Title: AE and Construction Change Order Estimating
1A/E and Construction Change Order Estimating
- Bob Smoot
- (202) 565-6400
- bob.smoot_at_hq.med.va.gov
2Types of Change Orders
- Design Period Change Orders
- A/E Change Orders and Supplemental Agreements
(SA) - IDIQAE Task Orders (TO)
- TO Change Order
- TO-SA
- Construction Period Change Orders
- FCO/FSA
- COCO/COSA
- Settlement By Determination
- Unilateral by CO Can Be Appealed by Contractor
3Design Period Change Orders
- Owner Initiated Change Orders
- Programmatic Changes
- Example Change Conference Room into Multiple
Exam Rooms - Example Delete Office Space From Contract
- Systems Changes
- Example - Upgrade HVAC
- Example - Delete Total Light Fixture Replacement
and Reuse Existing Light Fixtures and Supplement
With New
4Design Period Changes Orders -Cost Ramifications
- A/E Contract Modification
- A/E Submits Proposal
- Develop Scope of Work as Directed by Contracting
Officer (CO) - Direct Costs of New Design
- Overhead and Profit on New Design
- CO or Project Manager (PM)
- Verify Scope of Work
- Develop Independent Estimate of Work Envisioned
Negotiate with A/E - Reconcile with A/E Estimate
5Design Period Changes Orders -Cost Ramifications
Contd
- At Times, CO Directs A/E to Proceed with Design
Via Change Order - Later Negotiate Price and Convert to SA
- On IDIQAE, Contracts are Issued as TO
6Design Period Changes Orders -Cost Ramifications
Contd
- A/E and CO/PM Prices the Construction Work
Involved in the New Design - Uses Local Market prices
- Uses Industry References
- RS Means
- MCA
- NEC
- Dodge
- Walker
- Richardsons
- Reconcile A/E and CO/PM Estimates
7Cost Ramifications Contd
- VA responsible for All Costs Associated With VA
Generated Proposed Changes - Methods to Determine A/E Fee
- Use Data From Previous Projects Similar in Size
and Complexity - Negotiate the Cost of Producing the New Design
Based on the Number of Drawings Use Previously
Negotiated A/E Contract as Basis - Use Previously Agreed Upon Mark-ups Per Original
Contract Provisions
8Cost Ramifications Contd
- If Due to the Size of the Change Order REQUIRES
an Audit, That Needs to Proceed Prior to
Negotiations
9Types of Construction Period Change Orders
- Errors and Omissions Usually RFI Generated
- Owner Initiated
- Programmatic
- Suspend Part of Work
- Acceleration of Work
- Value Engineering
- Time Extension
10(No Transcript)
11General Procedures For Construction Period Change
Orders
- CO Issues a Change Order (CO), in Writing
- Contractor Has 30 Days to Submit Proposal for
Change Orders or COCO or Request Extension - GC and All Effected Subcontractors MUST Sign
Their Respective Portions of the Submitted Change
Order - The Government MUST Negotiate in Good Faith for a
Fair and Agreeable Price
12General Procedures For Construction Period Change
Orders Contd
- If an Agreeable Price CANNOT be Reached, the CO
MAY Instruct the Contractor to Proceed Based on a
Tentative Price - Request the CO to Issue Final Decision
- CO May Issue Settlement By Determination
- Have IDIQAE Prepare Second Independent Estimate
to Bring Closure
13Common Considerations For Construction Period
Change Orders
- Mark-ups Overhead and Profit Equal
- 10 Allowed for the First 20,000
- 7-1/2 Allowed for the Next 30,000
- 5 for everything Over 50,000
- The Primes or Upper-tier Subcontractors Fee on
the Work Performed by Lower-tier Subcontractor
Will be Based on Net - 4 Tiers are the Allowable Limit No Matter the
Number of tiers Involved - Social Security Taxes, Workmans Compensation,
and Public Liability Insurance Will Be Adjusted
for each Change Order However, These Arent
Marked up with OHP
14Common Considerations For Construction Period
Change Orders Contd
- Overhead Includes
- Insurance,
- Field and Home Office Supervisors and Assistants,
- Security Police
- Small Tools and
- Incidental Job Burdens
- Can Include Office equipment and Supplies,
Port-a-Johns, Telephone, and OSHA Compliance - And, General Home Office Expenses
15Errors and Omissions (EO)
- Architect/Engineer Responsible
- Forgot
- Example Branch Ductwork for an Exam Room
- Example Re-enforcing Beam
- Example Equipment Hook-up
- Wrong
- Example Wrong Size Waste Pipe
- Example Wrong Size Beam
- Example Wrong Equipment for Designated Room
- Lack of Coordination Between Disciplines
- Example Improper Electric Service for Motor
requirements
16Errors and Omissions (EO) - Contd
- Process
- Contractor Develops Change Order Based on RFI as
a Result of EO - Under 1,000 Detail Breakdown NOT Required
- Between 1,001 and 100,000 Contractor Submits
Breakdown Based on Spec Section and/or Trades for
Labor, Materials, and Equipment - Over 100,000, Contractor MUST Submit Cost
Pricing Certification Detailing Breakdown - A/E Develops Scope of Work and Estimate
- CO/PM Develop Independent Scope Of Work and
Estimate - Contracting Officer Reconciles all Data
17EO - Contractor Proposed Change Order
- Contractor Prices Change Order
- Direct Costs
- Take-off Quantities
- Price Materials, Manpower and Equipment
- Use Previously Agreed Upon Unit Costs
- Prevailing Market Prices
- Use Previously Agreed Upon Reference Books
- RS Means
- MCA
- NEC
- Dodge
- Walker
- Richardsons
18EO - Contractor Proposed Change Order Contd
- Indirect Costs
- Mark-ups on Direct Costs Overhead and Profit
Equal - The Primes or Upper-tier Subcontractors Fee on
the Work Performed by Lower-tier Subcontractor
Will be Based on Net - 4 Tiers are the Allowable Limit No Matter the
Number of Tiers Involved
19EO - Contractor Proposed Change Order Contd
- A/E Submits Proposal
- Develop Scope of Work as Directed by Contracting
Officer - Develop Construction Cost Estimate
- CO/PM
- Verify Scope of Work
- Develop Independent Estimate of Work Envisioned
- Reconcile with A/Es and Contractors Estimate
20Owner Initiated Programmatic and Completion
Items
- CO Issue the Change Order
- Again the Contractor Must Respond Within 30 days
with a Proposal Signed by All Subs and the Prime
Following - Again, the 10, 7-1/2 and 5 Overhead and Profit
Markups Apply to ONLY 4 Tiers - CO Reconciles Contractor, A/E and the Independent
Estimates
21Other Sources of Change Orders
- Value Engineering Proposals
- Savings are Split 60 to Government and 40 to
the Contractor - Contractor Factors-in Design, Construction Costs,
and All Other Impacted Items Social Security,
etc.. - Usually Overhead Is Negotiated and Profit is Per
10, 7-1/2 and 5 - Again a Maximum of 4 Tiers
22Supplemental Change Orders Over 500,000
- When requested by the CO, Contractor Submits
- Itemized Breakdown Including Quantities, Labor,
Materials, Unit Costs, and Equipment, - With Each Subs and the Primes Signatures,
- Including the 10, 7-1/2, and 5 Markups on a
Maximum of 4 Tiers, - CPC within 30 Days
- Audit Require for anything Over 550,000
- If Agreement is NOT Reached or Contractor Has NOT
Submitted the Proposal within the Timeframe, - CO MAY Issue Unilateral Equitable Adjustment to
the Contract - Or, Direct the Contractor to Proceed Based on a
Tentative Price
23Change Order Issues
- SF 30 Need to Address Scope of Change Order in
detail - Need to Get All Administrative Signatures on PNM
- PM Codes FCO/COCO
- Item 13 of the PNM Must Present a Complete
History of Negotiations, NOT a Couple of Lines
and Signed By RE
24Change Order Issues Contd
- When is an Independent Estimate required
- FAR says 100,00
- VVAR Says 20,000
- FM Says for ALL Change Orders (COs)
- Below 20,000 Use Price Analysis
- Use Contractors proposal as a Basis for
Quantities - Call Local Suppliers and Subcontractors to Verify
pricing - Use a Pricing and/or Productivity Reference Books
- RS Means, MCA, NEC, etc
- Need Basis of Pricing and Justification
25Change Order Issues Contd
- Above 20,000
- Have A/E Prepare Estimate BEFORE GC Sends His In
- Use IDIQAE
- SRE or RE Could Prepare it, However, It CAN NOT
Be Based on the GCs Change Order
26Change Order Issues Contd
- Daily Logs Absolutely Critical, Governments
Only Way of Truly Documenting What Happened - Note Weather, Where Work Occurred, Contractor
Difficulties, What Is Important to VA, etc.. - Use A/E to Prepare Change Order Estimate, They
See The Big Picture, Impacts on Other Items/Areas
Have Vested Interest
27Change Order Issues Contd
- Verify Scope of Work Proposed by GCs Proposal
Matches Change Order - Proposals and Independent Estimate No More Than
10 Spread