THE WASA LTCP CONSENT DECREE - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

THE WASA LTCP CONSENT DECREE

Description:

THE WASA LTCP CONSENT DECREE. STRATEGIES EMPLOYED TO ACHIEVE A FAIR AND ... AVIS MARIE RUSSELL. GENERAL COUNSEL. DISTRICT OF COLUMBIA WATER AND SEWER AUTHORITY ... – PowerPoint PPT presentation

Number of Views:49
Avg rating:3.0/5.0
Slides: 21
Provided by: veja
Category:
Tags: consent | decree | ltcp | the | wasa | avis

less

Transcript and Presenter's Notes

Title: THE WASA LTCP CONSENT DECREE


1
THE WASA LTCP CONSENT DECREE
  • STRATEGIES EMPLOYED TO ACHIEVE A FAIR AND
    BALANCED LONG TERM CSO CONTROL PLAN
    IMPLEMENTATION MECHANISM FOR THE DISTRICT OF
    COLUMBIA

AVIS MARIE RUSSELL GENERAL COUNSEL DISTRICT OF
COLUMBIA WATER AND SEWER AUTHORITY
2
WHAT WERE THE KEY INGREDIENTS?
  • A technically sound, economically feasible, and
    legally defensible long -term control plan
  • Well-developed legal defenses
  • An overall strategy that narrowed the case to the
    issues that WASA was prepared to litigate
  • Bottom-line goals and objectives that had to
    be met in the settlement

3
WHAT WERE THE KEY INCREDIENTS? (cont)
  • Involvement by decision makers and respected
    neutral parties at critical stages in the
    negotiations
  • Continued trial preparation throughout the
    negotiations

4
WASAS LONG TERMCONTROL PLAN
  • Developed in strict accordance with the CSO
    policy following an extensive stakeholder process
  • Consists of a system of tunnels, pumping
    stations, upgrades to Blue Plains, sewer
    separation, and low impact development
  • Provides for incremental CSO reductions during
    implementation with ultimate volume reductions of
    97.5 for the Anacostia, 92.5 for the Potomac,
    and 89.8 for Rock Creek during average year
    rainfall conditions

5
WASAS LONG TERM CONTROL PLAN (cont)
  • Provides for compliance with water quality
    standards, and, therefore, meets the
    Demonstration Approach under the CSO policy
  • Planning level cost estimate - 1.265 million
    (2001 dollars)
  • LTCP gave us the confidence to proceed to trial,
    if necessary
  • We knew that if the case went to trial, the Court
    would not fashion its own remedy (i.e., its own
    LTCP)

6
WASAS LONG TERM CONTROL PLAN (cont)
  • Penalties were not a major consideration
  • Penalty exposure was minor compared to the
    potential consequences of a bad consent decree.
  • WASA had substantial defenses to penalties.

7
LEGAL DEFENSES
  • WASA was committed to implement its LTCP, and,
    therefore, accepted this as a legal obligation
  • But, WASA was not prepared to agree that its CSO
    discharges violated the Clean Water Act or that a
    consent decree was the appropriate LTCP
    implementation mechanism
  • WASA developed legal defenses based upon

8
LEGAL DEFENSES (cont)
  • Clean water act 402 (q)
  • D.C. water quality standards
  • WASA permit language
  • These legal defenses, the LTCP, and our
    commitment to litigate, if necessary, gave us the
    leverage needed to narrow the case for trial and
    ultimately, settle the case on favorable terms

9
AGREEMENTS WERE MADE TO NARROW THE CASE AS IT
PROCEEDED TOWARD TRIAL
  • Issues that were resolved through partial
    settlement and stipulation
  • Partial consent decree resolved nine minimum
    controls issues
  • The parties stipulated that the LTCP was the
    appropriate remedy for the alleged violations
  • WASA stipulated that is was legally obligated to
    implement the LTCP
  • The plaintiffs agreed to waive any claims for
    penalties

10
AGREEMENTS WERE MADE TO NARROW THE CASE AS IT
PROCEEDED TOWARD TRIAL (cont)
  • Issues that were left for trial
  • Whether, subject to post-construction monitoring,
    the LTCP would comply with water quality
    standards following implementation
  • The appropriate LTCP implementation schedule

11
WASA HAD SEVERAL BOTTOM LINE GOALS AND
OBJECTIVES THAT HAD TO BE MET IN ANY SETTLEMENT
  • A written determination from both the District
    and EPA that, subject to post-construction
    monitoring, WASAS LTCP would comply with water
    quality standards following implementation
  • An implementation schedule that met the following
    criteria
  • Overall schedule that was long enough to avoid
    steep rate increases over the life of the
    schedule.

12
WASA HAD SEVERAL BOTTOM LINE GOALS AND
OBJECTIVES THAT HAD TO BE MET IN ANY SETTLEMENT
(cont)
  • Phased schedule that addressed the Anacostia
    first, and also
  • Minimized increased costs due to excessive
    demands on available management, engineering and
    construction resources.
  • Provided opportunities to achieve efficiencies
    and cost savings from lessons learned in earlier
    phases.

13
WASA HAD SEVERAL BOTTOM LINE GOALS AND
OBJECTIVES THAT HAD TO BE MET IN ANY SETTLEMENT
(cont)
  • Flexibility to modify the LTCP or schedule in
    response to new or unanticipated developments
    that materially changed any of the assumptions
    underlying the LTCP or LTCP schedule
  • WASA wanted a 30-year schedule if there was
    little flexibility to modify it, but was prepared
    to compromise on the schedule in return for the
    flexibility to modify both the LTCP and the
    schedule
  • Protection against future citizen suits

14
INVOLVEMENT BY DECISION MAKERS AND RESPECTED
NEUTRAL PARTIES
  • Negotiations ended in the spring of 2004 when DOJ
    and EPA refused to make a standards compliance
    determination, refused to agree to a schedule
    longer than 20 years, and would agree only to
    their standard consent decree modification
    language
  • Discovery proceeded through summer of 2004 with
    over 1.5 million pages of documents processed and
    reviewed
  • Catalyst to resumed negotiations in September
    2004 was involvement by top DOJ, EPA, DC, and
    WASA officials at the urging of a respected
    member of DCs environmental community

15
WASA CONTINUED TRIAL PREPARATION DURING THE
RESUMED NEGOTIATIONS
  • Document production, written discovery, and
    preparation of expert reports continued until it
    became apparent that the case would settle
  • Depositions were postponed, but not cancelled,
    when there was agreement on a settlement
    framework
  • The trial date was retained on the courts docket
    until final agreement on the consent decree

16
THE FINAL PRODUCT
  • Phase II permit issued containing the water
    quality standards compliance determination and
    performance standards sought by WASA
  • Twenty-year phased schedule in consent decree
  • Anacostia projects to be completed first, then
    Potomac projects, followed by Rock Creek projects
  • Phasing has several benefits
  • Most serious water quality problems addressed
    first.

17
THE FINAL PRODUCT (cont)
  • Allows WASA to benefit from knowledge and
    experience gained in earlier phases and move to
    modify LTCP and schedule, if necessary.
  • Accommodates possible modification to Rock
    Creek projects based on experience with LID.
  • Avoids over-extending available management,
    engineering and construction resources.
  • Only two enforceable interim milestones for each
    project

18
THE FINAL PRODUCT (cont)
  • Consent decree recites that the 20-year schedule
    is based on current information, assumptions and
    financial and other projections, and permits WASA
    to move for modification of the LTCP or schedule
    based on a significant change in the current
    assumptions or projections, whether or not the
    change was anticipated
  • Consent decree incorporates all of the current
    assumptions and projections that are the bases
    for the LTCP and 20-year schedule

19
THE FINAL PRODUCT (cont)
  • Twenty-year schedule financial assumptions do not
    include projects such as nitrogen control and
    improvements to the collection system that are
    not in the current CIP
  • Administrative process for resolving disputes
    over proposed modifications with the following
    two important features
  • Imposes deadlines on EPA to act
  • Provides for de novo review by court of
    disputes arising out of modification requests

20
THE FINAL PRODUCT (cont)
  • - Consent decree contains a re-bid clause which
    allows WASA to re-bid construction contracts and
    avoid penalties for failing to meet interim
    deadlines
  • Consent Decree contains language designed to help
    ensure that it will be deemed diligent
    prosecution as a defense against future citizen
    suits
Write a Comment
User Comments (0)
About PowerShow.com