Title: Contra Costa Approach I: Initial Implementation of LID
1Contra Costa Approach (I)Initial Implementation
of LID
- Tom Dalziel, Assistant Program Manager
- Contra Costa Clean Water Program
- Dan Cloak, P.E., Principal
- Dan Cloak Environmental Consulting
2Contra Costa Approach Afternoon Presentations
- Experience So Far with LID(Tom Dalziel and Dan
Cloak) - Sizing IMPs to manage hydrograph modification
(Tony Dubin, Brown Caldwell) - Stream Classification Methodology (Andy
Collison, Philip Williams Associates) - Next Steps in Implementation(Dan Cloak)
3NPDES Permit New Development requirements
- Treat runoff before discharge from site.
- Match runoff peak flows and durations to
pre-project conditions. - Cover or control sources of stormwater
pollutants. - Maintain treatment facilities in perpetuity.
4Cities, Towns, and County must
- Incorporate requirements into their policies and
processes for development review - Verify that on-site treatment devices are
maintained - Prepare a Hydrograph Modification Management Plan
to control future increases in runoff peaks and
durations
5Program Objectives
- Comply with NPDES permit requirements.
- Achieve reasonable protection of beneficial uses.
- Minimize staff time required for additional
project review. - Minimize costs to applicants.
- Encourage smart growth and maintain economic
competitiveness. - Adopt a flexible approach.
- Encourage participation and consensus among
interested parties.
6Key Implementation Steps
- Update to Model Stormwater Ordinance
- Requires Stormwater Control Plan with Planning
and Zoning Application - Adopted by each municipality countywide
- Stormwater C.3 Guidebook
- Workshops for municipal staff and land
development professionals - Assistance with initial projects and preparation
of examples
7Stormwater C.3 Guidebook
- Step-by-Step Approach to Compliance
- How to Prepare a Stormwater Control Plan
- Guidance for Selecting Treatment Facilities
- Design Checklists and Standard Details for LID
IMPs - Spreadsheet for Sizing BMPs and presenting
calculations - Sample Outline and Examples
- How to prepare an Operation and Maintenance Plan
for treatment facilities - References and Hyperlinks to Design Resources
8Stormwater Control Plan
Contents
- Project Setting
- Measures to Limit Imperviousness
- Selection Design of Treatment BMPs
- Source Control Measures
- Permitting and Code Compliance Conflicts
- BMP Maintenance
- Construction Plan C.3 Checklist
- Certification
9Development Review
Pre-Application Meeting
Completed Application
Deemed Complete
Section Review
Conditions of Approval
Planning Commission
CEQA Review
Detailed Design
Plan Check
Permits to Build
10Stormwater C.3 Compliance
Section staff may review planning zoning docs
for C.3
Pre-Application Meeting
Completed Application
Deemed Complete
Planning staff may determine if C.3 reqts are
addressed
Staff identifies general C.3 requirements
Section Review
Conditions of Approval
Planning Commission
CEQA Review
C.3 requirements attached to COAs
Detailed Design
Plan Check
Permits to Build
Staff reviews C.3 implementation in drawings
specs
11Operation Maintenance
General descriptionof OM requirements
Detailed description and maintenance plan for
each facility
Certification of inspection continued
operation
Stormwater Control Plan
Stormwater Facilities Operation Maintenance
Plan
Stormwater Facilities Compliance Certificate
Submitted with Planning Zoning Application
Draft submitted with construction documents
Renewedeachyear
12Results so far
- Development community has responded positively
to - Consistent ordinances countywide
- Usability of Stormwater C.3 Guidebook
- Workshops
- Biggest Challenges
- LID requires a different approach to drainage
design - Resolving conflicts with public works standards
- IMP ownership and maintenance responsibility
13Low Impact Development in Contra Costa
CountyProblems and Solutions
- Dan Cloak, P.E.
- Dan Cloak Environmental Consulting
14Implementing LID
- Showing compliance with NPDES permit criteria for
treatment - Designing effective IMPs
- Residential Subdivisions
- Street and drainage design
- IMP operation and maintenance
- Integrating with the HMP
15Showing Compliance
- NPDES Permit sizing criteria for treatment
control - collect and convey drainage design
- conventional, end of pipe treatment
- use of runoff factors to determine design inflow
or volume
16Accounting for Pervious Areas
Conventional
LID
- Self-treating areas
- Zero discharge or self-retaining areas
- Reduced runoff areas
17Zero discharge areas
Conventional grading
Zero-discharge area
18Zero-discharge areas
19Example LID Site Design
20Example LID Site Design
- Make landscaped areas self-retaining
21Example LID Site Design
- Delineate areas that drain to each IMP
- Decide where roofs will drain
- Divide paved areas along grade breaks
22Example LID Site Design
- Fit IMPs into landscaping at low points of each
drainage area
23Example LID Site Design
- Show each IMP is sized to treat runoff from its
tributary area
24IMP Design Gallery
- Flow-through Planter
- In-ground Planter
- Bioretention Area
- Vegetated or Grassy Swale
- Infiltration Basin
- Dry Well
- Infiltration Trench
Indirect Infiltration
Direct Infiltration
25Indirect Infiltration
Turf or planting
Planting medium
Gravel or drain rock
Perforated pipe
26Sizing Criterion
0.2 inches/hour
BMP Area/Impervious Area 0.2/5 0.04
Planting medium
i 5 inches/hour
27Flow-through Planter
28Vegetated (Dry) Swale
29Design Checklists
- Vegetated Swale
- Setbacks from structures
- Sizing criteria
- Minimum depth
- Side slopes
- Specification for imported soil
- Specification for underdrain
- Irrigation
30Direct Infiltration
Dry Well
31Residential Subdivision
32Residential Subdivision
- Suitably sized infiltration basin would require 3
of 80 lots - Roofs, driveways, and landscaped areas drain to
front yard swales - Streets drain to same swales
33Seattle SEA Streets
34Swales in Front Yards
- Some jurisdictions prefer monolithic curb
gutter - Access to parked vehicles
- Avoid trip hazards
- Standard location for public utilities
- Still developing standard designs and
maintenance responsibility
35Curb and sidewalk
36HMP Requirements
- NPDES permittees must propose a plan
- Manage increases in flow and volume where
increases could - Increase erosion
- Generate silt pollution
- Impact beneficial uses
- Post-project runoff may not exceed pre-project
rates and durations - Option Equivalent Limitation
- Account for expected stream change
- Maintain or improve beneficial uses
37Contra Costa HMP
- Succinct standard, with four compliance options
- Encourage Low Impact Development Integrated
Management Practices (LID IMPs) - Allow proposals for stream restoration in lieu of
flow control where benefits clearly outweigh
potential impacts - No exemptions for
- Project size (gt1 acre impervious area must
comply) - Infill projects in highly developed watersheds
- Project cost
38Four Compliance Options
- Demonstrate project will not increase impervious
area - Implement pre-designed hydrograph modification
IMPs - Use a continuous simulation model to compare
post- to pre-project flows - Demonstrate increased flows will not accelerate
stream erosion