Title: Distance Learning Center
1Distance Learning Center
- Technology Project Management
- Risk Management Part One
- Melissa Lin, IT Consultant
- HenEm, Inc. Parkville, Missouri
- linm_at_ipfw.edu
- http//www.etcs.ipfw.edu/linm
2Basic Concept
- Risk management focuses on
- Known unknowns
- Proactive management
- The alternative to proactive management is
reactive management, also called crisis
management. This requires significantly more
resources and takes longer for problems to
surface.
3Risk Management
- Historically, we focused our attentions on
schedule and cost risk management - Risk and Information are inversely related
- Risk Management focuses on the future
- Today, our primary emphasis is on technological
risk management - Can we design it and build it?
- What is the risk of obsolescence?
4Definition Of Risk
- A probability (Likelihood) of occurrence of
that event - Impact is the amount at stake
Risk f(Likelihood, Impact)
event
5Tolerance For Risk
- Risk avoider
- Risk neutral
- Risk lover
6Decision-Making Categories
- Decision Making Categories
- Complete uncertainty
- Hurwicz criterion
- Wald (maximin) criterion
- Savage criterion
- Laplace criterion
- Relative risk (partial information)
- Complete certainty
7Example 1 Decision Making under Certainty
- A company wishes to invest 50 million to develop
a new product - Product choices
- A product
- B product
- C Product
- States of nature
- A strong market demand (N1 Up)
- An even market demand (N2 Even)
- A low market demand (N3 Low)
8Example 1 (continue)
States of Nature
Payoff Matrix (Profit in Millions)
Payoff 50 40 -50 50
50 60 100 80 90
9Example 2 - Decision Making under Risk
States of Nature
Payoff Matrix (Profit in Millions)
E1 Payoff for strategy 1 50 0.25 40
0.25 90 0.5 67.50E2 55 million E3
20 millions
10Example 2 - Decision Making under Risk (continue)
States of Nature
Payoff Matrix (Profit in Millions)
E1 Payoff for strategy 1 50 0.6 40
0.2 90 0.2 56E2 52 millions E3 66
millions
11Savage, Minimax Criterion
Table 2
Table 3 Regret Table
12Laplace Criterion
Table 17-2
Table 17-4
13Five Steps to Develop Payoff Table
- List all the alternatives.
- List the future consequences of each alternative.
- Identify the payoffs associated with each
combination. - Assess the degree of certainty that these
combinations will materialize - Decide on a decision criterion.
14Developing and Using Payoff Tables
Establishing the procedure to follow
Construct the Payoff table
Decision-making under complete uncertainty
Decision-making under certainty
Decision-making under risk
Maximin Approach Maximax Approach Minimax regret
Approach Insufficient Reason Approach
Expected Monetary Value (EMV) Approach Expected
Opportunity Loss (EOL) Approach Expected Value of
Perfect Information (EVPI) Approach
15Decision Tree Example (Fig. 17-3)
- A Manufacturing Example the probability of each
combination of manufacturing process - A product can be manufactured using Machine A or
Machine B - Machine A has a 40 chance of being used, and
machine B has 60 - Both machines use either process C or D
- When machine A is selected, process C is selected
80 of the time, and the process D 20 - When machine B is selected, process C is selected
30, and process D 70
16Decision Tree Example (Fig. 17-3)
17Expanded Tree Example (Fig. 17-4)
- A Make or Buy Decision Example
- Make the product
- Purchase a new machine (35,000)
- Market good 70 of time, 80,000 profit
- Market poor 30,000 profit
- Subcontract out the work
- Administration cost 5,000
- Market good 50,000 profit
- Market poor 15,000 profit
18Expanded Tree Example (Fig. 17-4) (continue)
Subcontract
19Summary
- Risk Management
- Concepts
- Definition
- Tolerance
- Next - Risk Management Process
20Question?
- Answers
- Email linm_at_ipfw.edu
- http//www.etcs.ipfw.edu/linm