Inner Harbor Navigation Canal Lock Replacement Project - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Inner Harbor Navigation Canal Lock Replacement Project

Description:

Authorized the construction of a new lock and connecting ... the analysis of the samples ... Demolition. West bank Levee Phase 1. Resume Lock Design. Questions! ... – PowerPoint PPT presentation

Number of Views:117
Avg rating:3.0/5.0
Slides: 19
Provided by: gicao
Category:

less

Transcript and Presenter's Notes

Title: Inner Harbor Navigation Canal Lock Replacement Project


1
Inner Harbor Navigation Canal Lock Replacement
Project
2
Inner Harbor Navigation Canal Lock Replacement
Facts
  • River and Harbor Act of 1956 -
  • Authorized the construction of a new lock and
    connecting channel when economically justified by
    obsolescence or by increased traffic
  • WRDA 1986
  • Re-authorized the project and established Cost
    Sharing requirements
  • WRDA 1996
  • Authorized Community Impact Mitigation Plan
  • Cost shared
  • 50 Federal / 50 IWW Fund - shallow draft
    portion
  • 65 Federal / 35 Non-Federal - deep draft
    portion
  • Sponsor
  • Port of New Orleans

3
  • IHNC Lock (known locally as the Industrial Canal
    Lock) was completed in 1921
  • Target for replacement for over 40 years

4
IHNC Lock Replacement Project
5
Current Lock Placed in Service 1921 75 feet
wide by 640 feet long by 31.5 feet deep
Existing Conditions
6
Recommended Plan Deep Draft Lock 110 feet wide
by 1200 feet long by 36 feet of draft
CONCEPTUAL VIEW OF COMPLETED PROJECT
7
The Impact Communities
8
Inner Harbor Navigation Canal Lock Replacement
Completed Work
  • Test Pile (completed May 2000)
  • Demolition of Galvez Street Wharf
  • (Completed Feb 2003)
  • East Bank Industrial Area Remediation (Completed
    Jun 2005)

9
Inner Harbor Navigation Canal Lock Replacement
Ongoing Work
  • In October 2006 the project was enjoined by order
    of Federal Court.
  • No work is to be done on the project until a
    Supplemental Environment Impact Statement (SEIS)
    is completed.

10
Inner Harbor Navigation Canal Lock Replacement
Sampling Locations
11
Inner Harbor Navigation Canal Lock Replacement
Reference Sites
12
Inner Harbor Navigation Canal Lock Replacement
Laboratory Analysis
13
Inner Harbor Navigation Canal Lock Replacement
Proposed Disposal
14
Inner Harbor Navigation Canal Lock Replacement
Coordination
  • New Orleans District
  • Miss Valley Division
  • USACE HQ
  • Weston Solutions (Sampling Analysis)
  • Lakes and Rivers Division (Cost Est, Const Sch)
  • Environmental Research Development Center (ERDC)
  • Evaluation, CDF Design, Ship modeling
  • Mobile District (SEIS ATR)
  • STL laboratories (Analysis)

15
Inner Harbor Navigation Canal Lock Replacement
Delays
  • Delays with the analysis of the samples
  • MVN and EPA Region VI developed a list of
    "Contaminants of Concern" that may pose an
    ecological risk to aquatic organisms when present
    in sediments. The contractor had trouble meeting
    the required detection limits and further testing
    methods had to be implemented to meet detection
    limits.

16
Inner Harbor Navigation Canal Lock Replacement
Delays
  • Florida Avenue Bridge Construction
  • In the 97 EIS we made the assumption that the
    State was going to replace the Florida Avenue
    Bridge. In the midst of our analysis it was
    determined prudent to assume the bridge would not
    be constructed due to funding problems. Therefore
    the traffic and noise impact models had to be
    recreated.

17
Inner Harbor Navigation Canal Lock Replacement
Path Forward
  • Traffic analysis sent for ITR to be completed by
    15 September
  • Public Comment Period to begin 15 October
  • Complete SEIS by Dec 2008

18
Inner Harbor Navigation Canal Lock Replacement
Future Contracts
  • Contracts to be completed when the enjoinment is
    lifted
  • Coast Guard Demolition
  • West bank Levee Phase 1
  • Resume Lock Design

19
  • Questions!
Write a Comment
User Comments (0)
About PowerShow.com