AM/FM)
- Field Verification/Sampling
7Challenges Encountered by Meralco
- Asset information was stored in several
databasesso asset tracker counts and other
sources such as Mapguide AM/FM, Meter Device
Management System (MDMS), Transformer Inventory
(TRINV), OTMS, CMS and SCADA have discrepancies. - Asset Tracker provided the historic costs, count,
age - AM/FM system provided the physical location for
verification - ERC used the Asset Tracker after comparison and
verification with other asset database
8Challenges Encountered by Meralco
- For Substation Assets
- Asset accounting was done using 100 field
survey of all Meralco substations (79 major
substations and 44 minor substations) - Installation date was captured during site
inspections from - name plate ratings
- Count of equipment was determined using single
line - diagrams
- Extensive photographic records were taken
9Sample Meralco Substations Survey Schedule
Major Substations From March 15 April 7, 2006
Minor Substations From June 1 June 8, 2006
D
10Actual Field Verification
Pre-survey Meeting
11Actual Field Verification
Verification of Single-line diagrams and
nameplate ratings
12Actual Field Verification
Verification of switchgear and control room
equipment
13Learnings on Asset Accounting
- There should only be one facility manager per
item who tracks the total count other relevant
information (installed, for test, under repair,
available in stock, for disposal, monthly usage
and if possible forecast requirements). - Revive the pole monitoring system.
- Assign company numbers to all major equipment
upon acceptance.
14Replacement Cost (RC)
15Replacement Cost
- Replacement Cost can be established by
- Reference to historical costs, adjusted for
inflationary increases since construction
(indexation) - Comparison with recent costs of similar assets
(replacement cost method) - Reference to technologically advanced assets in
use elsewhere (modern equivalent asset) - Aside from material and labor costs, RC includes
design and engineering costs, transport, freight,
duty, local delivery, interest during
construction, etc.
16Challenges Encountered by Meralco
Cost Estimating Methods
- 1. There were differences between the estimated
and actual costs because of the following - Average material costs were used instead of last
purchase cost. - Overtime and night differential cost not
considered as relevant cost. - 2. Actual and estimated labor cost do not match
perfectly.
17Learnings on Replacement Cost
- Incorporate overtime and night differential pay
in the cost estimates. - Review manhours requirement per constructive
unit. - Implementing offices to explain if there are wide
discrepancies between estimated and actual costs.
18Optimization
19Optimization
In practice, optimization is carried out in
accordance with the following principles
- Exclude stranded assets.
- Optimize the configuration of the network
system is reconfigured resulting in a lower value
network. - Optimize the capacity of elements in the network.
- Optimize network engineering components of the
network are replaced with components with lower
value. - Optimize stores and spares.
20Planning Horizon
21Factors Considered in the Optimization
- Loading of delivery point power transformers or
grid exit points - Loading of subtransmission lines
- Subtransmission System Configuration (number and
size of transformers and feeders per substation) - Loading of substation power transformers
- Substation topology (breaker-and-a-half bus
configuration against single bus scheme) - Substation engineering (AIS or GIS 34.5 kV
switchgear, spare GIS breakers, OLTC vs. AVRs)
22Factors Considered in the Optimization
7. Loading of distribution lines 8. Loading
of distribution line transformers 9. Circuit
breaker interrupting current ratings 10. Power
conditioning equipment 11. Low voltage
service 12. Spares meters, DTs, poles and
wires 13. Load Forecast
23SUMMARY OF PROPOSED OPTIMIZATION OF PBA OF
MERALCO DISTRIBUTION ASSETS
Optimization of circuit breakers was not
included in the final valuation report but
included in the optimization report.
24Loading Of Distribution Transformers (2012)
25SUMMARY OF PBAs PROPOSED OPTIMIZATION OF MERALCO
DISTRIBUTION ASSETS
PBA found the optimization of line transformers
not significant and thus was not included in the
final valuation report.
26Learnings on Optimization
- Review policies on GIS modules and circuit
breaker fault ratings. - Improve the process of DT monitoring (existence,
SIN to DT connectivity, kWH to kW computation). - Review policies on DT sizing to increase the
loading of the DTs (minimum capacity, initial kVA
size). - Review asset data on meters.
27Depreciation
28Depreciation
- Straight line depreciation is adopted.
- Factors to consider
- Effective lives estimated life, assuming
continued use in its present function as part of
a continuing business. - Age of equipment
29Factors in assessing effective lives
- Manufacturers recommendations
- Maintenance levels and life extension policies
- Environment in which the assets reside
- External factors such as supply/demand
characteristics - Physical, technological, functional and economic
obsolescence - Survivor data failure rates
30Challenges Encountered by Meralco
- Insufficient validated failure rate records and
asset life of equipment - - Power Transformers, Breakers, Distribution
Transformers, - Meters, Poles and Wires
- - Not all asset data were available or easy to
gather - Aside from depreciation, this data is used to
justify spare units
31Learnings on Asset Lives
Finalize failure rates for power transformers,
distribution transformers and meters. PBA used a
10 annual DT failure rate (of the total DT
population)
32Results of MeralcosODRC Valuation
33Results of Valuation
34Results of Valuation
35Results of Valuation
36Results of Valuation
As of June 30, 2006
37THANK YOU!