Title: THE WASA LTCP CONSENT DECREE
1THE WASA LTCP CONSENT DECREE
- STRATEGIES EMPLOYED TO ACHIEVE A FAIR AND
BALANCED LONG TERM CSO CONTROL PLAN
IMPLEMENTATION MECHANISM FOR THE DISTRICT OF
COLUMBIA
AVIS MARIE RUSSELL GENERAL COUNSEL DISTRICT OF
COLUMBIA WATER AND SEWER AUTHORITY
2WHAT WERE THE KEY INGREDIENTS?
- A technically sound, economically feasible, and
legally defensible long -term control plan - Well-developed legal defenses
- An overall strategy that narrowed the case to the
issues that WASA was prepared to litigate - Bottom-line goals and objectives that had to
be met in the settlement
3WHAT WERE THE KEY INCREDIENTS? (cont)
- Involvement by decision makers and respected
neutral parties at critical stages in the
negotiations - Continued trial preparation throughout the
negotiations
4WASAS LONG TERMCONTROL PLAN
- Developed in strict accordance with the CSO
policy following an extensive stakeholder process
- Consists of a system of tunnels, pumping
stations, upgrades to Blue Plains, sewer
separation, and low impact development - Provides for incremental CSO reductions during
implementation with ultimate volume reductions of
97.5 for the Anacostia, 92.5 for the Potomac,
and 89.8 for Rock Creek during average year
rainfall conditions
5WASAS LONG TERM CONTROL PLAN (cont)
- Provides for compliance with water quality
standards, and, therefore, meets the
Demonstration Approach under the CSO policy - Planning level cost estimate - 1.265 million
(2001 dollars) - LTCP gave us the confidence to proceed to trial,
if necessary - We knew that if the case went to trial, the Court
would not fashion its own remedy (i.e., its own
LTCP)
6WASAS LONG TERM CONTROL PLAN (cont)
- Penalties were not a major consideration
- Penalty exposure was minor compared to the
potential consequences of a bad consent decree. - WASA had substantial defenses to penalties.
7LEGAL DEFENSES
- WASA was committed to implement its LTCP, and,
therefore, accepted this as a legal obligation - But, WASA was not prepared to agree that its CSO
discharges violated the Clean Water Act or that a
consent decree was the appropriate LTCP
implementation mechanism - WASA developed legal defenses based upon
8LEGAL DEFENSES (cont)
- Clean water act 402 (q)
- D.C. water quality standards
- WASA permit language
- These legal defenses, the LTCP, and our
commitment to litigate, if necessary, gave us the
leverage needed to narrow the case for trial and
ultimately, settle the case on favorable terms
9AGREEMENTS WERE MADE TO NARROW THE CASE AS IT
PROCEEDED TOWARD TRIAL
- Issues that were resolved through partial
settlement and stipulation - Partial consent decree resolved nine minimum
controls issues - The parties stipulated that the LTCP was the
appropriate remedy for the alleged violations - WASA stipulated that is was legally obligated to
implement the LTCP - The plaintiffs agreed to waive any claims for
penalties
10AGREEMENTS WERE MADE TO NARROW THE CASE AS IT
PROCEEDED TOWARD TRIAL (cont)
- Issues that were left for trial
- Whether, subject to post-construction monitoring,
the LTCP would comply with water quality
standards following implementation - The appropriate LTCP implementation schedule
11WASA HAD SEVERAL BOTTOM LINE GOALS AND
OBJECTIVES THAT HAD TO BE MET IN ANY SETTLEMENT
- A written determination from both the District
and EPA that, subject to post-construction
monitoring, WASAS LTCP would comply with water
quality standards following implementation - An implementation schedule that met the following
criteria - Overall schedule that was long enough to avoid
steep rate increases over the life of the
schedule.
12WASA HAD SEVERAL BOTTOM LINE GOALS AND
OBJECTIVES THAT HAD TO BE MET IN ANY SETTLEMENT
(cont)
- Phased schedule that addressed the Anacostia
first, and also - Minimized increased costs due to excessive
demands on available management, engineering and
construction resources. - Provided opportunities to achieve efficiencies
and cost savings from lessons learned in earlier
phases.
13WASA HAD SEVERAL BOTTOM LINE GOALS AND
OBJECTIVES THAT HAD TO BE MET IN ANY SETTLEMENT
(cont)
- Flexibility to modify the LTCP or schedule in
response to new or unanticipated developments
that materially changed any of the assumptions
underlying the LTCP or LTCP schedule - WASA wanted a 30-year schedule if there was
little flexibility to modify it, but was prepared
to compromise on the schedule in return for the
flexibility to modify both the LTCP and the
schedule - Protection against future citizen suits
14INVOLVEMENT BY DECISION MAKERS AND RESPECTED
NEUTRAL PARTIES
- Negotiations ended in the spring of 2004 when DOJ
and EPA refused to make a standards compliance
determination, refused to agree to a schedule
longer than 20 years, and would agree only to
their standard consent decree modification
language - Discovery proceeded through summer of 2004 with
over 1.5 million pages of documents processed and
reviewed - Catalyst to resumed negotiations in September
2004 was involvement by top DOJ, EPA, DC, and
WASA officials at the urging of a respected
member of DCs environmental community
15WASA CONTINUED TRIAL PREPARATION DURING THE
RESUMED NEGOTIATIONS
- Document production, written discovery, and
preparation of expert reports continued until it
became apparent that the case would settle - Depositions were postponed, but not cancelled,
when there was agreement on a settlement
framework - The trial date was retained on the courts docket
until final agreement on the consent decree
16THE FINAL PRODUCT
- Phase II permit issued containing the water
quality standards compliance determination and
performance standards sought by WASA - Twenty-year phased schedule in consent decree
- Anacostia projects to be completed first, then
Potomac projects, followed by Rock Creek projects - Phasing has several benefits
- Most serious water quality problems addressed
first. -
17THE FINAL PRODUCT (cont)
- Allows WASA to benefit from knowledge and
experience gained in earlier phases and move to
modify LTCP and schedule, if necessary. - Accommodates possible modification to Rock
Creek projects based on experience with LID. - Avoids over-extending available management,
engineering and construction resources. - Only two enforceable interim milestones for each
project
18THE FINAL PRODUCT (cont)
- Consent decree recites that the 20-year schedule
is based on current information, assumptions and
financial and other projections, and permits WASA
to move for modification of the LTCP or schedule
based on a significant change in the current
assumptions or projections, whether or not the
change was anticipated - Consent decree incorporates all of the current
assumptions and projections that are the bases
for the LTCP and 20-year schedule
19THE FINAL PRODUCT (cont)
- Twenty-year schedule financial assumptions do not
include projects such as nitrogen control and
improvements to the collection system that are
not in the current CIP - Administrative process for resolving disputes
over proposed modifications with the following
two important features - Imposes deadlines on EPA to act
- Provides for de novo review by court of
disputes arising out of modification requests
20THE FINAL PRODUCT (cont)
- - Consent decree contains a re-bid clause which
allows WASA to re-bid construction contracts and
avoid penalties for failing to meet interim
deadlines - Consent Decree contains language designed to help
ensure that it will be deemed diligent
prosecution as a defense against future citizen
suits