Title: April 15, 2004
1Recent ASR Developments in Southwest Florida
Presented at the American Ground Water Trust
Aquifer Storage Recovery IV Tampa, Florida
Presented by Mark McNeal, PG /CH2M HILL
April 15, 2004
2Three primary types of ASR projects are in
operation in Southwest Florida
- Potable Water ASR
- Reclaimed Water ASR
- Partially Treated Surface Water ASR
3ASR Projects in Southwest Florida
Potable Water ASR Project
Reclaimed Water ASR Project
Partially Treated Surface Water ASR Project
4Select Southwest Florida Potable Water ASR
Projects
- Peace River/Manasota Regional Water Supply
Authority - Manatee County
- City of Tampa
- City of Bradenton
- City of Fort Myers
- City of Punta Gorda
- Bonita Springs Utilities
Bonita Springs Utilities
5Manatee County had the first ASR wells to come on
line in Florida
- Two ASR wells completed in 1983 at Lake Manatee
- Stores treated surface water from the Manatee
River - Storage zone is relatively fresh, at upper limits
of drinking water
- Recently expanded to 6 wells
- Approximately 10 mgd ASR capacity
- Demonstrates success of ASR in this area
6The Peace River Facility relies on its ASR system
to meet its dry weather demands
7The Peace River system is another ASR success
story in SW Florida
- Largest ASR system in eastern US
- Additional expansion underway - up to 26
additional ASR wells
PRMRWSA Boundary
S-1
S-2
WF1
T-1
AP-1
SR761
S-5R
S-3R
S-6
S-9R
Reservoir
S-7
S-8
Peace River
Railroad
WF2
Kings Highway (SR769)
8The older ASR wells were evaluated as the initial
step of the ASR expansion
- 16 years of operational data were reviewed to
determine effectiveness of ASR WF 1 - 2.5 BG of water was stored at the site, and 2 BG
was recovered over a 2-year period
9Storage zone selection is becoming an important
decision for many ASR facilities
- Many utilities are faced with a decision -
expand outward or utilize multiple zones - Competing users or impacts to sensitive surface
water bodies must be addressed - Recovery efficiencies will likely decrease as
deeper, more brackish zones are utilized - Certain zones may be more apt to experience
geochemical changes than others - Stacking wells may help control upconing
100 200 400 600 800 1000 1200 1400 1600
The Suwannee Zone is the primary storage interval
at the site
TDS (mg/L)
Geologic Unit
Hawthorn Group
1 mgd
1 mgd
Tampa Zone
500
3 mgd
900
Suwannee Zone
Depth in Feet
Ocala Limestone
Avon Park Formation
2900
11Six alternatives are being considered for 38 mgd
firm capacity
- Existing WUP scenario is a dispersed WF in the
Suwannee Zone - 5 other scenarios consider various spacings,
locations, and storage intervals
12Cost estimates were prepared for each of the
26-well ASR expansion scenarios
- The existing WUP layout was the most expensive
alternative at 17.3M - The other five scenarios ranged from 13.1M to
14.9M
- Construction costs equate to about 0.50 to 0.70
per mgd of ASR capacity - Assuming 100 MG storage per well, 5k to 7k /MG
stored
13Care must be taken that future expansions do not
impact existing ASR well performance
14Tampas ASR system is important to west-central
Florida
- Water resources are stressed in this area
- Alternative water supplies under development
- A successful ASR system would provide benefits
not only to the City, but to the region as well
- Tampa has constructed its initial system
- 8-well, 10 mgd system
- Constructed in an urban setting
- Tampa is exploring ASR expansion options in the
Avon Park Fm
15The City of Tampa has faced several challenges
with their ASR program
- Geology is leakier in this area relative to the
successful ASR systems to the south - Upconing of saline water from below occurs during
recovery - Other geochemical changes have also been observed
- Returning water to the WTP has allowed aggressive
recovery
ASR-1
Cycle 3
Cycle 2
Cycle 1
16Water Use Permitting has also been challenging
for Tampa
- Numerous domestic well owners (none have been
impacted) - Potential for sinkholes in an urban area (none)
- Lake level responses
- Urban wetlands?
- Withdrawal schedule to allow recharge
- How to bank water during wet years to recover
during dry yrs - Rolling avg not allowed
- Fluctuating chloride concentrations in ASR wells
and MWs
17Chloride concentrations show temporary response
during recovery
- Chloride in nearby storage zone MWs increases
from 20 to as high as 850 mg/L
- Once recharge begins, storage zone freshens
- No noticeable impact to shallow (domestic) zone -
no impacts to adjacent users
18Tampa has also has had many successes...
- Able to co-exist with residents
- No impacts to private well owners
- No sinkholes linked to ASR pumpage
- No ASR-related impacts to neighborhood
- Lake level responses not typical ofgroundwater
production in this area - Surficial water level impacts insignificant
- attributed to deeper well casing settingsand
cyclical nature of ASR operations - Able to provide about 15 percent of the Citys
water supply during the 2000-2002 drought - CO2 treatment to increase ASR well capacity
19Tampas carbon dioxide treatment has effectively
replaced well acidization
- Initial investment of about 1,000 for CO2
equipment - Now costs about 100 per CO2 event vs. 25k-30k
for acidization
- No by-products requiring disposal
- No chloride increase _at_ ASR wells
- No pump removal
- No kidding
- Increased injectivity from less than 1 to 40
gpm/psi - 10 MG recharged in 1 week vs. 3 months
2nd CO2 application
Post-CO2
Pre-CO2
20Status of Southwest Florida reclaimed water ASR
projects
- Operational testing has been initiated
- Englewood Water District Hillsborough Co.
- Constructed and ready to start testing
- St. Petersburg Manatee County
- Others permitted to construct systems
- City of Sarasota, Lehigh Acres
- In the feasibility study/permitting phase
- Sarasota Co., Pinellas Co., Clearwater, Largo,
and others
21Englewoods reclaimed water ASR system is
undergoing testing
- Permit issued in 1999 - renewal underway
- System constructed at WWTP in 2000
- Storage zone 500 to 700 feet bls
- Storage zone was saline (20,000 mg/L TDS)
- Began operational testing in July 2001
- Required a WQCE for color - other drinking water
standards were met - Initial cycle testing has been limited but is
encouraging
22Cycle testing has posed challenges for EWD
- The WWTP was a zero discharge facility, with
reuse accounting for all discharges - EWD is sewering the area, with flows increasing
significantly - Additional reuse customers have been brought
online within the past year - EWD has 500 MG in storage, as reuse demand has
not kept up with supply
- Timing can be challenging for reclaimed water ASR
- Cant add reuse customers without ASR
- Cant test w/o sufficient reuse demand
- Result A deep injection well was constructed
- Will allow EWD to perform more aggressive cycle
testing - Some water will be wasted to confirm well
performance
23The City of St. Petersburgs ASR program is unique
- Located at its Southwest WRF
- Couples ASR with DIW system
- Freshening in overlying zones
- Storage zone previously 30,000 mg/L TDS, now
5,000 mg/L TDS - Solute transport modeling suggests this will
improve early recovery efficiency from 3 to an
estimated 35 - Recovery endpoint expected to be 1500-2000 mg/L
TDS - Testing expected to begin soon
St. Petersburg ASR site
Solute Transport Model Output
24Summary
- ASR systems are alive and well in Southwest FL
- ASR allows effective use of our major rivers
- Approximately 40 mgd capacity among top 3 potable
water ASR systems in southwest FL, with several
other smaller ASR systems as well - Reclaimed water ASR projects are advancing due to
the importance of reuse in the area and the
seasonal variations between supply and demand - Only one partially treated surface water ASR site
is in operation, but others are anticipated in
the future - Although each program has its challenges, ASR
remains a very cost effective, safe alternative
water supply option with significant importance
to SW FL