Title: CREATIVE SOLUTIONS TO PPP RISKS Presented by: Jeremy Terndrup
1CREATIVE SOLUTIONS TO PPP RISKSPresented
byJeremy Terndrup Vyacheslav Andriyko
2What is PPP?
Public Private Partnership (PPP) is an
alternative to standard public sector procurement
of capital assets by up-front payment. PPP can
be described as, An agreement between a Public
and Private Entity in which a Private Entity
delivers goods or services under the Public
Entities Regulatory Authority for a financial
return. A typical PPP structure involves the
creation of a single stand-alone company/business
financed and operated by the private sector. The
purpose is to create the asset and then deliver
the service to the public sector in return for
payment equal to the service levels provided.
3New concept?
- UK first to develop the PFI concept as is known
today, but.. - the concept of a working partnership between the
private sector and public bodies is well
established. Compagnie Generale des Eaux,
launched in 1853 and the founders of the Veoila
Environment, was contracted to supply water to
the city of Lyons. The company was awarded a 50
year contract to supply water to Paris in 1860.
4PPP Model an example
The consortium company joint venture model
Government Customer
Operation
Finance
Construction investor
Services delivered in return for annual charge
Equity and sub debt finance
Facilities mgmt (FM) investor
Procuring Authority/ Public Agency, and ongoing
users of public services
Special Purpose Vehicle
Unitary charge payment
3rd party equity investor
Carried out under contract
Debt finance
Debt investor
Construction contractor
Facilities mgmt (FM) operator
5Why is PPP needed?
There are 2 key objectives in commissioning a PPP
Project
- Maximise value for money (VFM) of providing
service over a long timescale of 20-30 years or
more having taken account of all the risks.
Maximising efficiency and innovation is key to
achieving VFM. - Enable public sector to procure services in a
manner consistent with economic policy in
particular where public sources of funding are
lacking/in short supply.
6Benefits of PPP
- Relieve Public sector cash constraints
- PPP allows public and private sectors to
concentrate on activities that best suit their
respective skills - Procurement efficiency
- Improved accountability
- Risk management
- Enhance quality and quantity of infrastructure
7UK PPP/PFI experience
- The Private Finance Initiative (PFI) was launched
by UK Treasury in 1992 - Applied to a wide range of projects (road, rail,
tram, rail, airport, hospital, IT, telecoms,
water, sewage, military, prisons etc) - Now accounts for 10-15 of public services budget
- 630 UK PFI projects
- 40 billion investment
- UK model is being applied (in modified forms)
throughout Europe
8PPP/PFI Credentials some examples
- Home Office HQ PFI project in the UK - value
311 million - Sydney Harbour Tunnel project first major
transport PFI in Australia - Cyprus Airports BOT project scheme closed 20
years after first mooted, reserve bidder stepped
in - A41 France motorway PPP project 55 year tenor
worth 941million - Port of Miami Tunnel (POMT) and access
improvement PPP project value 1 billion
9Responsibility
10The Insurance Schedule and Insuring Clauses
within the Concession and Loan Agreements
- The Minimum Insurance Requirement Schedule within
Concession and Loan Agreements details the
required insurances to be procured during the
phases of the project e.g. construction and
operational - The Schedule defines the operative cover, policy
limits, levels of deductible, principal
extensions and exclusions based on prevailing
insurance market conditions - The Schedule contains a Broker Letter of
Undertaking (BLU) providing undertakings on
behalf of the placing Broker - The insurance clauses define the regime and
mechanism under which the required insurances
operate for the Project period
11Key PPP Project Insurances
- Insurance requirements on a co-insured basis
during the construction phase
12Key PPP Project Insurances (contd)
- Insurance requirements on a co-insured basis
during operational phase
- Operational Period
- Property Damage All Risks
- Property Damage All Risks Terrorism
- Business Interruption
- Business Interruption Terrorism
- Third Party Public and Products Liability
- Statutory Insurances (Workers Compensation/EL -
not co-insured) - Pollution Legal Liability
- Auto Liability
- Depending on the nature of the project, there may
be a requirement for - specialist project related insurances e.g.
Aviation, MARINE, Professional - Liability (operational)
13Why are these insurances required?
- They protect the Public Agency, SPV, Lenders and
other parties with an insurable interest in
respect of - physical loss or damage to Project
property/assets - earnings and additional costs of the SPV in
respect of the above - incurred Third Party Legal Liabilities (bodily
injury and property damage) - Without insurance the SPV could not accept the
financial consequences of such risk events
occurring
14Role of Insurance
- Means of Risk Transfer SPV is constrained to a
much greater degree in terms of manner in which
it can adopt its business to prevailing risk
environment. Insurance is a tool used for the
transfer of risk. - Coverage will generally be bought on a wide basis
with low deductibles to ensure minimum risk is
retained at SPV level. - Project Insurances relied upon by main project
related parties as a key mechanism for the
management of risk.
15Why is the insurance regime under PPP different
to standard procurement?
- The Public Agency, Lenders and others with an
insurable interest sit inside the insurance
mechanism as a co-insured taking direct benefit
for their separate insurable interest - Insurances to be procured on a project specific
basis (in the main) and not derived from parent
company programme. - Public Agency guidelines and Lender requirements
seek to ensure specific conditions are in place
defining the duties of the parties to the Project
in terms of the operation of the required
insurances
16What are the key conditions of a PPP insurance
regime?
- Non vitiation protection (Multiple Insured
Clause) - Waiver of subrogation (Multiple Insured Clause)
- Separate policy
- Waiver of disclosure of material information
- No obligation for premium payment
- Additional insured
- Control of claim monies (Loss Payee)
- Notification of change in cover
- Notice of cancellation and subsequent step in
rights of various parties to the Project
17PPP Insurances considerations solutions
- Relief Events and Force Majeure
- Premium increases who bears the risk?
- Insurance market capacity and market participants
- Uninsurability
- Excesses/Deductibles who pays?
- Bid costs funding bid process sunk cost,
which can amount to million per project - Meeting bid/tender requirements - what level of
information is required insurance proposals
must remain fluid and negotiable until final
design and construction timetable is known - Cost of insurance provision for cost of
insurance in the Financial Model prevailing
market cost contingency amounts
18PPP Insurances considerations solutions
- Phased completion timetable
- Overlap of ALOP/BI
- Pre-existing property
- LAD interface with ALOP
- Latent Defects
- Environmental/Contamination issues
- Contractors plant and equipment
- Terrorism risk
- Marine/Transit
19PPP Insurances considerations solutions
- Premiums Who bears the risk?
- Firm Pricing Is it achievable?
- Alternatives
- Cap and Collar premium movement mechanism
- Firm Price X years RPIX thereafter
- Benchmarking annual pass through cost
- Public Agency Related Claims increasing premiums.
Who bears this risk how is it stipulated within
the Concession Agreement?
20PPP Insurances considerations solutions
- Insurance Market Capacity
- Size and nature of risk exposures
- Market security issues
- Importance of quality risk data
- Number of Market participants
21PPP Insurances considerations solutions
- Uninsurability
- Uninsurability
- Definition of trigger of Uninsurability what is
the test? - What happens to the risk if it becomes
uninsurable (Termination/Public Agency insurer
of last resort)
22PPP Insurances considerations solutions
- Deductibles Who pays?
- Public Agency accepts no liability?
- Public Agency liability for Public Agency default
and/or negligence only (Public Agency Related
Claims) - Must link to general Indemnity provisions
23What does this mean for the project insurances?
- Contractor/Lender uncertainty over the risk of
insurance cost and availability - Fear of the unknown from insurers on contractual
requirements of PPP - No established insurance market experience of
some risk exposures through PPP contracts - Unpredictable insurance market cycles
- Sector specific claims impacting on competitive
terms and also cost provision in Financial Model - Short term underwriting stance for both cover
provision and pricing
24PPP Project Insurances working examples
- Project Insurance Package making the package
fit with the contractual obligations and the
financial model to the Lenders and Government
Agency satisfaction - Structure of Project Insurance Package where
project affordability is an issue - Covering off unidentified risks through an
insurance solution to ensure bankability of
project - Utilisation of premium efficiencies via Annual
Insurance Programmes
25An Introduction to PPP