Title: Baselines and additionality
1- ??????
- Baselines and additionality
??CDM??????????Training Material Building
Capacity for the CDM in China
2????? The baseline scenario
- ???(?????)Baseline (baseline scenario )
- ???CDM????????,?GHG?????????
- Scenario forecasted to show the trend of
anthropogenic GHG emissions - that would occur in the absence of the proposed
CDM project. - ????Project scenario
- ??CDM????????,?GHG?????????
- Scenario forecast to show the trend of
anthropogenic GHG emissions - that would occur with the proposed CDM project
intervention.
3???Baseline
- CDM???????????????????????????????????????????????
?????????A ???????????????? - The baseline for a CDM project activity is the
scenario that reasonably represents the
anthropogenic emissions by sources of greenhouse
gases that would occur in the absence of the
proposed project activity. A baseline shall cover
emissions from all gases, sectors and source
categories listed in Annex A within the project
boundary. - ???????????????????????????????????????????????
- The baseline may include a scenario where future
anthropogenic emissions by sources are projected
to rise above current levels, due to the specific
circumstances of the host Party. - CDM modalities procedures, paragraph 44 46
4?????Baseline approaches (MA48)
????????????????????????????????????? Select from
among the following approaches the one deemed
most appropriate for the project activity and
justify the appropriateness of your choice
- ?????????????(????)
- ????????????,??????????????????????
- ???????????????????,????????????????????20
- Existing actual or historical emissions, as
applicable - Emissions from a technology that represents an
economically attractive course of action, taking
into account barriers to investment - The average emissions of similar project
activities undertaken in the previous five years,
in similar social, economic, environmental and
technological circumstances, and whose
performance is among the top 20 per cent of their
category.
5?????Establishing a baseline
- ??????????
- ???????????????????
- ??????????????????????????????????????,???????
- ??????????????????????,???????????????????????????
???? - ????CDM????,???????????,??????????
- On a project-specific basis
- In accordance with provisions for the use of
approved and new methodologies - In a transparent and conservative manner manner
regarding the choice of approaches, assumptions,
methodologies, parameters, data sources, key
factors and additionality, and taking into
account uncertainty - Taking into account relevant national and/or
sector policies and circumstances, such as sector
reform initiatives, local fuel availability,
power sector expansion plans, and the economic
situation in the project sector. - In the case of small-scale CDM project activities
which meet the criteria specified in accordance
with simplified procedures developed for such
activities
6???????Baseline and additionality
eq
2-
???Emission reductions
GHG emissions t CO
Year
7?????Additionality requirements
- CDM??????????????????????????????????
- GHG emission reductions of CDM projects shall be
real, measurable, and assure long-term benefits
related to the mitigation of climate change - CDM ??????????????????????????????????????????
- GHG emission reductions of CDM projects shall be
additional to any that would occur in the absence
of the certified project activity. - Kyoto Protocol, Article 12/ 5(c)
- ????????????????,?????????????????????????????????
????? - A CDM project activity is additional if
anthropogenic emissions of greenhouse gases by
sources are reduced below those that would have
occurred in the absence of the registered CDM
project activity. - CDM modalities procedures, paragraph 43
8?????Additionality assessment
????????????????????????????,???????
Additionality assessment is an explanation of
how, through the use of the methodology, it can
be demonstrated that a project activity is
additional and therefore not the baseline
scenario.
- ????????????????????????
- ?????????????????,????????????????
- ??????????????????
- ?????????????,??????? lt???????X
- A flow-chart or series of questions that lead to
a narrowing of potential baseline options - A qualitative or quantitative assessment of
different potential options and an indication of
why the non-project option is more likely - A qualitative or quantitative assessment of one
or more barriers facing the proposed project
activity - (An indication that the project type is not
common practice (e.g. occurs in less than lt x
of all cases)
9???????? Additionality Introduction of new
legislation
- E??????(?)??????????????????,
?????????????????/?????????? - Type E Existing national and/or sectoral
policies or regulations that create policy driven - market distortions which give comparative
advantages to more emissions-intensive
technologies - or fuels over less emissions-intensive
technologies or fuels. - ??? E?????(?)????????COP???????(1997.12.11?deci
sion 1/CP.3)?????,????????????????E?????(?)????
????COP????????????,???????????????????????? - -Only Type E national and/or sectoral policies
or regulations that have been implemented - before adoption of the Kyoto Protocol by the COP
(decision 1/CP.3, 11 December 1997) shall be
taken into account when developing a baseline
scenario. If Type E national and/or sectoral
policies were implemented since the adoption of
the Kyoto Protocol, the baseline scenario should
refer to a hypothetical situation without the
national and/or sectoral policies or regulations
being in place. - E-??????(?)???????,????????????????/??????????(??
???????????????) - Type E- National and/or sectoral policies or
regulations that give positive comparative - advantages to less emissions-intensive
technologies over more emissions-intensive
technologies (e.g. public subsidies to promote
the diffusion of renewable energy or to finance
energy efficiency programs) - E-?????(?)????????COP???????(1997.12.11?decisio
n 1/CP.3)?????,??????????????? (??????????????????
???????) - Type E- national and/or sectoral policies or
regulations that have been implemented since the - Adoption by the COP of the CDM MP (decision
17/CP.7, 11 November 2001) may not be taken into
account in developing a baseline scenario (i.e.
the baseline scenario should refer to a
hypothetical situation without the national
and/or sectoral policies or regulations being in
place).
10?????The additionality tool
- 0. ??????????
- 0 Justify early start of the project and show
that CDM was considered - 1. ????????????
- 1. Baseline options related to existing laws and
regulations - 2. ???? 2.Investment analysis
- ???NVP/IRR,??Simple, NPV/IRR, benchmark
- ??,?????Comparisons, sensitivity analysis
- 3. ???? 3 Other barriers
- ??????????
- Other First of kind, capacity, technology etc..
- 4. ??????????
- 4Demonstarte that the project is not common
practice - 5. ?????? 5 Impact of CDM registration
11???????-??1 Additionality testing example -Step 1
- ??????
- Define alternatives
- ???????CDM??
- The project not undertaken as CDM project
- ?????????
- All other plausible and credible scenarios
- ????(????)
- The business as usual (as applicable)
- ????
- Check towards legislation
- ??????, ???????????
- If legislation is not enforced, this may cause
the project to be additional
12???????-??2 - Additionality testing example -Step
2
- ??????????????IRR
- ????CERs?????
- ????????????????
- ???????
- ????
- ????
- ?????????????
- ???????
- ?????????????
- Calculate a conservative internal rate of return
(IRR) for the proposed project activity - Excluding expected revenue from the sale of CERs.
- Include the incremental investment cost, the
operations and maintenance costs, and all other
costs of upgrading the BAU scenario to the
proposed project activity. - Also include all revenues generated by the
project activity, including revenue from the sale
of electricity and cost savings due to avoided
electricity purchases,
13???????-??2 - Additionality testing example Step
2
- ?????IRR??????????????????IRR?????????????
- ??????IRR???
- ????????????????(??????)
- ??????IRR???????????
- ??????????????.
- Determine whether the project IRR is
significantly lower than a conservatively (i.e.
rather low) expected and acceptable IRR for an
alternative to this project or a comparable
project type in the relevant country. - The conservatively acceptable IRR can be based
on - ?Government bond rates or other appropriate
estimates of the cost-of-capital (e.g. commercial
lending rates) - ?Expert views on expected IRRs for this or
comparable project types - ?Other hurdle rates that can be applied for the
country or sector.
14?????????(1) Barriers and Economic Theory (1)
15?????????(2)Barriers and Economic Theory (2)
16????????Project financial analysis
B (??) Benefits C (??)Costs
17????Time Value
- ???????
- ????1000?? A. Receive 10,000 now OR
- 3????1000??B. Receive 10,000 in three years
???1??????1????? 10 000 now are worth more than
10 000 in the future
18????Future Value
19??Present Value
20???Net Present Value
- ????????????,?????????????????????????????????
- Net Present Value is the cumulative present value
of income (positive values) and a series of
future payments (negative values) from a series
of investment cash flow using a discount rate to
handle time values of money.
i Discount rate CF Cash Flow j the j-th
period n the total number of the period
21???Net Present Value
- ???????, NPV gt 0 ???????????,?????????
- more economic attractive
- ???????, NPV lt 0???????????,????????,
- less economic attractive
- ??????, NPV 0???????????????????????
- Balance attractive
22?????IRR
- ???????????????????
- IRR is the discount rate r which makes the NPV of
the investment exactly zero.
23??2??Step 2 summary
- ??NPV/IRR ??,??CERs?????,????????
- if NPV/IRR is too low, the project will not go
ahead anyway, regardless of the CERs revenue or
not - ??NPV/IRR??,?????????????
- if NPV/IRR is too high, the project will have
difficulties in explaining the investment
barrier, as it may be argued that it would be
implemented anyway, regardless of the CERs
revenue. - ???????????????,DOE????????????
- it is very difficult for the DOE to check the
IRR as we don't know a project developer's
internal costing approach, the way benefits are
evaluated, etc. there are a lot of assumptions in
such calculations, as we're talking about future
cash flows. - ?????????????????????????NPV/IRR????
- DNV bases its judgement on experiences with
similar projects in the respective sector and
country context and will ask authorities or other
stakeholders whether the NPV/IRR analysis in the
PDD is reasonable. - ?PDD????????????????
- Add a qualitative discussion about the NPV/IRR
in your PDD to make the case of an investment
barrier.
24???????-??3 - Additionality testing example -Step
3
- ????
- Barrier assessment
- ????
- Investment barriers
- ????
- Technological barriers
- ??????????
- Barriers due to prevailing practice
- ?????????
- Support barriers with sufficient evidence
- ?????????????? (?????!)
- Show that at least one of the scenarios would
not be prevented by the barriers (that will be
the baseline!)
25???????-??4 - Additionality testing example -Step
4
- ??????
- Common practice analysis
- ????
- Other activities
- ??????
- Similar options occurring
- ????
- Discuss!
26??5 CDM ?????Step 5. Impact of CDM registration
- ??????????????CDM???,????????????????????(???????)
????????(???????) - Explain how the approval and registration of the
project activity as a CDM activity, and the
attendant benefits and incentives derived from
the project activity, will alleviate the economic
and financial - hurdles (Step 2) or other identified barriers
(Step 3) and thus enable the project activity to
be undertaken. - ????????????
- The benefits and incentives can be of various
types, such as - ???????Anthropogenic greenhouse gas emission
reductions - ??CERs???The financial benefit of the revenue
obtained by selling CERs, - ?????????Attracting new players who are not
exposed to the same barriers, or can accept a
lower IRR (for instance because they have access
to cheaper capital), - ????????Attracting new players who bring the
capacity to implement a new technology, and - ????Reducing inflation /exchange rate risk
affecting expected revenues and attractiveness
for investors.