Project Planning PowerPoint PPT Presentation

presentation player overlay
1 / 15
About This Presentation
Transcript and Presenter's Notes

Title: Project Planning


1
Project Planning
  • Eugene Lai
  • Nottingham Trent University

2
Starting to Plan
Objectives / quality constraints
Cost and resource constraints
Time constraints
3
Elements of a Plan
  • Work breakdown with
  • clear deliverables
  • Project Activities
  • Dependencies
  • Resource Estimates - persondays - Mb
  • Activity Schedules
  • Risk Analysis
  • Quality Plan

4
Steps Involved
  • Decide the tasks
  • Understand dependencies
  • Estimate tasks
  • Schedule
  • Assess risks
  • Iterate

5
Deciding the Tasks
Project
Design
Program Coding
Testing
Prog Prog Prog A B
C
Prog Prog Prog A B
C
Prog Prog Prog A
B C
A work breakdown structure Tasks defined
goals clear Particular skills /
resources Duration
Contingency
6
Process Of Decomposition
  • Guidelines
  • Method of evaluating task completeness
  • Tasks clearly defined
  • Tasks should be assigned to very few people
  • Time duration short enough to monitor
  • Task cohesion (same type of work)
  • Minimise task coupling (interdependency)

7
Estimating is Important Why ?
  • To determine feasibility
  • Calculate when and at what cost a system can be
    delivered
  • Deciding on staffing policies and how to carry
    out a project
  • Inaccurate estimates can affect
  • the ability to control and deliver the
  • system on time and to budget
  • all subsequent stages

8
Methods for Estimating
Known factors
Estimate
  • Standard methods e.g. Function Point COCOMO
  • PERT weighted average (A4BC)/6
  • Ratios high level (phases) low level (tasks)
  • Standard Estimates
  • Fixed / Multiplied by number of items
  • Based on complexity / size
  • Multiple Estimate compare and contrast
  • Evolution of a local model

9
Scheduling
  • Gantt (bar) Chart
  • What to be done
  • Who will do it
  • When it will be done
  • Activity Network
  • Inter-dependencies
  • Estimated Effort
  • Resource Matrix
  • Skills/resources required
  • Under/over utilisation
  • Used to smooth team size

10
Gantt Chart
Tasks
Time
Week 1 Week 2 Week 3
11
Network Analysis Diagrams
  • Activity on
  • the arrow
  • Activity on
  • the node

12
Dependencies
  • Four types
  • FinishStart
  • StartStart
  • FinishFinish
  • Partial Finishstart

13
Network Analysis
  • Steps
  • Establish sequence
  • Timetable for each job
  • Analysing spare time
  • Identifying most critical jobs

14
Network Conventions
Start and Finish Events single start activity
and
completion activity
  • Left to right Dependencies

No Dangling Events
No Looping
Avoid Redundancy
15
Example Node
Earliest Start Time
estimated DURation
  • SLacK
  • (LST EST)

Latest Start Time
Write a Comment
User Comments (0)
About PowerShow.com