Title: Parallel Flow Visualization Data Requirements


1
Parallel Flow Visualization Data Requirements
Jim Busbin Chairman, IDC Working Group
  • NERC ORS Meeting
  • Toronto, Ontario
  • September 23-24, 2009

2
Parallel Flow Visualization
  • Presentation Topics
  • Purpose
  • Background
  • Data Requirements
  • Data Archive
  • IDC Change Order 283, Revision 2

3
Parallel Flow Visualization
  • Purpose

4
Parallel Flow VisualizationPurpose
  • The Purpose Statement from the Parallel Flow
    Visualization SAR states
  • The requested enhancements to the TLR procedure
    in the Eastern Interconnection will improve the
    wide-area view of Reliability Coordinators (RCs)
    such that they better understand the current
    operating state of the bulk electric system and
    will result in the assignment of relief
    obligations during periods of congestion that are
    more representative of those actually
    contributing to the congestion.

5
Parallel Flow Visualization
  • Background

6
Parallel Flow VisualizationBackground
  • May 6 NERC ORS Meeting in Indianapolis, IN.
  • IDCWG was directed to
  • Identify the minimum data set required to
    achieve the required calculations by the
    September 2009 ORS meeting
  • Identify the required changes to the IDC to
    identify the GTL impacts
  • Recommend a vendor to perform the GTL
    calculations for all EI RCs
  • Determine, in cooperation with the vendor, the
    GTL calculation methodology
  • Identify to the ORS any additional items that
    are required to incorporate GTL impacts
  • The IDCWG should target having proposed
    recommendations to the ORS for the November
    2009 meeting

7
Parallel Flow VisualizationBackground
  • IDCWG has discussed and identified requirements
    to support Parallel Flow Visualization we
    continue to evaluate these requirements
  • June 3-4 IDCWG Meeting
  • Discussed charge given by ORS
  • Initiated identification of requirements
  • July 8-9 IDCWG Meeting
  • Meeting held to discuss Parallel Flow
    Visualization
  • Identification of requirements continued
  • August 18-19 IDCWG Meeting
  • OATI asked to revise Change Order 283 to include
    requirements identified in July meeting this
    modification will become Revision 2

8
Parallel Flow Visualization
  • Data Requirements

9
Parallel Flow Visualization
  • Data Requirements Introductory Notes
  • Reference Generation-to-Load Reporting
    Requirements whitepaper, January 2, 2009
  • Generation-to-load flows will be calculated by
    one vendor. Raw data used in the calculation
    will be submitted to the vendor
  • Frequency of all data submission will be every
    fifteen minutes unless otherwise noted by (?).
  • Data will be submitted to reflect current-hour
    conditions and a projection of peak next hour
    conditions. To be clear, each data submission
    will contain data for the present hour and also
    for the next hour

10
Parallel Flow Visualization
  • Data Requirements Categories
  • Load and Losses
  • Real Time Load Magnitude and Distribution
  • Generation Output
  • Real-Time Output vs. Static Values
  • Flowgate Flows
  • Provides Error Checking Capability
  • Topology Updates
  • Provides More Frequent Update of Topology and
  • Additional Data

11
Parallel Flow VisualizationData Requirements
  • Load and Losses
  • Total Real-Time BA Load
  • Geographic Zones
  • Conforming / Non-Conforming Zones
  • Individual Bus Loads
  • and Total for BA
  • Real-Time Losses for Total BA
  • Projection of Next Hour Total Peak BA Load
  • Geographic Zones
  • Conforming / Non-Conforming Zones
  • Individual Bus Loads
  • and Total for BA
  • Projection of Next Hour Losses for Total BA

12
Parallel Flow VisualizationData Requirements
  • Generation Output
  • Real-Time Generation Output
  • Output for Each Generating Unit Shown in Model
  • Net of Auxiliary Equipment / As Modeled
  • Total Real-Time Generation Output for BA
  • Projected Next Hour Generation Output
  • Output for Each Generating Unit Shown in Model
  • Projected Maximum Output of Unit in Next Hour
  • Net of Auxiliary Equipment / As Modeled
  • Total Projected Next-Hour Generation Output for
    BA
  • Generating Unit Real-Time Upper and Lower Normal
    Limits
  • Joint Ownership Identification ?

13
Parallel Flow VisualizationData Requirements
  • Flowgate Flows
  • Actual real-time flow on each active flowgate
    monitored element shown in the Book of Flowgates
  • Projection of next hour maximum flow on each
    active flowgate monitored element shown in the
    Book of Flowgates Projection of Next Hour Losses
    for Total BA
  • Actual real-time flow on each active flowgate
    contingency element shown in the Book of
    Flowgates
  • Projection of next hour maximum flow on each
    active flowgate contingency element shown in the
    Book of Flowgates
  • Un-accounted for usage will be identified and
    calculated as the difference between real time
    flows and the summation of calculated tag
    impacts, market flows and generation-to-load flows

14
Parallel Flow VisualizationData Requirements
  • Topology Updates
  • Increase frequency of IDC update from SDX and
    matrix calculation to every fifteen minutes
  • Outage updates submitted to SDX every fifteen
    minutes

15
Parallel Flow VisualizationData Requirements
  • Additional Data
  • Control Device Data Scheduled and Actual Flows,
    Real-Time and Projected Next Hour
  • Phase shifting transformers
  • DC lines
  • Variable frequency transformers
  • Dynamic Schedules Actual and projected
    next-hour flows
  • Identification of pumped storage hydro units ?

16
Parallel Flow VisualizationData Requirements
  • Additional Data
  • (NAESB / United States) Designated Network
    Resource (DNR) generating units/plants
  • (NAESB / United States) DNR capacity
  • (NAESB) Assignment of priorities for
    generation-to-load (7-F versus 6-NN)
  • Net scheduled interchange
  • Net actual interchange
  • Individual actual tie-line flows

17
Parallel Flow Visualization
  • Data Archive

18
Parallel Flow VisualizationData Archive
  • Impact archive will be added that saves
  • Tag impacts
  • Market flows
  • Generation to load flows
  • Un-accounted for usage
  • Real-time flows by flowgate
  • Archive to run around the clock not just when a
    flowgate is in TLR
  • Suggest current calendar years and previous
    years data be available on line
  • Suggest previous three years data be available
    off-line

19
Parallel Flow Visualization
  • IDC Change Order 283,
  • Revision 2

20
Parallel Flow Visualization

Questions