Title: JAPAN'S SPENT FUEL AND PLUTONIUM MANAGEMENT CHALLENGES
1Asian Energy Security Project Meeting Beijing,
Oct 31-Nov.2, 2007
JAPAN'S SPENT FUELAND PLUTONIUM MANAGEMENT
CHALLENGES
Tadahiro Katsuta and Tatsujiro Suzuki University
of Tokyo
CONTENTS 1. Introduction 2. Spent fuel
management 3. Plutonium balance 4. Impact of
Chetsu Earthquake 5. Conclusion
21. Introduction
- Japans Plutonium Policy Current Status
- At the end of 2006, Japan had 25.3t(f)
(37.8t(t)) of separated plutonium in Europe
recovered under contracts with BNFL and COGEMA
and about 6.7t from its domestic reprocessing
plants, i.e. the total is now 44.5 t. - On March 31, 2006, the Rokkasho reprocessing
plant by JNFL started active testing. If this
plant operates at nominal capacity, about 8t of
plutonium will be recovered annually. During
2006, 738kg of Pu was separated at Rokkasho
plant. - Japanese utilities plan to recycle all plutonium,
into existing Light Water Reactors (LWRs), but no
single reactor has been loaded with MOX fuel as
of May 2006. - Therefore, it is likely that more plutonium will
be accumulated once the Rokkasho plant starts
operating. - Rokkasho plant is now preparing for its full
operation planned in early next year. -
3Rokkasho Reprocessing Plant
- - Owner JNFL
- - 800 tHM /yr of capacity
- - 3,000tHM of spent fuel storage capacity.
- Active testing started March.31, 2006.
- -Plutonium separated and MOX powder was produced
in November, 2006 - - Commercial operation early 2008
4Table 1. Amount of Spent Fuel at Each Site (As of
end of March 2004)
Reactor on-site pools are filling up
5Three types of spent fuel storage capacity
At-reactor storage
Storage capacity 16,940 tHM/16 sites On-site dry
cask storage is not allowed by local governments
(Fukushima-1 was allowed one time).
Rokkasho reprocessing plant Storage
capacity3,000tHM (Received 1,776 tHM as of April
2006) Construction cost 18 billion
Mutsu Interim storage site
Dry storage Capacity 5,000 tHM Operation
2010 (Status Planned) Construction cost 0.8
billion (including dry casks)
6Cost Estimates of Rokkasho Project (40-year life
time cost)
Report of Study Group on Cost Estimate for
Nuclear Fuel Cycle (METI, 2004)
7Cost Comparison of Fuel Cycle Options by Japan
Atomic Energy Commission (2004)
Assumes that all nuclear power plants would be
shut down due to shortage of spent fuel storage
capacity and have to be replaced with
fossil-fueled power plants.
8Comparison of projected cumulative spent fuel
discharges with currently planned storage
capacity
2024
2028
Figure 1. Cumulative inventory and management of
spent fuel in the future
9Spent fuel storage Inflexibilities
- Although total spent fuel storage capacity is
large enough to store spent fuel up to mid-2020s,
inflexibilities of spent fuel storage management
make situation more complex - No transfer of spent fuel between utilities is
allowed. - Storage pool at Rokkasho plant (3,000tU) is
divided into three sections 1,000tU of PWR spent
fuel, 1,000tU of BWR spent fuel and 1,000tU for
either type of spent fuel. - Mutsu interim storage facility (5,000 tU) owned
by only two utilities TEPCO (4000 tons), and
JAPCO (1,000tU). - As a result, some utilities with PWRs may face
shortage of spent fuel storage as early as 2014. - Local mayors and governor of Aomori demand that
the recycling program continue in order to
guarantee that spent fuel will be removed from
the site within 50 years.
103. Plutonium balance
Current stockpile
Figure 3. Management of plutonium (As of March
2004)
11Japans Pu Stockpile (2006)
1281tPu
74tPu
81tPu
37tPu
48tPu
6tPu
Figure 4. Future plutonium stockpile until 2020
Assumption (a) Oversea Pu used first (b) Overseas
Pu not recycled before 2020 (c) Operation of
Rokkasho postponed After 2005 Demand MOX
fuel From 2012, 9.3 tPu/year/plants x18 plants
Monju re-start from
2010, 0.47tPU/year Supply
Rokkasho reprocessing plant start from 2006
(2 -6tPu/year
from 2006-2009, 8tPu/year from 2010)
13Progress of MOX fuel program as of September 2006
?
?
14Japan's stockpile of separated plutonium
15Plutonium Balance Change in Japan (2006)
16 Plutonium stockpile owned by Utilities (as of
September 2006, tonPuf)
Unit tons of fissile Plutonium
- ??22????16-18??MOX??????????
- ?????????????MOX????????????MOX???????????????????
MOX??????????
17Utilities Pu stockpile in Japan(kgPuf)
18Impact of Advanced Fuel Cycle (GNEP)
19Impact of Advanced Fuel Cycle(GNEP)
20Chuetsu Earthquake and its impact on
Kashiwazaki-Kariwa Nuclear Plant(1)
- Kashiwazaki-Kariwa is the biggest nuclear plant
site in Japan, hosting 7 units, total of 7965 MWe
net capacity. - On July 16, 2007, a strong earthquake occurred at
1013 am, with a magnitude of M 6.8(JMA scale).
Its epicenter was about 16 km north of the site,
and its hypocenter below the seabed of the
Jo-chuetsu area in Niigata (37.33N, 138.37E) - At that time, four reactors were in operation
(Unit 2,3,4,and 7), and the other three (Unit
1,5, and 6) were in shutdown for planned outages. - All of them are now shutdown and safety
investigation has started, and it is not clear
when plants will be back into operation
21Chuetsu Earthquake and its impact on
Kashiwazaki-Kariwa Nuclear Plant(2)
22Siting in Japan would be more difficult
Source Katsuhiko Ishibashi, Nuclear Plant
safety from viewpoint of Seismic Conditions,
(2003
23Design Base Earthquake and Actual Responses
24Niigata Earthquake and its Impacts on
Kashiwazaki-Kariha Nuclear Plant
Source Tokyo Electric Power
25Impact of Earthquake
- TEPCO lost 7GW of planned nuclear capacity, and
there was concern about supply during summer
peak. - Estimated peak was 61-65 GW and total planned
capacity without nuclear was 58 GW - Emergency power supply arrangements plus start up
of old power plants added up about 4.7 GW, and
finally peak demand conservation contract saved
its peak ( 1GW), and peak was finally met. - TEPCO lost about 600 billion yen(5.5 bill) due
to the earthquake, resulting in estimated 95
billion yen loss for FY 2007. - Future repair cost is uncertain
- Need to purchase CO2 credit from overseas
26HLW Disposal Issues
- Voluntary siting process of HLW disposal facility
- In Jan, 2007, Mayor of Toyo-town of Kochi
Prefecture officially requested investigation of
feasibility of HLW disposal facility (first such
request made by a town) - The town would receive \1 billion just for this
investigation. - The proposal was accepted by
- METI, but local opposition
- stopped the process
- In Oct. 2007, METI adv. comm.
- proposed to modify the process
- Govt can propose to local
- community
27Conclusions (1)
- Japan continues its reprocessing program, and the
Rokkasho reprocessing plant separated 0.7 ton of
plutonium during its test operation. - Meanwhile plutonium recycling program has made
little progress. - As a result, Japans plutonium stockpile has
steadily increased to 44.5 ton. - The introduction of advanced fuel cycle would
increase cost of fuel cycle and will not likely
to reduce area requirements.
28CONCLUSION (2)
- The Chuestu earthquake and shutdown of all 7
nuclear plants at Kashiwazaki-Kariwa site have
had significant impact on Japans nuclear debate. - Safety concerns remain, and future of KK plants
are uncertain - Financial risk and CO2 emission increase are also
sources of concern