Title: Program Element 2
1Program Element 2 Develop and Implement a
Comprehensive Recharge Program Current Status and
Future Prospects
April 27, 2009
2Outline
- We will answer the following questions pertaining
to Program Element 2 - What is the present project condition?
- What are the future plans?
- What are the projected time limits for the
formulation and implementation? - What are the future anticipated problems in
implementation?
3What is the Present Project Condition?
- Groundwater production projections
- Replenishment projections
- Storm water recharge
- Effective supplemental water recharge capacity
- Conclusions
4Groundwater Production Projections based on IEUA
Investigation Completed in September 2008
5What is the Present Project Condition?
6What is the Present Project Condition?
- Where did the new storm water recharge estimate
of 6,000 acre-ft/yr come from?
7(No Transcript)
8(No Transcript)
9What is the Present Project Condition?
- What is the effective supplemental water recharge
capacity relative to the required supplemental
water recharge capacity?
10The Effective Supplemental Water Recharge
Capacity is Most Sensitive to MWD Replenishment
Water Availability
11Current Status of Replenishment Capacity Assuming
Replenishment Water Service from MWD at
30(acre-ft/yr)
12What is the Present Project Condition?
- Conclusion No. 1 The reliability of
replenishment water service from MWD is not
adequate to meet future replenishment needs and
to meet the dilution requirements for recycled
water recharge. - The reliability of supplies for replenishment
purposes will need to be about 90 percent to meet
the overall supplemental water recharge needs of
the basin. -
- Watermaster and the stakeholders should consider
improving the reliability of the imported water
used for replenishment.
13What is the Present Project Condition?
- Conclusion No. 2 The theoretical maximum
supplemental recharge capacity of the spreading
facilities available to Watermaster is about
92,000 acre-ft/yr but is limited by the turnout
capacity of CB13 to about 79,000 acre-ft/yr. -
- The recharge capacity of the San Sevaine Basins
is about 50 cfs. CB13 was initially rated at 30
cfs but can only be operated to 23 cfs, or less
than half the recharge capacity of the basin. -
- Watermaster and the stakeholders should consider
improving the CB13 turnout to increase the
supplemental recharge capacity of the basin.
14What is the Present Project Condition?
- Conclusion No. 3 New spreading basins are not
required to meet future replenishment
obligations. New ASR wells may likely be
necessary to focus replenishment in areas of high
groundwater production to sustain production - Cucamonga Ontario pumping depression
- Jurupa pumping depression
- Chino subsidence area
- Monte Vista Pomona subsidence area
15What is the Present Project Condition?
- Conclusion No. 4 IEUA is currently planning to
recharge 28,000 acre-ft/yr of recycled water.
With the present reliability of MWD replenishment
water of 30 percent, only about 7,500 acre-ft/yr
of recycled water can be recharged in the Chino
Basin. - If the reliability of MWD imported water used for
replenishment were increased to 90 percent, only
about 16,000 acre-ft/yr of recycled water can be
recharged in the Chino Basin. - Watermaster and the stakeholders should consider
increasing the recycled water contribution that
in turn will reduce the need to acquire
additional firm imported supplies.
16What is the Present Project Condition?
- Conclusion No. 5 Storm water has not been
optimized. The facilities and operating plans
envisioned in the 2000 Recharge Master Plan have
not been completely implemented. - Improvements were down scaled to reduce
construction costs - Operations and maintenance have not been
optimized. There is no nexus between the value
of storm water conserved and maintenance cost.
17What are the Future Plans?
18What are the Future Plans?
- Complete the 2010 Recharge Master Plan and update
every five years thereafter - Implement the 2010 Recharge Master Plan that will
contain the following - Increasing water conservation
- Securing additional reliable replenishment
supplies - Improving hydraulic capacity to get more imported
water to the Chino Basin and to recharge
facilities - Constructing aquifer storage and recovery (ASR)
wells in key areas - Aligning (or increasing) investments in storm
water recharge to the value of avoided
supplemental water recharge
19What are the Projected Time Limits for the
Formulation and Implementation?
20What are the Projected Time Limits for the
Formulation and Implementation?
- Complete the 2010 Recharge Master Plan
- Will be completed by July 1, 2010
- Implement the 2010 Recharge Master Plan
- Recommended implementation time line will be
included in Master Plan - Agreements among the parties will need to be
developed to implement the 2010 Recharge Master
Plan - Could take to 2012 or 2013 to complete these
agreements and begin implementation
21What are the Future Anticipated Problems in
Implementation?
22What are the Future Anticipated Problems in
Implementation?
- Availability of imported water
- MWD cannot supply enough imported water we need
to secure access to non MWD imported water
sources - Related challenges cost, environmental issues,
wheeling capacity - Hydraulic capacity in MWD pipelines
- MWD will not commit to delivering replenishment
water in the quantities required by Watermaster
due to capacity limitations in the Rialto Pipeline
23What are the Future Anticipated Problems in
Implementation?
- Equity issues
- Judgment provides for equal access to groundwater
- Replenishment capacity is driven by supply
reliability, recharge capacity, growth, and
business interests of the parties - Unclear how to distribute the new costs
associated with meeting future replenishment
capacity - Cost and funding
- The types of facilities anticipated include ASR
wells, new treatment plant capacity for imported
and recycled water, pipelines, basin improvements - New water rights and or long term water transfer
contracts - Capital cost could easily exceed 200 million
24End
25(No Transcript)
26(No Transcript)