Program Element 2 - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

Program Element 2

Description:

We will answer the following ... Improving hydraulic capacity to get more imported water to the Chino Basin and ... Hydraulic capacity in MWD pipelines ... – PowerPoint PPT presentation

Number of Views:33
Avg rating:3.0/5.0
Slides: 27
Provided by: pba54
Category:

less

Transcript and Presenter's Notes

Title: Program Element 2


1
Program Element 2 Develop and Implement a
Comprehensive Recharge Program Current Status and
Future Prospects
April 27, 2009
2
Outline
  • We will answer the following questions pertaining
    to Program Element 2
  • What is the present project condition?
  • What are the future plans?
  • What are the projected time limits for the
    formulation and implementation?
  • What are the future anticipated problems in
    implementation?

3
What is the Present Project Condition?
  • Groundwater production projections
  • Replenishment projections
  • Storm water recharge
  • Effective supplemental water recharge capacity
  • Conclusions

4
Groundwater Production Projections based on IEUA
Investigation Completed in September 2008
5
What is the Present Project Condition?
6
What is the Present Project Condition?
  • Where did the new storm water recharge estimate
    of 6,000 acre-ft/yr come from?

7
(No Transcript)
8
(No Transcript)
9
What is the Present Project Condition?
  • What is the effective supplemental water recharge
    capacity relative to the required supplemental
    water recharge capacity?

10
The Effective Supplemental Water Recharge
Capacity is Most Sensitive to MWD Replenishment
Water Availability
11
Current Status of Replenishment Capacity Assuming
Replenishment Water Service from MWD at
30(acre-ft/yr)
12
What is the Present Project Condition?
  • Conclusion No. 1 The reliability of
    replenishment water service from MWD is not
    adequate to meet future replenishment needs and
    to meet the dilution requirements for recycled
    water recharge.
  • The reliability of supplies for replenishment
    purposes will need to be about 90 percent to meet
    the overall supplemental water recharge needs of
    the basin.
  • Watermaster and the stakeholders should consider
    improving the reliability of the imported water
    used for replenishment.

13
What is the Present Project Condition?
  • Conclusion No. 2 The theoretical maximum
    supplemental recharge capacity of the spreading
    facilities available to Watermaster is about
    92,000 acre-ft/yr but is limited by the turnout
    capacity of CB13 to about 79,000 acre-ft/yr.
  • The recharge capacity of the San Sevaine Basins
    is about 50 cfs. CB13 was initially rated at 30
    cfs but can only be operated to 23 cfs, or less
    than half the recharge capacity of the basin.
  • Watermaster and the stakeholders should consider
    improving the CB13 turnout to increase the
    supplemental recharge capacity of the basin.

14
What is the Present Project Condition?
  • Conclusion No. 3 New spreading basins are not
    required to meet future replenishment
    obligations. New ASR wells may likely be
    necessary to focus replenishment in areas of high
    groundwater production to sustain production
  • Cucamonga Ontario pumping depression
  • Jurupa pumping depression
  • Chino subsidence area
  • Monte Vista Pomona subsidence area

15
What is the Present Project Condition?
  • Conclusion No. 4 IEUA is currently planning to
    recharge 28,000 acre-ft/yr of recycled water.
    With the present reliability of MWD replenishment
    water of 30 percent, only about 7,500 acre-ft/yr
    of recycled water can be recharged in the Chino
    Basin.
  • If the reliability of MWD imported water used for
    replenishment were increased to 90 percent, only
    about 16,000 acre-ft/yr of recycled water can be
    recharged in the Chino Basin.
  • Watermaster and the stakeholders should consider
    increasing the recycled water contribution that
    in turn will reduce the need to acquire
    additional firm imported supplies.

16
What is the Present Project Condition?
  • Conclusion No. 5 Storm water has not been
    optimized. The facilities and operating plans
    envisioned in the 2000 Recharge Master Plan have
    not been completely implemented.
  • Improvements were down scaled to reduce
    construction costs
  • Operations and maintenance have not been
    optimized. There is no nexus between the value
    of storm water conserved and maintenance cost.

17
What are the Future Plans?
18
What are the Future Plans?
  • Complete the 2010 Recharge Master Plan and update
    every five years thereafter
  • Implement the 2010 Recharge Master Plan that will
    contain the following
  • Increasing water conservation
  • Securing additional reliable replenishment
    supplies
  • Improving hydraulic capacity to get more imported
    water to the Chino Basin and to recharge
    facilities
  • Constructing aquifer storage and recovery (ASR)
    wells in key areas
  • Aligning (or increasing) investments in storm
    water recharge to the value of avoided
    supplemental water recharge

19
What are the Projected Time Limits for the
Formulation and Implementation?
20
What are the Projected Time Limits for the
Formulation and Implementation?
  • Complete the 2010 Recharge Master Plan
  • Will be completed by July 1, 2010
  • Implement the 2010 Recharge Master Plan
  • Recommended implementation time line will be
    included in Master Plan
  • Agreements among the parties will need to be
    developed to implement the 2010 Recharge Master
    Plan
  • Could take to 2012 or 2013 to complete these
    agreements and begin implementation

21
What are the Future Anticipated Problems in
Implementation?
22
What are the Future Anticipated Problems in
Implementation?
  • Availability of imported water
  • MWD cannot supply enough imported water we need
    to secure access to non MWD imported water
    sources
  • Related challenges cost, environmental issues,
    wheeling capacity
  • Hydraulic capacity in MWD pipelines
  • MWD will not commit to delivering replenishment
    water in the quantities required by Watermaster
    due to capacity limitations in the Rialto Pipeline

23
What are the Future Anticipated Problems in
Implementation?
  • Equity issues
  • Judgment provides for equal access to groundwater
  • Replenishment capacity is driven by supply
    reliability, recharge capacity, growth, and
    business interests of the parties
  • Unclear how to distribute the new costs
    associated with meeting future replenishment
    capacity
  • Cost and funding
  • The types of facilities anticipated include ASR
    wells, new treatment plant capacity for imported
    and recycled water, pipelines, basin improvements
  • New water rights and or long term water transfer
    contracts
  • Capital cost could easily exceed 200 million

24
End
25
(No Transcript)
26
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com