Title: OMEGA PROJECT


1
OMEGA PROJECT
  • TEAM ALPHA
  • Members Alexandra Salgado
  • Shaun Besse
  • Lizzabeth Ponce

2
Expected Results

Julich Ozone Sonde Intercomparison Experiment

3
System Design
  • 1.      Power supply system
  • 2.      Data-processing system
  • 3.      Electrical system
  • 4.      Launch system
  • 5.      Mechanical system
  • 6.      Thermal system
  • 7.      Ozone sensor system

4
Power Budget
5
Power Budget (cont.)
6
Power Budget (cont.)
7
Battery Specification
www.energizer.com
8
Battery Specifications (cont.)
www.energizer.com
9
Battery Specifications (cont.)
www.energizer.com
10
Data-Processing System
  • The software
  •  
  • - 1. The uploading software
  • Allows the user to download data from the
    EEPROM
  • using a PC as the user interface
  • .
  • The mission software
  • Talks to the sensors.

11
Electrical system
12
Launch system
Top View of Spacecraft interface
The interface to the spacecraft will consist
of two metal tubes attached to two
corners of the payload box. The two corners
will be opposite a diagonal.
13
Mechanical Design
Payload Box Dimensions 18.5 cm x 14.5 cm x 14.5
cm
Ozone/Heater compartment Dimensions 16cm x 9cm x
9cm
14
Mechanical Design (cont.)
Electronic Compartment
Battery compartment
15
Thermal System
A1 Area of conducting surfaces A2 Area of
radiating surfaces Pc Power that is being
conducted out of the payload Pr Power that is
being radiated out of the payload s Boltzmann
constant e emissivity k conductivity
16
Ozone Sensor System
17
Weight Budget
700 g from ACES program office 200 g from Team
JHK 100 g from Team Late Ballooners
18
Budget
19
Main Schedule
  • Activity Start Finish
  • Mission Objectives Mon 2/3/03 Wed 2/5/03
  • Project Management Thu 2/6/03 Tue 2/11/03
  • Payload Design Wed 2/5/03 Thu 2/13/03
  • Science Abstract and WBS Fri 2/14/03 Fri
    2/14/03
  • Payload Development Plan Thu 2/13/03 Tue
    2/18/03
  • Payload Construction Plan Thu 2/13/03 Tue
    2/18/03
  • Master Budget Thu 2/13/03 Tue 2/18/03
  • Written PDR Wed 2/19/03 Wed 2/26/03
  • Preliminary Design Review Thu 2/27/03 Thu
    2/27/03
  • Critical Design Review Thu 4/10/03 Thu
    4/10/03
  • Ordering of Parts Fri 4/11/03 Tue 4/15/03
  • Fabrication of Payload Box Mon 4/14/03 Thu
    4/17/03
  • Receiving ordered parts Mon 4/20/03 Wed
    4/23/03
  • Build Ozone Sensor system Wed 4/23/03 Fri
    4/25/03
  • Build Electrical system Wed 4/23/03 Fri
    4/25/03
  • Test built systems Sat 4/26/03 Wed 4/30/03
  • Assemble payload Thu 5/1/03 Thu 5/01/03

20