Modified Guaranteed Maximum Price MGMP Contracting For the Public Rental Housing Development At East - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

Modified Guaranteed Maximum Price MGMP Contracting For the Public Rental Housing Development At East

Description:

Risk-reduced Model Developed from Private Sector's Target Cost and Guaranteed ... Earmarked for Premier League Contractors. Corporate Strength. Partnering Commitments ... – PowerPoint PPT presentation

Number of Views:114
Avg rating:3.0/5.0
Slides: 14
Provided by: hous96
Category:

less

Transcript and Presenter's Notes

Title: Modified Guaranteed Maximum Price MGMP Contracting For the Public Rental Housing Development At East


1
Modified Guaranteed Maximum Price
(MGMP)Contracting For the Public Rental Housing
Development At Eastern Harbour Crossing Site
Phase 4
2
MGMP Contracting
  • Risk-reduced Model Developed from Private
    Sectors Target Cost and Guaranteed Maximum Price
    (GMP) Contracting
  • A contracting model which allows for
  • Integration of contractors expertise and
    innovation in design and construction at tender
    and post tender stage
  • And in doing so, it embraces the feature of
  • - a guaranteed maximum price at main contract
    award
  • - shared savings during construction

3
MGMPContract Procurement Route
4
MGMP at Various Stages of Procurement
  • Design Stage
  • Tender Stage
  • Construction Stage

5
Design Stage
  • Key features at design stage
  • Employer identifies works packages that require
    integration of contractors input in design,
    buildability, and procurement
  • Employer prepares basic scheme / outlined design
    and performance specification for works packages
  • Works Packages subject to detailed design
    development by the contractor

6
Tender Stages
  • Key features at tender invitation
  • Earmarked for Premier League Contractors
  • Corporate Strength
  • Partnering Commitments
  • Experience on GMP
  • MGMP Sub-contract Packages
  • Domestic sub-contracts
  • Back to back contract documentation
  • Follow HAs tendering guidelines
  • MGMP sub-contract tender prices
  • Ceiling price
  • Part of the overall contract sum

7
Tender Stages
  • Key features at tender evaluation and award
  • Contractors submit technical proposal for the
    MGMP Sub-contract works
  • Technical and price evaluation in tender
    assessment
  • Contract Sum and the technical proposals are
    binding to the contract

8
Construction Stage
  • Key features at Construction Stage
  • MGMP Subcontracts under Open Book accounting
    arrangement
  • Further savings from improvements in buildability
    anduse of materials would be shared
  • Adjudication Committee to settle differences on
    MGMP design developments and variations

9
Opportunities offered by EHC Site Phase 4
  • Project
  • Three site-specific domestic blocks
  • Bus terminus and noise barrier
  • Lift tower cum footbridge

10
Opportunities offered by EHC Site Phase 4
  • The Master Layout Plan

11
  • Integration of Contractors Expertise
  • Good potential GMP packages for site specific
    nature of project
  • Proposed packages of works
  • Bus Stop
  • Specialist External Works (Footbridge and Lift
    Tower, Covered Walkway, etc.)
  • Plumbing and Drainage
  • Fire Services and Water Pump Installation
  • Electrical Services Installation
  • Superstructure

12
  • Moderation of Benefits and Risks
  • Opportunities
  • Integration between building services and
    reinforced concrete construction
  • Optimization of precast construction
  • Optimization of contractors expertise in
    specialist design

13
  • Thank you