CREATIVE SOLUTIONS TO PPP RISKS Presented by: Jeremy Terndrup - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

CREATIVE SOLUTIONS TO PPP RISKS Presented by: Jeremy Terndrup

Description:

Public Private Partnership (PPP) is an alternative to standard public sector ... LAD interface with ALOP. Latent Defects. Environmental/Contamination issues ... – PowerPoint PPT presentation

Number of Views:131
Avg rating:3.0/5.0
Slides: 26
Provided by: jeremyt6
Category:

less

Transcript and Presenter's Notes

Title: CREATIVE SOLUTIONS TO PPP RISKS Presented by: Jeremy Terndrup


1
CREATIVE SOLUTIONS TO PPP RISKSPresented
byJeremy Terndrup Vyacheslav Andriyko

2
What is PPP?
Public Private Partnership (PPP) is an
alternative to standard public sector procurement
of capital assets by up-front payment. PPP can
be described as, An agreement between a Public
and Private Entity in which a Private Entity
delivers goods or services under the Public
Entities Regulatory Authority for a financial
return. A typical PPP structure involves the
creation of a single stand-alone company/business
financed and operated by the private sector. The
purpose is to create the asset and then deliver
the service to the public sector in return for
payment equal to the service levels provided.
3
New concept?
  • UK first to develop the PFI concept as is known
    today, but..
  • the concept of a working partnership between the
    private sector and public bodies is well
    established. Compagnie Generale des Eaux,
    launched in 1853 and the founders of the Veoila
    Environment, was contracted to supply water to
    the city of Lyons. The company was awarded a 50
    year contract to supply water to Paris in 1860.

4
PPP Model an example
The consortium company joint venture model
Government Customer
Operation
Finance
Construction investor
Services delivered in return for annual charge
Equity and sub debt finance
Facilities mgmt (FM) investor
Procuring Authority/ Public Agency, and ongoing
users of public services
Special Purpose Vehicle
Unitary charge payment
3rd party equity investor
Carried out under contract
Debt finance
Debt investor
Construction contractor
Facilities mgmt (FM) operator
5
Why is PPP needed?
There are 2 key objectives in commissioning a PPP
Project
  • Maximise value for money (VFM) of providing
    service over a long timescale of 20-30 years or
    more having taken account of all the risks.
    Maximising efficiency and innovation is key to
    achieving VFM.
  • Enable public sector to procure services in a
    manner consistent with economic policy in
    particular where public sources of funding are
    lacking/in short supply.

6
Benefits of PPP
  • Relieve Public sector cash constraints
  • PPP allows public and private sectors to
    concentrate on activities that best suit their
    respective skills
  • Procurement efficiency
  • Improved accountability
  • Risk management
  • Enhance quality and quantity of infrastructure

7
UK PPP/PFI experience
  • The Private Finance Initiative (PFI) was launched
    by UK Treasury in 1992
  • Applied to a wide range of projects (road, rail,
    tram, rail, airport, hospital, IT, telecoms,
    water, sewage, military, prisons etc)
  • Now accounts for 10-15 of public services budget
  • 630 UK PFI projects
  • 40 billion investment
  • UK model is being applied (in modified forms)
    throughout Europe

8
PPP/PFI Credentials some examples
  • Home Office HQ PFI project in the UK - value
    311 million
  • Sydney Harbour Tunnel project first major
    transport PFI in Australia
  • Cyprus Airports BOT project scheme closed 20
    years after first mooted, reserve bidder stepped
    in
  • A41 France motorway PPP project 55 year tenor
    worth 941million
  • Port of Miami Tunnel (POMT) and access
    improvement PPP project value 1 billion

9
Responsibility
10
The Insurance Schedule and Insuring Clauses
within the Concession and Loan Agreements
  • The Minimum Insurance Requirement Schedule within
    Concession and Loan Agreements details the
    required insurances to be procured during the
    phases of the project e.g. construction and
    operational
  • The Schedule defines the operative cover, policy
    limits, levels of deductible, principal
    extensions and exclusions based on prevailing
    insurance market conditions
  • The Schedule contains a Broker Letter of
    Undertaking (BLU) providing undertakings on
    behalf of the placing Broker
  • The insurance clauses define the regime and
    mechanism under which the required insurances
    operate for the Project period

11
Key PPP Project Insurances
  • Insurance requirements on a co-insured basis
    during the construction phase

12
Key PPP Project Insurances (contd)
  • Insurance requirements on a co-insured basis
    during operational phase
  • Operational Period
  • Property Damage All Risks
  • Property Damage All Risks Terrorism
  • Business Interruption
  • Business Interruption Terrorism
  • Third Party Public and Products Liability
  • Statutory Insurances (Workers Compensation/EL -
    not co-insured)
  • Pollution Legal Liability
  • Auto Liability
  • Depending on the nature of the project, there may
    be a requirement for
  • specialist project related insurances e.g.
    Aviation, MARINE, Professional
  • Liability (operational)

13
Why are these insurances required?
  • They protect the Public Agency, SPV, Lenders and
    other parties with an insurable interest in
    respect of
  • physical loss or damage to Project
    property/assets
  • earnings and additional costs of the SPV in
    respect of the above
  • incurred Third Party Legal Liabilities (bodily
    injury and property damage)
  • Without insurance the SPV could not accept the
    financial consequences of such risk events
    occurring

14
Role of Insurance
  • Means of Risk Transfer SPV is constrained to a
    much greater degree in terms of manner in which
    it can adopt its business to prevailing risk
    environment. Insurance is a tool used for the
    transfer of risk.
  • Coverage will generally be bought on a wide basis
    with low deductibles to ensure minimum risk is
    retained at SPV level.
  • Project Insurances relied upon by main project
    related parties as a key mechanism for the
    management of risk.

15
Why is the insurance regime under PPP different
to standard procurement?
  • The Public Agency, Lenders and others with an
    insurable interest sit inside the insurance
    mechanism as a co-insured taking direct benefit
    for their separate insurable interest
  • Insurances to be procured on a project specific
    basis (in the main) and not derived from parent
    company programme.
  • Public Agency guidelines and Lender requirements
    seek to ensure specific conditions are in place
    defining the duties of the parties to the Project
    in terms of the operation of the required
    insurances

16
What are the key conditions of a PPP insurance
regime?
  • Non vitiation protection (Multiple Insured
    Clause)
  • Waiver of subrogation (Multiple Insured Clause)
  • Separate policy
  • Waiver of disclosure of material information
  • No obligation for premium payment
  • Additional insured
  • Control of claim monies (Loss Payee)
  • Notification of change in cover
  • Notice of cancellation and subsequent step in
    rights of various parties to the Project

17
PPP Insurances considerations solutions
  • Relief Events and Force Majeure
  • Premium increases who bears the risk?
  • Insurance market capacity and market participants
  • Uninsurability
  • Excesses/Deductibles who pays?
  • Bid costs funding bid process sunk cost,
    which can amount to million per project
  • Meeting bid/tender requirements - what level of
    information is required insurance proposals
    must remain fluid and negotiable until final
    design and construction timetable is known
  • Cost of insurance provision for cost of
    insurance in the Financial Model prevailing
    market cost contingency amounts

18
PPP Insurances considerations solutions
  • Phased completion timetable
  • Overlap of ALOP/BI
  • Pre-existing property
  • LAD interface with ALOP
  • Latent Defects
  • Environmental/Contamination issues
  • Contractors plant and equipment
  • Terrorism risk
  • Marine/Transit

19
PPP Insurances considerations solutions
  • Premiums Who bears the risk?
  • Firm Pricing Is it achievable?
  • Alternatives
  • Cap and Collar premium movement mechanism
  • Firm Price X years RPIX thereafter
  • Benchmarking annual pass through cost
  • Public Agency Related Claims increasing premiums.
    Who bears this risk how is it stipulated within
    the Concession Agreement?

20
PPP Insurances considerations solutions
  • Insurance Market Capacity
  • Size and nature of risk exposures
  • Market security issues
  • Importance of quality risk data
  • Number of Market participants

21
PPP Insurances considerations solutions
  • Uninsurability
  • Uninsurability
  • Definition of trigger of Uninsurability what is
    the test?
  • What happens to the risk if it becomes
    uninsurable (Termination/Public Agency insurer
    of last resort)

22
PPP Insurances considerations solutions
  • Deductibles Who pays?
  • Public Agency accepts no liability?
  • Public Agency liability for Public Agency default
    and/or negligence only (Public Agency Related
    Claims)
  • Must link to general Indemnity provisions

23
What does this mean for the project insurances?
  • Contractor/Lender uncertainty over the risk of
    insurance cost and availability
  • Fear of the unknown from insurers on contractual
    requirements of PPP
  • No established insurance market experience of
    some risk exposures through PPP contracts
  • Unpredictable insurance market cycles
  • Sector specific claims impacting on competitive
    terms and also cost provision in Financial Model
  • Short term underwriting stance for both cover
    provision and pricing

24
PPP Project Insurances working examples
  • Project Insurance Package making the package
    fit with the contractual obligations and the
    financial model to the Lenders and Government
    Agency satisfaction
  • Structure of Project Insurance Package where
    project affordability is an issue
  • Covering off unidentified risks through an
    insurance solution to ensure bankability of
    project
  • Utilisation of premium efficiencies via Annual
    Insurance Programmes

25
An Introduction to PPP
  • Questions?
Write a Comment
User Comments (0)
About PowerShow.com