Design and Test of the First Article Accufix 7500 Transmitter - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Design and Test of the First Article Accufix 7500 Transmitter

Description:

Megatron Charger Assembly. A4 Resistor Board. Connector Replacement. Megatron Assembly. Oil filling Connector. Snubber Board Addition. Higher Power Diode ... – PowerPoint PPT presentation

Number of Views:143
Avg rating:3.0/5.0
Slides: 24
Provided by: christine165
Category:

less

Transcript and Presenter's Notes

Title: Design and Test of the First Article Accufix 7500 Transmitter


1
Design and Test of theFirst Article Accufix 7500
Transmitter
  • Presented by Mark Danieli

2
Need for New Transmitter
  • Factors leading to decision for new transmitter
  • Goals for new transmitter

3
Factors Leading To Decision For New Transmitter
  • TTX not supportable in near term
  • TTX/SSX do not support additional capabilities
    (i.e. IFM)
  • Cost reduction associated with fewer personnel
    requirements
  • Unmanned Stations
  • Remote Control

4
Goals for New Transmitter
  • Increase individual HCG output power through
    component improvements
  • Modernize Control Console - TCS
  • Make the number of DHCs variable and assignments
    flexible
  • Future incorporation of IFM has minimal impact on
    system architecture
  • Maximize commonality with existing USCG assemblies

5
Accufix 7500 Transmitter Overview
6
Improved Architecture
  • Prime Power Distribution Unit
  • Pulse Generator Assembly
  • Switch Network Assembly
  • Coupling Cabinet Assembly
  • Transmitter Control Subsystem (TCS)

7
Prime Power Distribution Unit
8
Prime Power Distribution Unit
  • Provides emergency shutdown, at the site and via
    remote control
  • Configuration dependent on the number of HCGs in
    transmitter
  • Each subsystem has a dedicated breaker

9
Pulse Generator Assembly
10
Pulse Generator Assembly
  • PGA consists of 4 HCGs
  • Component modernization
  • Fire detection module linked to TCS
  • HCG Assembly
  • Power Supply Reengineering
  • Card Cage / Circuit Boards
  • Backplane PCB
  • Module connections
  • Increased Capacitance (Droop)

11
HCG Power Supply
  • 6500 Series 7500 Series Control Logic
    Boards

12
Pulse Generator Assembly (Cont)
  • Megatron Charger Assembly
  • A4 Resistor Board
  • Connector Replacement
  • Megatron Assembly
  • Oil filling Connector
  • Snubber Board Addition
  • Higher Power Diode
  • Connector Replacement

13
Switch Network Assembly
14
Switch Network Assembly
  • 3 second switchover
  • Switch modules interchangeable
  • New lightning arrestor
  • Redundant DHC and Antenna current feedbacks
  • Service Life Extension Program (SLEP)

15
Coupling Cabinet Assembly
16
Coupling Cabinet Assembly
  • Total Redesign symmetric
  • Reduced footprint
  • Modular
  • Electrically a hybrid between the 6500 and the
    AN/FPN-64
  • Circuit breakers now used in place of fuses

17
Benefits
  • Increased Output Power/higher efficiency
  • Increased flexibility
  • More robust ECD control
  • Improved Timing Stability

18
Work In Progress
  • Ongoing development
  • Future software enhancements
  • Refined fail soft
  • Signal Quality Analyzer (SQA)

19
Factory System Acceptance Testing
  • Performance Measurements
  • Test and Demonstration Tasks

20
Transmitted Signal Performance Measurements
  • Envelope Shape Measurements
  • Amplitude measurements for positive and negative
    phase-coded pulses
  • RF Zero Crossing Measurements
  • Specifications relates more the timing accuracy
    of the output pulses rather than to phase
    accuracy
  • Spectrum Harmonics Measurements
  • Power Input Measurements
  • IAW COMDTINST M16562

21
Performance Measurements
22
Test and Demonstration Tasks
  • Single Rate Test
  • Dual Rate Test
  • HCG Failure Recovery Test
  • Switch-over Test
  • 120-Hour Burn-In Test

23
Summary
  • 16 HCG Transmitter for USCG LSU
  • FSAT completed in October 02
  • Installation completed in November 02
  • 48 HCG Transmitter for LORSTA George, WA
  • FSAT in December 02
  • Installation in January 03
  • 16 HCG Transmitter for LORSTA Kodiak, AK
  • In process
  • USCG Support
Write a Comment