Title: PMG Agenda August 3, 2000
1PMG AgendaAugust 3, 2000
- Overview (Weerts)
- Detector status
- Reportable milestones
- Summary
- Silicon (Demarteau)
- Forward Muon (Denisov)
- Installation (Kotcher)
- The next few months (Weerts)
2Status Overview
- Silicon
- Marcel will give details
- Production of components looking better
- Micron is producing, the end is in sight
- oversight at Promex has improved yield
- Detector looking good
- Dead/noisy channels reasonable
- Low mass cable rate some concern at vendor
- Production rate has dropped, being monitored
carefully but first half is done - Fermilab (Jones group) doing excellent job in
completing cables - 10 readout test
- Continuous struggle, but are reading out
- F disk will be next
3Fiber Tracker Status
- Hookup of clear waveguides
- Installation to start end of August ( platform
move completed) - Waveguide Production and QC are going well
60 complete
4Fiber Tracker Status
- VLPC Cassettes
- 36 done
- Sub-component assembly
- 80-98 complete
5Status Overview
- Forward Preshower
- Both detectors installed
- ICD
- North South Installed
- Luminosity monitor
- North South Installed
6Status Overview
- Central Muons
- Commissioning continues
- Forward Muon detectors
- Trig Pixels (48 octants)
- All octants assembled tested starting to move
to DAB - First A layer plane installed in detector
- Pixel VME crate readout through DAQ
- MDTs (48 octants)
- A layer octants installed
- Readout through DAQ tomorrow
- B octants 8 assembled completion late Aug
- C octants done testing
- Gas systems
- Engineering design manpower . being solved
More from Denisov
7Status Overview
- Trigger DAQ
- Progressing, no schedule concerns
- Online
- No schedule concerns, not on critical path
- Preparing for CFT waveguide installation
checkout pushing the DAQ system need full time
shifters - Multiple run functionality going
- Solenoid and beam pipe
- Beam pipe installed within D0
8Status Overview Electronics
- Electronics
- Calorimeter
- 5000 preamps installed on detector (of 55k)
- 100 pre-production BLS boards in hand
- ECS re-cabled
- To allow detector move this week
- Muon
- PDT electronics - done
- Scintillator
- Front end
- Have enough in hand, complete early Sept
- Readout card - done
- MDT - done
- Readout electronics
- Readout 100
- Fanout 15 complete early Nov, enough in hand
for commissioning
9Status Overview Electronics
- Tracking Electronics
- Si Interface Card
- Bids are back visiting vendor
- Agreed on final changes to address crosstalk
issues - 2 boards immediately on fast turnaround
- 15 boards by end Aug
- Cabling/infrastructure work underway
- Analog Front End boards
- Delayed to mid-Aug (vendor)
- MCM yields improving
- 44 good out of 50
- Unlikely that we need to order additional SVX
from UTMC bank to cover yields - Adapter card
- Sept 1 34 pre-production cards
10Installation
- Installation
- Lots of activity in DAB
- Muons, Fiber tracker, CPS, Calorimeter,Platform
moving, detector closed ( looks like detector) - Installation is taking over the upgrade, the
hall, the experiment, absorbing most manpower and
Kotcher will talk about it
11Summary
- Concerns
- There is obvious progress in DØ. Seems clear
after my absence (is that a sign ? ) - Silicon concerns continue, but shifting from
production to readout and preparing for receipt
of Si in DAB - Electronics delays are a concern for
commissioning - Getting the DAB infrastructure in place
- Holding the Nov 1 wall-down date and therefore
March 2001 - More about that later..
12The next few months part 1
The DØ schedule Up to November 1 DØ
Assembles, installs commissions until Nov 1,
no access to collision hall, no impact on BD (
have lum. monitoring in and will try to install
SMT radiation monitoring) BD brings up complex,
establish 36x36 operations with collsions,
measure losses Nov 1 thru Feb 28, 01 shutdown
of Tevatron DØ continues to assemble, rolls in
and commissions complete detector.
13The next few months part 2
Concerns Further problems in
Tevatron Scenario I CDF (no Si) rolls in in
August ( or not), machine starts up with no
collisions until ????. No collisions by Nov 1
? pressure to delay Nov 1 shutdown, because we
desire stable conditions to operate silicon
detectors into beam. DØ currently Nov 1
needs to be fixed. If it slips then March
readiness slips by same amount. Scenario II
things go so wrong that we keep the March 1
date, but redefine what a Run II detector is.
Example no silicon. This decision is made late,
after we have installed siliconnot good. DØ
if this is a conceivable option, we need to know
by Sept 15, 2000 to delay silicon
installation Other scenarios ?? We can only
conceive of one scenario our default