Title: FY09 Tactical Plans for Database Services
1FY09 Tactical Plans forDatabase Services
2FY09 Tactical Plan for Database Services
- CD DocDB Document 2889-v1
- 2009 Tactical Plan Database Services
- Tactical Plan Leader J.Trumbo
- Organizational Unit home LSCS/DBI/DBA
3FY09 Tactical Plan Strategies and Goals
- Tactical Plan Strategies
- Develop stronger expertise and support for open
source databases, reducing the dependency on
Oracle, with a goal of reducing development and
support costs. - Tactical Plan Goals
- Continue to provide a stable, professional
operation of laboratory scientific and
information systems databases, providing maximum
uptime and technical support.
4FY09 Tactical Plan Objectives
- Tactical Plan Objectives
- 1. Database Systems Operations
- Support running experiments at appropriate
levels. - 2. Database Support.
- Promote Postgres and Oracle as a 1st tier
database and MS-SQL and MySQL as second-tier
databases. - Support production, integration and development
on all database platforms. Configure, tune, test,
and maintain databases. - 3. Agile response to new and rapid shifts of
responsibilities and demands accompanying the end
of Run II data taking and reduction of effort in
the Run II experiments.
5FY09 Tactical Plan Objectives
- 4. Kerberize Oracle using Advanced Security
Option. - 5. Maintain expertise for new features. Work with
databases on vm environments, oracle rac testing,
etc. - 6. Implement Oracle Internet Directory (OID).
- 7. Complete upgrade to Oracle 10 for the
information systems databases. - 8. Upgrade information systems hardware for
databases, including major apps, computer
security, 24.7 applications and nimi development.
- 9. Continued Deployment of the 3par San
technology. - 10. Ramp SDSS support down to maintenance levels.
6FY09 Tactical Plan Past Action Items
- Resolution of Past Action Items SDSS
- Planning hardware/software layouts for the next
DR7 and final DR8 releases. Obtaining new
machines and licenses promptly. Reconfigured
number of existing machines to meet our hardware
requirements for the future maintenance of the
SDSS machines to keep less machines in the rack. - Implemented 2 mirror sites for DR5 Data Release
in the Libraries of JHU and University of
Chicago. - SDSS team working close with team of the
librarians to setup SDSS help desk support using
new web application Question Point. - SDSS DBA team successfully completed transition
CasJobs web service from SQL2K to SQL2K5. - Completed incremental loading from DR6 to DR7.1
(BestDR7.1, TargDR7.1, SegueDR7.1 - total more
than 6TB data) and released it to the SDSS
collaboration on February 14 - two weeks early. - Working close with team of developers from JHU
and Princeton to implement and test new code
related to schema modifications for DR7.2 with
major changes in data model and merging
SegueDR7.1 to BestDR7.2. - Completed loading 3TB data into new database
Stripe82, this is a new - addition to the SDSS databases in respond to the
SDSS scientists to - merge stripe 82 runs into one database.
- Successfully upgraded 7TB RunsDB database from
SQLServer2000 to SqlServer 2005 environment. - Working constantly on SDSS documentation and
improving monitoring tools to maintain stable
production environment.
7FY09 Tactical Plan Past Action Items
- Resolution of Past Action Items Open Source
- To be clear, points below include effort from
sysadmins as well as dbas! - Established best practices, standards, how tos
for open source implementations. - Cross training as much as possible.
- Established postgres general purpose boxes for
dev/int/prd. Installed several users including
content_mgmt, ilc ground motion and edu office
lasso project dbs. - Took mgmt of mysql general purpose boxes. they
need work to upgrade and bring to stds, work is
pending. - Migrating support of gratia db to dba.
- Benchmarked MyISAM vs InnoDB engines for Gratia.
- Evaluated several backup products for mysql
operating under InnoDB engine. - Established nova dev/int/prd postgres boxes.
- Took over support of NIMI. Modifying to
standardized installs, upgrade os and db. - Continuing cross training of group. Attempted to
set up an onsite postgres class for developers
and dbas, but furloughs disrupted attendance
planning. - Assisted minerva with mysql and postgres installs
on general purpose boxes. - Established the Content Mgmt postgres database
dev/int/prd. - Still not quite transitioned minos production
mysql db to dba.
8Service Activity Database Support, including
Oracle, SqlServer Open Source
- Support running experiments at appropriate
levels, insure a stable, performant, and smooth
running environment. - Goals Related to this Activity
- Install, configure, and test new databases,
perform version upgrades of existing databases. - Administer and operate production and development
database information systems. - Participate in a 24x7 on-call rotation schedule
for production issues. - Perform database backups and data restores.
- Disaster recovery for databases.
- Replication
- Diagnose problems, and monitor database
performance. - Perform tuning of SQL queries.
- Install and configure Oracle Internet Directory
(OID) for Oracle v10 dbs.
9Service Activity Database Support
- Key Metrics
- Uptime Statistics
- http//www-css.fnal.gov/dsg/external/database_upti
me/ - http//www-css.fnal.gov/dsg/internal/SDSS/metrics/
metrics.htm - Issues and Risks (specific to this activity,
includes allocation impact) - Hardware failure
- Aging Hardware
10Project Activity Kerberosize Oracle with ASO
- Continue Kerberos for Oracle Implementation
- Goals Related to this Activity
- continue oracle aso kerberos project
- implement Kerberos authentication for DBA tasks
- install aso for users as needed
- define an action plan to support aso
- Key Milestones
- Implementation into production databases.
- Metrics, of kerberized dba tasks, of
kerberized user tasks - Issues and Risks (specific to this activity,
includes allocation impact) - Manpower
11Project Activity Complete Upgrade to Oracle 10
- Upgrade Infrastructure Databases (miscomp) to
Oracle 10 - Goals Related to this Activity
- os upgrade
- Information systems databases upgrade 10gR2
- Key Milestones
- Os upgrade, databases upgraded.
- Metrics, of instances upgraded
- Issues and Risks (specific to this activity,
includes allocation impact) - Application readiness
12Project Activity Upgrade Infrastructure Hardware
- Upgrade infrastructure with new hardware
- Goals Related to this Activity
- plan separation of information systems apps,
including 24.7 instances and misprod1. - plan for data movement to new databases
- Implement new databases, including oid repository
and new remedy.
- Key Milestones
- New hardware implementation successes
- Metrics, of upgraded
- Issues and Risks (specific to this activity,
includes allocation impact) - manpower
13Project Activity Migrate Databases to 3Par
- Move databases to 3Par array
- Goals Related to this Activity
- Move dev/int cdf offline databases to 3par to
replace aging and unsupported disk array. - Move dev/int d0 luminosity databases/snapshots to
3par to allow for a full and complete testing
environment. (complete) - Move fcdfora6 replica to 3par
- Assess and move if possible the cdf online
dev/int environments of aging array.
- Key Milestones
- Number of successful moves successes
- Metrics, uptime, saving on time and materials
repairs to unsupported hardware.Issues and Risks
(specific to this activity, includes allocation
impact) - Issues and Risks (specific to this activity,
includes allocation impact) - 3par readiness
14Project Activity SDSS to Maintenance Mode
- Ramp down SDSS to maintenance levels.
- Goals Related to this Activity
- Load and Release DR7
- Load and Release DR8
- Loading Runs Database
- Standardizing the Idrea Monitoring.
- Support the transition from SDSS operations to
long-term maintenance. - Consultancy JHU and UC for hosting DR5
- UC DR7 implementation
- Key Milestones
- Meet release dates
- Metrics, less time spent on SDSS, uptime stats
- Issues and Risks (specific to this activity,
includes allocation impact) - Manpower,
15FY09 Resource Request, Preliminary Allocation
Level 0 Activity Application Support
16Impact of Preliminary Allocation
- SDSS will be annually funded 60k for continuing
support. In addition 3 fte months are allotted
for Oct/Nov, Oct (2 ftes) completing public
release, Nov. (1fte) tying up loose ends. - Additional funding needs to be procured if DR7 at
U of C is to be completed, needing hardware and
manpower.
17Template Guidance (not part of the presentation)
- Activity Activity Level 1 or lower explicitly
listed in Tactical Plan - Activities have been classified in Tactical Plans
as either being more Project-like or Service-like - Projects finite defined lifetime, defined
deliverable. Includes RD work. - A.k.a Upgrades,
- Services same operation or task repeatedly.
- A.k.a. Operations, Maintenance, Support,
- Whether an activity is a project or service
determines which format slide to use later. - Terminology
- Obligation Budget Allocated budget. This may
differ from the budget request. - YTD Obligations Fully incurred expenses. Does
not include RIPs, Req.s in CD, etc. - Current FY08 Forecast Estimate of all
obligations to be incurred by the end of FY08. - MS Equipment Operating. Operating includes
Travel, Material Purchases, Professional Services
(contractors), Maintenance (licenses), and Other. - RIP Requisitions in Progress