U.S. 41 Venice BypassSarasota Manatee MPO CAC
Presentation
  • Florida Department of Transportation District One

October 5, 2006
2
Florida Department of Transportation
Federal Highway Administration
City of Venice
U.S. 41 Venice Bypass
Sarasota County
Sarasota-Manatee MPO
  • A design change reevaluation of a PDE study
    approved in 1994

3
Design Change Reevaluation
  • Evaluate new design alternatives
  • Minimize right-of-way impacts
  • Reduce right-of-way acquisition costs
  • Document changes to the project area since 1994

4
Regional Roadway
  • Sarasota Manatee MPO 2030 Plan
  • City of Venice Comprehensive Plan

5
Project Need
6
Project Limits Original PDE
Bird Bay Drive
Center Road
Hatchett Creek
Gulf Coast Blvd.
SEGMENT 3
SEGMENT 2
SEGMENT 1
0.50 Miles
0.66 Miles
1.19 Miles
6
P\fdt2044\docs\transp\pub wrkshp
7
Original PDE Segment 12
7
P\fdt2044\docs\transp\pub wrkshp
8
Original PDE Alignment Segment 12
Seaboard Avenue
Center Road
Gulf Coast Blvd.
Via Veneto
Corporation Way
Venice Avenue
Hatchett Creek
James Street
SEGMENT 2
SEGMENT 1
0.50 Miles
1.19 Miles
9
Original PDE Preferred Alternative Seg 1-2
  • 55 Parcels impacted
  • 18 Business relocations
  • 1 Church relocation
  • 0 Residence relocations
  • Right-of-way costs 66,000,000
  • Construction costs 26,000,000
  • Design CEI costs 5,100,000
  • Total estimated cost 97,100,000

Seaboard Avenue
Center Road
Gulf Coast Blvd.
Via Veneto
Corporation Way
Venice Avenue
Hatchett Creek
James Street
SEGMENT 2
SEGMENT 1
0.50 Miles
1.19 Miles
10
Original PDE Segment 3
Bird Bay Drive
Hatchett Creek
SEGMENT 3
0.66 Miles
10
P\fdt2044\docs\transp\pub wrkshp
11
Original PDE Segment 3
12
Original PDE Segment 3
  • 4 Parcels impacted
  • 0 Business relocations
  • 0 Residence relocations
  • Right-of-way costs 4,200,000
  • Construction costs 11,500,000
  • Design CEI costs 2,150,000
  • Total estimated cost 17,850,000

Bird Bay Drive
Hatchett Creek
SEGMENT 3
0.66 Miles
12
P\fdt2044\docs\transp\pub wrkshp
13
Project Limits Design Change Reevaluation
Bird Bay Drive
Center Road
Hatchett Creek
SEGMENT 2
SEGMENT 1
13
P\fdt2044\docs\transp\pub wrkshp
14
Segment 1
Center Road
Gulf Coast Blvd.
Hatchett Creek
14
P\fdt2044\docs\transp\pub wrkshp
15
Segment 2
Bird Bay Drive
Hatchett Creek
SEGMENT 2
0.66 Miles
15
P\fdt2044\docs\transp\pub wrkshp
16
Public Information Workshop
  • Venice Community Center 326 South Nokomis Avenue
    Thursday, March 16, 2006

16
P\fdt2044\docs\transp\pub wrkshp
17
No-Build Alternative
  • ADVANTAGES
  • No traffic flow interruptions due to construction
  • No relocations or right-of-way acquisition
  • No expenditure of funds

18
No-Build Alternative
  • DISADVANTAGES
  • Increase in traffic congestion
  • Rise in maintenance cost
  • Incompatible with future network plans
  • Increase in air pollution
  • Increase in traffic demand
  • No improvements in emergency response time 
  • No improvements in evacuation routes

19
Preferred Build Alternative for Segment 1
20
Preferred Build Alternative for Segment 1
  • 49 Parcels Impacted
  • 19 Business relocations
  • 0 Residence relocations
  • Right-of-way costs 28,900,000
  • Construction costs 25,000,000
  • Design CEI costs 4,700,000
  • Total estimated cost 58,600,000

Seaboard Avenue
Center Road
Gulf Coast Blvd.
Via Veneto
Corporation Way
Venice Avenue
Hatchett Creek
James Street
SEGMENT 1
1.69 Miles
21
Preferred Build Alternative for Segment 2
22
Roadway Alignment for Segment 2
  • 4 Parcels impacted
  • 0 Business relocations
  • 0 residence relocations
  • Right-of-way costs 4,000,000
  • Construction costs 11,000,000
  • Design CEI costs 2,100,000
  • Total estimated cost 17,100,000

Bird Bay Drive
Hatchett Creek
Substation Road
SEGMENT 2
0.66 Miles
23
Access Management
  • Increase safety
  • Reducing conflictpoints
  • Lengthen turn lane storage

24
Environmental Effects
  • Social
  • Cultural
  • Natural
  • Physical

25
FDOT Adopted Five-Year Work Program
2005 - 2008
Final Design
Not Funded
R / W Acquisition
Not Funded
Project Construction
26
Questions and Comments
  • The project websitewww.us41venicebypass.com
Write a Comment