Transcript and Presenter's Notes

Title: Title 39


1
  • Title 39
  • UA Projects Under 50,000.

2
What has UA been doing on public works projects
under 50,000?
  • During the 2006 calendar year, the University of
    Alabama issued purchase orders for approximately
    250 individual projects.
  • During the 2006 calendar year, the University of
    Alabama issued purchase orders for the above
    listed projects exceeding 3.7 million dollars
    with the average cost of each project being
    approximately 15,000.00 while utilizing the
    services of over 60 different contractors.

3
What has UA been doing on public works projects
under 50,000?
  • During the 2007 calendar year, the University of
    Alabama has already issued purchase orders for
    approximately 60 individual projects.
  • During the 2007 calendar year, the University of
    Alabama has issued purchase orders in excess of
    6000,000.00, with an average cost of each
    project being approximately 10,000.000.

4
Title 39 Public Works LawGeneral Guidelines for
Projects 50,000 and Under
  • Definition of Public Works
  • The construction, repair, renovation, or
    maintenance of public buildings, structures,
    sewers, waterworks, roads, bridges, docks,
    underpasses, and viaducts as well as ay other
    improvement to be constructed, repaired,
    renovated, or maintained on public property and
    to be paid, in whole or in part, with public
    funds or with financing to be retired with public
    funds in the form of lease payments or otherwise.

5
Title 39 Public Works LawGeneral Guidelines for
Projects 50,000 and Under
  • Under 50,000 Projects Exempt under Title 39 Bid
    Requirement
  • The following are not required for under 50,000
    projects
  • Performance Bond
  • Payment Bond
  • Bid Guarantee
  • Formal Advertising of sealed bids
  • Very Important No public work as defined in
    Title 39 Public Works law shall be split into
    parts involving sums of 50,000 or less for the
    purpose of evading the requirements of this
    section.

6
Title 39 Public Works LawGeneral Guidelines for
Projects 50,000 and Under
  • Requirements for Projects 50,000 and under
  • Generally, three (3) written quotations will be
    required for each project. Exceptions will be
    considered upon review of special circumstances
    and approved by the Purchasing Manager for
    Facilities.
  • To expedite final payment, a notice of final
    completion of the project will be published one
    time in a newspaper of general circulation in the
    county of the contracting agency and a notice of
    final completion will be posted on the Purchasing
    Departments bulletin board for one week the
    contractor is required to verify under oath that
    all bills have been paid in full. Final
    settlement with the contractor may be made at any
    time after the notice has been posted for one
    entire week.

7
Title 39 Public Works LawGeneral Guidelines for
Projects 50,000 and Under
  • Daily Operating Guidelines
  • A published notice of final completion of each
    project as stipulated in Title 39 for under
    50,000 projects is required even when the
    primary contractor has not subcontracted any
    portion of the work.
  • The following statement must appear on all
    purchase orders issued for under 50,000 Public
    Work projects
  • Pursuant to Title 39, Public Works Law, this
    project is exempt form the sealed bid
    requirements, since it is less than 50,000.

8
Quick Reference Guide to Procedures For Title 39
Projects Under 50,000.
  • University Department submits a request to
    initiate a project.
  • University Facility and Construction
    Administration Departments review the request to
    decide whether the work will be performed
    in-house or contracted with an outside
    contractor.
  • If the project is to be assigned to an outside
    contractor, a University Project Manager is
    assigned to the project.
  • UA Project Manager develops specifications,
    contacts possible contractors, and conducts a
    site inspections of the project with interested
    contractors to discuss requirements.
  • Contractors submit written quotes to the UA
    Project Manager.

9
Quick Reference Guide to Procedures For Title 39
Projects Under 50,000.
  • UA Project Manager reviews written quotes to the
    UA Project Manager.
  • The selected contractors insurance is reviewed
    to ensure compliance with University
    requirements.
  • A purchase order is issued to the successful
    contactor.
  • At completion of project, contractor submits
    notice of completion of project and invoice for
    payment.
  • a legal notice will be placed in the Tuscaloosa
    News by the University for one day, advertising
    the completion of this projects and will be
    posted outside the Purchasing Department for one
    week before final payment is released to the
    contractor.

10
Insurance Requirements
11
Insurance Requirements (continued)
12
  • UA Construction Projects Over 50,000
  • Title 39

13
  • I. Advertisement for Bids
  • a. Advertise for 3 consecutive weeks in
    Tuscaloosa News
  • b. State a description of the project
  • c. State that the plans and specifications are on
    file for examination at UA and at specified Plan
    Rooms
  • d. State the procedure for obtaining Plans and
    Specifications
  • e. State the time and place bid will be opened
  • f. Identify if Pre-Qualification is necessary
  • i. PQ packets available for GCs and Subs
  • ii. Deadline to return the packets
  • iii. Notification of those approved as
    Pre-Qualified
  • g. Bid notification system sign up after session

14
  • II. Plans Specs
  • a. GCs - can obtain with a deposit that is
    refundable within 10 days after bid opening if in
    good condition
  • Subcontractors can obtain for cost of
    reproduction paid to Architect
  • III. Requirements for bidding
  • a. Must be Pre-Qualified if required
  • b. Must have a current Alabama General
    Contractors License and show proof thereof
  • c. Must place with their bid 5 of their bid but
    not greater than 10,000 in the form of a
  • i. Cashiers check for said amount
  • ii. Bid bond for said amount executed by a Surety
    Company duly authorized and qualified to do so in
    Alabama
  • d. Bid must be Responsible and Responsive
  • i. Responsible if they meet the
    Pre-Qualification procedures and Criteria (job
    specific)
  • ii. Responsive submits a bid that complies with
    the terms and conditions of the invitation for
    bids
  • e. Awarding Authority (UA) has the right to
    reject any and all bids if it is in the best
    interest of the University

15
  • IV. Exclusions from bidding must not perform
    any of the Work or subcontract it
  • a. Architects
  • b. Engineers
  • c. Construction Management
  • d. Program Management
  • Project Management
  • V. Insurance Requirements if awarded a project
    (all in bid documents)
  • a. Commercial General Liability (CGL)
  • b. Automobile Owned/Non-owned
  • c. Workers Compensation
  • d. Builders Risk or Installation Floater
  • e. Owners Contractors Protective Liability
    (OCP)

16
  • VI. Bonds required if awarded a project
  • a. Performance Bonds 100 of the contract price
  • Payment Bonds 50 of the contract price
  • VII. Payments during the project through
    close-out
  • a. Materials UA pays direct to achieve Sales
    Tax savings
  • b. GC monthly draws
  • i. Once a month during project
  • ii. Retainage
  • 1. 5 of adjusted contract amount until 50
    complete
  • 2. 2.5 from 51 - 100 complete
  • c. Closeout of project
  • i. Must provide closeout documents agreed on at
    beginning of project (standard closeouts)
  • ii. Must advertise in Tuscaloosa News for 4
    consecutive weeks
  • iii. After all closeouts received and punchlist
    items are approved by Architect and 4 weeks
    advertising is d one GC may submit final pay
    request for retainage