Title: Disaster Recovery: Lessons from Katrina
1Disaster RecoveryLessons from Katrina
- Gail Ann McCreary, CRM
- Mississippi Power Company
2(No Transcript)
3Hurricane Katrina August 29, 2005
- Worst natural disaster in U.S. history
- Affected Alabama Mississippi Louisiana
- 250 miles wide
- 140 mph winds
- 30 ft tidal surge along coast line
4(No Transcript)
5(No Transcript)
6(No Transcript)
7(No Transcript)
8(No Transcript)
9Were Dealing With
- Rain and wind damage
- Tornadoes
- Flooding
- Coal water
- Submerged records
- Bio-hazard
10(No Transcript)
11(No Transcript)
12(No Transcript)
13(No Transcript)
14(No Transcript)
15(No Transcript)
16(No Transcript)
17(No Transcript)
18Determined Priorities
- Damage incurred
- Business unit and function
- Criticality to restoration effort
- Building access issues
19(No Transcript)
20The Plan.
- Identify records needing to be dried
- Pack into boxes
- Stage on pallets
- Shrink wrap
- Load into freezer truck
21First Priorities
- Substation Construction
- Powerco
- Plant Watson
22(No Transcript)
23(No Transcript)
24(No Transcript)
25(No Transcript)
26(No Transcript)
27(No Transcript)
28(No Transcript)
29Plan Changed
- Downtown buildings had to be vacated
- All dry records
- All PCs, printers, phones
- Employee personal effects
- Undamaged furniture and modular
- Office supplies
- 400 employees
30New Issues
- Needed more boxes!!!!
- Needed temporary office space for 400 employees
- What to do with all the stuff
- Employees still on storm duty
- 2-3 weeks
31Plan B
- DR would stay and pack dry records too
- I did not have the manpower
- DR was experienced
- Had supply and manpower resources in place
32Determined Numbering Scheme
- Building ID
- Floor number
- Location number
- 202-101 General Office 2nd floor cubicle 202
- SI221-106 GSI 2nd floor location 221
- 842-102 Hancock Bank 8th floor location 842
33(No Transcript)
34Challenges Faced
- Locked doors
- On-going building clean-up restoration
- No elevators
- No electricity
- Storage for 7700 boxes
35 Back to Normal
36(No Transcript)
37(No Transcript)
38Phase II
- Multiple temporary offices
- No storage in temporary offices
- No file cabinets
- Delivery issues
- Palletized boxes not in order by location
39Phase II
- Employees would have to review
- Coordinate with occupancy schedule
- Named coordinators for each site
- Small volumes delivered where possible
40Location No. ______818 _________ Name _Lateral
file __
41Options
- Take
- Destroy
- Interim
- Records center storage
42(No Transcript)
43(No Transcript)
44Lessons Learned - Disaster Recovery Process
- Utilize document recovery contractor
45Lessons Learned -Disaster Recovery Process
- Utilize document recovery contractor
- Understand the process / clarify costs
46Lessons Learned - Disaster Recovery Process
- Utilize document recovery contractor
- Understand the process / clarify costs
- Utilize multiple people
47Lessons Learned - Disaster Recovery Process
- Utilize document recovery contractor
- Understand the process / clarify costs
- Utilize multiple people
- Work closely with contractor
48Lessons Learned - Disaster Recovery Process
- Utilize document recovery contractor
- Understand the process / clarify costs
- Utilize multiple people
- Work closely with contractor
- Walk-thru after packing completed
49Lessons Learned - Disaster Recovery Process
- Utilize document recovery contractor
- Understand the process / clarify costs
- Utilize multiple people
- Work closely with contractor
- Walk-thru after packing completed
- Have floor plans for all buildings
50Lessons Learned - Disaster Recovery Process
- Utilize document recovery contractor
- Understand the process / clarify costs
- Utilize multiple people
- Work closely with contractor
- Walk-thru after packing completed
- Have floor plans for all buildings
- Document! Document! Document!
51Lessons Learned - Disaster Recovery Process
- Need business continuity plan
52Lessons Learned - Disaster Recovery Process
- Need business continuity plan
- Definition of vital records has changed
53Lessons Learned - Disaster Recovery Process
- Need business continuity plan
- Definition of vital records has changed
- Have emergency contact numbers
54Lessons Learned - Disaster Recovery Process
- Need business continuity plan
- Definition of vital records has changed
- Have emergency contact numbers
- Post-critique
55Lessons Learned - Facilities
- Get to know your Facilities department
56Lessons Learned - Facilities
- Get to know your Facilities department
- Establish liaisons with field/branch offices
57Lessons Learned - Facilities
- Get to know your Facilities department
- Establish liaisons with field/branch offices
- Limit employees personal items
58Lessons Learned - Facilities
- Get to know your Facilities department
- Establish liaisons with field/branch offices
- Limit employees personal items
- No locked file cabinets or overheads
59Lessons Learned - Facilities
- Get to know your Facilities department
- Establish liaisons with field/branch offices
- Limit employees personal items
- No locked file cabinets or overheads
- Take office keys with you
60Lessons Learned - Facilities
- Get to know your Facilities department
- Establish liaisons with field/branch offices
- Limit employees personal items
- No locked file cabinets or overheads
- Take office keys with you
- No critical or only copy records in disaster
susceptible areas
61Lessons Learned - Personnel
- Storm procedures not heeded
62Lessons Learned - Personnel
- Storm procedures not heeded
- Records preparation should be part of storm
preparation and communications
63Lessons Learned - Personnel
- Storm procedures not heeded
- Records preparation should be part of storm
preparation and communications - Files should be labeled / identified
64Lessons Learned - Personnel
- Storm procedures not heeded
- Records preparation should be part of storm
preparation and communications - Files should be labeled / identified
- Enforce corporate policies
65Lessons Learned - Personnel
- Storm procedures not heeded
- Records preparation should be part of storm
preparation and communications - Files should be labeled / identified
- Enforce corporate policies
- People are stressed
66Lessons Learned - Personnel
- Storm procedures not heeded
- Records preparation should be part of storm
preparation and communications - Files should be labeled / identified
- Enforce corporate policies
- People are stressed
- Promote disaster preparedness and vital records
protection
67Silver Linings
- Files were cleaned out
- Inactive records sent to storage
- Destruction of expired and unnecessary records
- Reduction in file volume
68Silver Linings
- Files were cleaned out
- Inactive records sent to storage
- Destruction of expired and unnecessary records
- Reduction in file volume
- New contacts with business units
69Silver Linings
- Files were cleaned out
- Inactive records sent to storage
- Destruction of expired and unnecessary records
- Reduction in file volume
- New contacts with business units
- Multiple opportunities to promote RIM
70Silver Linings
- Files were cleaned out
- Inactive records sent to storage
- Destruction of expired and unnecessary records
- Reduction in file volume
- New contacts with business units
- Multiple opportunities to promote RIM
- Department credibility enhanced
71Silver Linings
- Disaster planning for records now priority
72Silver Linings
- Disaster planning for records now priority
- Records protection procedures part of storm manual
73Silver Linings
- Disaster planning for records now priority
- Records protection procedures part of storm
manual - No people or records in Lower Level
74Silver Linings
- Disaster planning for records now priority
- Records protection procedures part of storm
manual - No people or records in Lower Level
- EOC and critical functions moved from coastal zone
75Silver Linings
- RIM storm assignment changed
76Silver Linings
- RIM storm assignment changed
- Employees will not be complacent about next storm
77Conclusions
- Be proactive vs. reactive
78Conclusions
- Be proactive vs. reactive
- Good sense, sound judgment and creativity are
necessary
79Conclusions
- Be proactive vs. reactive
- Good sense, sound judgment and creativity are
necessary - Dont be complacent
80Conclusions
- Be proactive vs. reactive
- Good sense, sound judgment and creativity are
necessary - Dont be complacent
- Expect the unexpected
81Conclusions
- Be proactive vs. reactive
- Good sense, sound judgment and creativity are
necessary - Dont be complacent
- Expect the unexpected
- Evaluate suppliers and services
82Conclusions
- Be proactive vs. reactive
- Good sense, sound judgment and creativity are
necessary - Dont be complacent
- Expect the unexpected
- Evaluate suppliers and services
- Empower people
83Questions?
- Gail Ann McCreary, CRM
- 228-865-5467 gamccrea_at_southernco.com