Title: Review
1LAT Environmental Test Planning and Design
Review 3-4 May 2005 2.0 Dynamics Tests
John Ku kuj_at_slac.stanford.edu Naval Research
Lab Bldg 226 Rm 113 Call-in number
510-665-5437 Passcode 3992
2Tue May 3 PM Agenda
- 2.0 Dynamics Tests (John Ku)
- 100 pm 2.1 Sine Vibe
- 100 2.1.1 Test Plan
- 130 2.1.2 Test Configuration
- 200 2.1.3 Test Logistics
- 220 2.1.4 Open Issues
- 230 pm 2.2 Acoustic
- 230 2.2.1 Test Plan
- 300 2.2.2 Test Configuration
- 330 2.2.3 Test Logistics
- 350 2.2.4 Open Issues
- 400 pm 2.3 Weight and CG
- 400 2.3.1 Test Plan
- 410 2.3.2 Test Configuration
- 415 2.3.3 Test Logistics
- 425 2.3.4 Open Issues
- 430 pm 2.4 Open Issues
- To get through these 57 Slides in 4 hours, we
must average 4.2 minutes/slide
3Sine Vibration Test Test Plan Overview
- Objectives of the test are well understood by all
- Verify the strength of the LAT and subsystem
interfaces under PFQ loads and durations - Measure primary natural frequencies (fn) of the
primary modes of the LAT - Determine transmissibility (Q) of the LAT
- Validate the math model used for coupled loads
analysis - Verify the workmanship and processes used in the
manufacture and assembly - Test Plan
- Third draft of test plan is out for review
first major update in over a year - Many technical details have been addressed in
previous meetings the current draft is very
mature and should be released in 1-2 weeks - First comments in from GSFC mechanical branch
have been minor and already incorporated - Instrumentation list is nearing completion, but
not finished yet - Internal accelerometers defined and CAD layout
complete - Strain gauges (16 channels) on flexures defined
(NRL can accommodate up to 40 channels, ¼ bridge)
- External accelerometer mathematical positions
defined, but CAD layout needed
4Sine Vibration Test Test Plan Overview
- Test Plan (Continued)
- Entrance/Exit Criteria are well understood by
all from the test plan - The sine vibe dynamic test is the first
environmental test to be performed after arrival
to NRL and the subsequent CPT. Criteria which
must be met before this test can be executed are - LAT mechanical integration is completeall
visual, dimensional, and torque testing has been
complete, and all travelers verified to be
complete. The LAT is in its flight
configuration, except as detailed in Section 8.3. - All subsystem units/modules functioneach
subsystem has passed its CPT following removal
from the shipping container. Any performance
discrepancies have been clearly documented. - Ensure all E-GSE needed is installed and
functioning. After moving and attaching the LAT
to the vibration test equipment, ensure each
subsystem has passed its LPT. All E-GSE cable
harnesses have been removed from the LAT prior to
test. - All test instrumentation is in place and
functioninginstrumentation has been verified to
be securely mounted in the correct locations and
oriented in the correct direction, as defined in
the test procedure, and electronics are working
correctly, and reading out signals. Cable
harnesses for this instrumentation are connected
and properly restrained for the test - Pretest analysis which provides predictions for
Fn and Q for significant modes at all test
accelerometers - Following the sine vibration test, an LPT will be
performed. Prior to breaking test configuration,
the following criteria must be met - Visual inspection of the LAT indicates that there
is no visible damage to the LAT - Successful completion of the LPT verifies that
all components and subsystems function properly
after testing - Rough analysis of test data shows that all
recorded data is useable for analysis purposes - Comparison of pre-test and post-test modal
signatures match to within 5, or at the
discretion of the test director, showing that
modal frequencies have not changed significantly
as a result of the test.
5Sine Vibration Test Test Plan Requirements
- Test Requirements
- Instrument Verification Plan
- The tests will be performed to the levels
published in the LAT environmental specification
document, LAT-SS-00778 - The dynamics tests are to be performed in the
mode in which the equipment will observe the
environment - LAT will be launched in a powered off mode
- The sine vibration tests will be performed with
the article powered off
6Sine Vibration Test Test Configuration
- The LAT is transported and supported on the TIP
- TIP is already installed for all handling before
and after test - TIP assembly uses SC flexures from Spectrum
- TIP is designed to simulate SC flexure/top deck
interface, so it provides a nearly flight-like
interface for the test - Interface to both the slip table and expander
head is by way of a simple bolt pattern that fits
well with the LAT geometry
X/Y-Axis Vibration Configuration
Z-Axis Vibration Configuration
7MGSE Requirements Flowing from Sine Vibe Test
Plans
- See the table, below, for a list of all MGSE/STE
that is needed for conducting the sine vibe test - Test Interface Plate
- TIP and mounting hardware capable of handling
inertial loads of LAT during test - TIP bolt pattern and size compatible with
expander head and slip table - TIP plate supported adequately to ensure stiff
connection to slip table/expander head - Dust Tent
- Capable of providing clean, dry environment
before/during/after vibe testing - Provides clearance around LAT for unrestricted
motion during vibe - Capable of being on/off-loaded from GPR to vibe
table - Heat Pipe Restraining Plates
- Supports DSHP/XLHP 3-way joints during vibe since
Radiator VCHPs are not mounted - Provides flight-like interface to simulate VCHP
flange - Chill Bars
- Capable of handling vibration loads (obviates
need to de-/re-integrate them)
MGSE/STE Needed for Sine Vibe Testing
8Auxiliary Cooling and Mechanical Handling
- Auxiliary cooling plans
- LAT needs to be cooled during LPTs between each
vibe axis run and before and after - Chill Bars one under each of the two X-wings on
the Grid - X-LAT Aux Cooling using fly-away cooling lines
already mounted to X-LAT Plate - This is room-temperature cooling to remove LAT
process heat - To simplify cooling connections, Chill Bars and
X-LAT cooling will be designed to handle vibe
loads - Hoses will be disconnected using quick-disconnect
fittings - Handling and mechanical operating procedures
- LAT lifting procedure
- TIP mounting procedure
- Dust tent handling and operating procedure
- LAT auxiliary cooling system operating procedure
9MGSE Issues for Sine Vibe Testing
- Dust Tent
- This is likely needed for sine vibe, but is still
TBR - If needed, how will dust tent be supported off of
the slip table/expander head around the LAT,
while the LAT is vibed? - How do we access the LAT for electrical and aux.
cooling interconnects before/after vibe testing? - How is the Dust Tent handled with the LAT
- LAT is transported with the Tent hanging from the
GPR - After integration on the slip table, the Tent
will need to be re-positioned onto the vibe table
base - Logistics in the vibe lab
- Space is tight in the vibe lab, and the LAT MGSE
is large - We will have 4 large-footprint objects in the lab
nearly simultaneously - LAT on the TIP
- GPR
- 4 x 4 Lift Fixture
- MGSE Cart
- Vibe lab also has 2 vibe tables and the expander
head which will need re-positioning during our
test - We will be running through the handling logistics
with paper dolls, then with the pathfinder, so we
should be able to catch the problem areas early
10MGSE Structural Analysis Status
- TIP was analyzed for lift loads and dynamic
performance (see FEA Mesh shown at left) - High margins were calculated for both cases
- Rough calculations for the mounting shoes were
performed, with more detailed analysis to follow - Conservative hand calculations show high margins
for strength and stiffness - Rough calculations for the test stand have been
performed, wth more detailed analysis to follow - Concentrated on regions of highest load
- Design is extrememly stout, and calculations show
corresponding high strength margins
11MGSE Structural Analysis TIP Lift case
- The TIP is only attached to the mounting shoes by
16 screws, in a thinned section - When lifted, how much will the TIP sag from its
own weight? ? 148 microns (0.6 mils) - How much stress is imparted from the prying
loads? ? 3.02 MPa (241 MPa Yield)
12MGSE Structural Analysis TIP Dynamic
Performance
Calculated First Mode 417 Hz Required
Performance gt225 Hz (1.5150 Hz)
13MGSE Structural Analysis Mounting Shoes
14MGSE Structural Analysis Test Stand
Test Interface Plate
LAT
Radiator SC Strut simulators
Test Stand
Radiator
15Sine Vibration Test Test Plan Constraints
- EGSE Constraints
- Cables
- Disconnected during vibration
- Must be long enough to reach LAT while mounted to
either expander head or slip table - Cable trays or protection if laid on floor
- Cart with EGSE Hardware
- Portable, can be rolled out of the way
- Power interface to lab?
16Sine Vibration Test Test Configuration
- Mechanical Configuration
- Radiators not attached
- By agreement with the GPO, no mass simulators are
needed - Mounted to GD/Spectrum Astro-provided test
flexures - Test flexures will be proof tested at SLAC prior
to GRID static test - TIP to interface test flexures and slip
table/expander head - LAT Z-axis is always vertical
- Access to connectors needed (scaffold around
expander head?) on X side - Layout needed to check cable run lengths
- Electrical Configuration
- SLAC purchased accelerometers are voltage type
and have 10-32 connectors, with a special
proprietary triax connector - Adapters will be needed to interface with NRL
equipment - ACD accelerometer interface to be verified
- Strain gauges do not have connectors (open leads)
- EGSE needed for LPTs between axes (Rich Baun to
define requirements)
17Sine Vibration Test Test Configuration
Instrumentation
- Test instrumentation by subsystem, total of 57
channels, calibrated and installed by SLAC IT,
final checkout by NRL
18Sine Vibration Test Test Configuration
Instrumentation
19Sine Vibration Test Test Configuration
Instrumentation
20Sine Vibration Test Test Configuration
Instrumentation
- Four strain gauges installed per flexure for a
total of 16 strain gauge channels - Assumed to be 120 Ohm, ¼ bridge, GF2
- Strain gauges should be temperature compensated
if possible - The gauges and data acquisition equipment should
be sized to capture a maximum strain of 2500
microstrain (titanium has a yield strain of 7500
microstrain) and have a 0.25 precision (6
microstrain error) - The combination of strain gauges will allow
measurement of axial strain and bending strain - Shear strain will not be directly measured, but
may be ascertained from the combined strain
readings of the two legs and pre-test analysis
21Sine Vibration Test Planning Detailed Sequence
- Pre-test Activities
- Move dolly into position in vibration lab and
disconnect LAT from dolly (SLAC-IFCT) - Lift LAT and TIP onto expander head, and torque
bolts (NRL) - Cable Hook-ups and system checkouts
- Electrical connections to shaker system and accel
tap checks (NRL) - Electrical connections to EGSE and perform LPT on
expander head (SLAC) - Z-Axis Vibration Test
- Low-level Signature Sine Sweep to 150 Hz (sweep
up and down) - Set-up sheet printouts (NRL), verification and
approval (SLAC) - If LPT results are okay, disconnect EGSE cables
- Run test
- Output FRF data (NRL)
- Review Data (SLAC)
- Determine notching, if needed
- Provide feedback to test conductor
- Check pass/fail criteria for Modal Test
requirement - Give OK to proceed (SLAC), or decide alternate
action is needed - Half-level run to 50 Hz
- Set-up sheet printouts (NRL), verification and
approval (SLAC)
22Sine Vibration Test Planning Detailed Sequence
(cont.)
- Z-Axis Vibration Test (continued)
- Full-level run to 50 Hz
- Set-up sheet printouts (NRL), verification and
approval (SLAC) - Run test
- Output data hardcopies (NRL)
- Review Data (SLAC)
- Check peak levels
- Check pass/fail criteria for Modal Test
requirement - Give OK to proceed (SLAC), or decide alternate
action is needed - Low-level Signature Sine Sweep to 150 Hz
- Set-up sheet printouts (NRL), verification and
approval (SLAC) - Run test
- Output data overlays (NRL)
- Review Data (SLAC)
- Re-Check pass/fail criteria for Modal Test
requirement - Concurrent with data review, hook-up EGSE and
perform LPT - If data review and LPT are good, Give OK to break
configuration, or decide is alternate action is
needed - Post- Z-Test / Pre- X-Test Activities
- Disconnect all electrical connections
23Sine Vibration Test Planning Detailed Sequence
(cont.)
- X-Axis Vibration Test
- Low-level Signature Sine Sweep to 150 Hz
- Same steps as Z-axis test
- Give OK to proceed (SLAC), or decide alternate
action is needed - Half-level run to 50 Hz
- Same steps as Z-axis test
- Give OK to proceed (SLAC), or decide alternate
action is needed - Full-level run to 50 Hz
- Same steps as Z-axis test
- Give OK to proceed (SLAC), or decide alternate
action is needed - Low-level Signature Sine Sweep to 150 Hz
- Same steps as Z-axis test
- Concurrent with data review, hook-up EGSE and
perform LPT - If data review and LPT are good, Give OK to break
configuration, or decide is alternate action is
needed - Post- X-Test / Pre- Y-Test Activities
- Disconnect EGSE electrical connections, leaving
Accel cables connected - Remove mounting bolts, lift and rotate LAT in
place - Lower LAT to slip table and torque bolts
- Perform vibration control system checkout (no
EGSE hook-up here)
Shaker
Slip Table
Shaker
Slip Table
24Sine Vibration Test Planning Detailed Sequence
(cont.)
- Y-Axis Vibration Test
- Low-level Signature Sine Sweep to 150 Hz
- Same steps as X-axis test
- Give OK to proceed (SLAC), or decide alternate
action is needed - Half-level run to 50 Hz
- Same steps as X-axis test
- Give OK to proceed (SLAC), or decide alternate
action is needed - Full-level run to 50 Hz
- Same steps as X-axis test
- Give OK to proceed (SLAC), or decide alternate
action is needed - Low-level Signature Sine Sweep to 150 Hz
- Same steps as X-axis test
- Concurrent with data review, hook-up EGSE and
perform LPT - If data review and LPT are good, Give OK to break
configuration, or decide is alternate action is
needed - Post- Y-Test Activities
- Disconnect all electrical connections
- Remove mounting bolts, lift and set LAT on
handling dolly - Attach LAT to handling dolly
25Sine Vibration Test Configurations Deviations
From Flight
- The Radiators are not integrated to the LAT for
this test. - Structural interactions between the Radiators and
the Grid are not captured - This interface will be strength verified at the
subsystem level - Coverplates to constrain the down spout heat
pipes (DSHPs) and X-LAT heat pipes (XLHPs) to
prevent relative motion to the Grid - This interface will be strength verified at the
subsystem level - The LAT is mounted to STE using test flexures
which simulate the flight connection to the SC - The STE and test flexures will be included in the
pre-test FEA analysis, so its impact on the
response of the LAT will be understood. - Since the Radiators and SC are not included in
this test, not all flight cable harnesses and
supports will be integrated for this test - These cables and their associated support
brackets will not be adequately verified by this
test - Workmanship for these flight connections and
harnesses will be accomplished with the
Observatory level sine vibration test.
26Sine Vibration Test Document List and Status
- LAT-MD-00408 LAT Instrument Performance
Verification Plan - LAT-MD-02717 LAT Environmental Test Sequence
- LAT-MD-01196 LAT Dynamics Test Plan
- LAT-MD-01533 LAT EGSE Plan
- LAT-MD-00649 LAT Transportation and Handling
Plan - LAT-MD-00404 LAT Contamination Control Plan
- LAT-SS-00778 LAT Environmental Spec
- LAT-TD-00890 LAT Instrumentation Plan
27Sine Vibration Test Test Logistics
- Test Personnel
- Test support personnel have been identified (to
be verified) - Test Director John Ku (SLAC)
- Test Conductor Bob Haynes (NRL)
- Discipline Lead Jim Haughton (NRL)
- Facility ManagerBill Raynor (NRL)
- MGSE Lead Martin Nordby (SLAC)
- EGSE Lead Mike Huffer (SLAC)
- Test Script Lead Rich Baun (SLAC)
- High-bay operations Paul Dizon (NRL)
- Quality Assurance Joe Cullinan (or Doug
Bartholomew) (SLAC) - IT Ken Fouts (SLAC)
- Subcommittees will be assembled from the
appropriate personnel above, with expert
consultation brought in if needed - Potential Vibration Experts Paul Baird Chris
Fransen Bill Haile
28Sine Vibration Test Test Logistics
- Many logistics have already been worked out
these remain - Complete and release drawings/model of slip table
and expander head - Verify slip table and expander head size, inserts
and pattern - Clearance to off-load frame on expander head
- Verify that Test Interface Plate fits completely
on expander head - Verify that LAT clears bracket parts on slip
table - Develop paper doll work-up to verify we have
floor space for 2 carts, GPR, and 4x4 Lift
Fixture - Lay out EGSE cable routing and locate EGSE crates
- Identify what contamination and humidity control
is needed in vibe facility - Is GN2 purge neccesary?
- Cleanliness (need blanket?)
- CG Alignment / sensitivity of equipment to
offsets (by analysis TBD) - Instrumentation patch panels and cable supports
(ensure all connectors interfaces) - Complete detailed design and analysis of TIP and
flexure mount brackets (In-process) - Verify response / control channel capability
(NRL) - Contingencies
- Need to be prepared to perform a modal test if
the LAT frequencies do not meet expectations - Modal test will not need additional
instrumentation - May require the use of portable shaker with
stinger to RMB or other hardpoint
29Sine Vibration Test Open Issues
- Complete structural analysis of MSGE
- Complete pre-test analysis, including a
simulation of LAT on fixtures - 10 action items are open and being tracked.
- 9 have clear closure paths and are actively being
worked on - 1 action not addressed yet is not a high
priority, as MGSE has not been designed yet
30Acoustic Test Test Plan Overview
- Objectives of the test are well understood by all
- The objective of the acoustic test is to
demonstrate that the fully integrated LAT is
capable of withstanding acoustic noise loads,
simulating launch conditions. - A secondary objective is to verify the acoustic
analysis, i.e. that the LAT components were
qualified to high enough levels of Random
vibration - Test Plan
- Third draft of test plan is out for review
first major update in over a year - Many technical details have been addressed in
previous meetings the current draft is very
mature and should be released in 1-2 weeks - First comments in from GSFC mechanical branch
have been minor and already incorporated - Instrumentation list is nearing completion, but
not finished yet - Internal accelerometers defined and CAD layout
complete - Strain gauges (16 channels) on flexures defined
(NRL can accommodate up to 40 channels, ¼ bridge)
- External accelerometer mathematical positions
defined, but CAD layout needed
31Acoustic Test Test Plan Overview
- Test Plan (Continued)
- Entrance/Exit Criteria are well understood by
all from the test plan - The LAT acoustic test is performed immediately
following the LAT sine vibe test. Criteria which
must be met before this test can be executed are - LAT mechanical integration is completeall
visual, dimensional, and torque testing has been
complete, and all travelers verified to be
complete. The LAT is in its flight
configuration, except as detailed in Section
10.3. - All subsystem units/modules functioneach
subsystem has passed its CPT following removal
from the shipping container. Any performance
discrepancies have been clearly documented. - Ensure all E-GSE needed is installed and
functioning. After moving and attaching the LAT
to the vibration test equipment, ensure each
subsystem has passed its LPT. All E-GSE cable
harnesses have been removed from the LAT prior to
test. - All test instrumentation is in place and
functioninginstrumentation has been verified to
be securely mounted in the correct locations and
oriented in the correct direction, as defined in
the test procedure, and electronics are working
correctly, and reading out signals. Cable
harnesses for this instrumentation are connected
and properly restrained for the test. - Following the acoustic test, an LPT will be
performed. The criteria for declaring a
successful completion of the acoustic test are - Visual inspection of the LATindicating that
there is no visible damage to the LAT - Successful completion of the LPTverifying that
all components and subsystems function properly
after testing - Preliminary analysis of test dataverify that all
recorded data is useable for analysis purposes - No significant mode shiftspre- and post-test
signatures match within 5 showing modal
frequencies have not changed as a result of
testing
32Acoustic Test Test Plan Requirements
- Test Requirements
- Instrument Verification Plan
- The tests will be performed to the levels
published in the LAT environmental specification
document, LAT-SS-00778 - The dynamics tests are to be performed in the
mode in which the equipment will observe the
environment - LAT will be launched in a powered off mode
- The acoustic test will be performed with the
article powered off
33MGSE/STE for Acoustic Testing
- LAT (on the TIP) is mounted on the Test Stand for
acoustic testing - LAT TIP mounts to Test Stand then Radiators are
integrated - LAT is rolled into the acoustic chamber, then
jacked off its casters - Dust Tent remains over the LAT for the entire
operation, including during testing (TBR) - SC top deck simulator
- A circular honeycomb-core panel is mounted in the
hole of the TIP - This simulates the acoustic behavior of the SC
top deck - There is free access to the underside of the TIP
through the Test Stand to integrate and
instrument this
Test Interface Plate
LAT
Radiator SC Strut simulators
Test Stand
Radiator
Acoustic Test Configuration
34MGSE Requirements Flowing from Acoustic Test Plans
- See the table, below, for a list of all MGSE/STE
that is needed for conducting the acoustic test - Test Interface Plate
- TIP accommodates a top deck acoustic simulator
- Top deck acoustic simulator adequately simulates
the acoustic behavior of the SC - Dust Tent
- Capable of providing clean, dry environment
before/during/after acoustic testing - Provides clearance around LAT
- Does not impact the acoustic response of the LAT
or acoustic environment in the chamber during
testing - SC Strut Simulators
- Provides flight-like interface to simulate SC
struts that support the Radiators - Interface with Radiator at flight interface, and
with Test Stand - Chill Bars
- Capable of handling acoustic loads (obviates need
to de-/re-integrate them)
MGSE/STE Needed for Acoustic Testing
35Auxiliary Cooling and Mechanical Handling
- Auxiliary cooling plans
- LAT needs to be cooled during LPTs before and
after acoustic testing - Chill Bars one under each of the two X-wings on
the Grid - X-LAT Aux Cooling using fly-away cooling lines
already mounted to X-LAT Plate - This is room-temperature cooling to remove LAT
process heat - To simplify cooling connections, Chill Bars and
X-LAT cooling will be designed to handle acoustic
loads - We may be able to leave all hoses and fittings
connected during the test (TBR), otherwise will
quick-disconnect them - Handling and mechanical operating procedures
- LAT lifting procedure
- Radiator integration procedure
- Test Stand handling and operating procedure
- Dust tent handling and operating procedure
- LAT auxiliary cooling system operating procedure
36MGSE Issues for Acoustic Testing
- Dust Tent
- This is likely needed for acoustic testing, but
is still TBR - If needed, what is impact of dust tent on
acoustic environment in the chamber? - Dust tent will need to be designed to not
overly-attenuate sound pressure levels - Transportation issues
- The acoustic chamber has a ¾ door sill/threshold
- We plan to build a ramp to roll up and over the
sill - This will definitely by prototyped with the
pathfinder, since the LAT c.g. is moderately high - Test Stand will be moved into the room with an
electric forklift - We need to verify that it can position the LAT
adequately
37Acoustic Test Test Plan Constraints
- EGSE Constraints
- Cables
- Disconnected during vibration
- Must be long enough to reach LAT while mounted to
either expander head or slip table - Cable trays or protection if laid on floor
- Cart with EGSE Hardware
- Portable, can be rolled out of the way
- Power interface to lab?
38Acoustic Test Test Configuration
- Mechanical Configuration
- Radiators attached (with flight thermal joint)
- Need to ensure thermal joint has enough time to
cure (7 days RT) - Mounted to GD/Spectrum Astro-provided test
flexures - Test flexures will be proof tested at SLAC prior
to GRID static test - Mounted on LAT acoustic test stand
- LAT Z-axis is vertical
- Access to connectors needed (ladder around MGSE)
on X side - Layout needed to check cable run lengths
- Electrical Configuration
- SLAC purchased accelerometers are voltage type
and have 10-32 connectors, with a special
proprietary triax connector - Adapters will be needed to interface with NRL
equipment - ACD accelerometer interface to be verified
- Strain gauges do not have connectors (open leads)
- EGSE needed for LPTs between axes (Rich Baun to
define requirements)
39Acoustic Test Test Configuration
Instrumentation
- Test instrumentation by subsystem, total of 57
channels, calibrated and installed by SLAC IT,
final checkout by NRL
40Acoustic Test Test Configuration
Instrumentation
- The STE will be centered in the acoustic chamber,
rotated to an angle of approximately 20-30
degrees, as measured between the Radiator surface
and chamber sidewall - Additionally, there will be a plastic sheet
placed under the STE to help identify any items
that may come loose as a result of the acoustic
vibration.
41Acoustic Test Planning Detailed Sequence
- Pre-test Activities
- Chamber Setup and empty cell calibration
- This is needed to verify the test cell is clean
and ready to accept the LAT for testing - The empty cell calibration will verify that the
specified sound pressure levels can be achieved - Move LAT on dolly (radiators already installed)
into chamber and set orientation to the
appropriate angle - Cable Hook-ups and system checkouts
- Electrical connections to shaker system and accel
tap checks (NRL) - Electrical connections to EGSE and perform LPT on
expander head (SLAC) - LPT on acoustic test stand
- Low-Level run at -6 dB for 30 seconds (establish
pre-test signature, review data) - Set-up sheet printouts (NRL), verification and
approval (SLAC) - If LPT results okay, disconnect EGSE cables and
close chamber door - Purge chamber of air
- Run Test
- Output Data, accel ASDs and strain gauge SSDs
(NRL) - Review data (SLAC)
- Check for dead channels
- Review mic average for level and chamber
uniformity - Review Grms values for obvious anomalies
42Acoustic Test Planning Detailed Sequence (cont.)
- Full-Level run at -0 dB for 60 seconds (impart
full SPL, check SPL, linearity, review data) - Set-up sheet printouts (NRL), verification and
approval (SLAC) - Run Full level Test
- As level steps up to -3dB, check critical channel
linearity and record data - Hold at full level for 60 seconds
- Immediately following full level run, perform low
level run - Do not review data between full level and
post-test low level run - Output Data accel ASDs and strain gauge SSDs
(NRL) - Review data (SLAC)
- Check for dead channels
- Review mic average that PFQ level is met and
chamber uniformity - Review Grms values for linearity
- Give Okay to proceeed (SLAC), or decide if
alternate action is needed
43Acoustic Test Planning Detailed Sequence (cont.)
- Low-Level run at -6 dB for 30 seconds (Signature
check, review data, complete axis) - Output Data (NRL)
- Review data (SLAC)
- Check for dead channels
- Review mic average for level and chamber
uniformity - Review pre- and post- test overlays for frequency
shifts and amplitude changes - Give Okay to proceeed (SLAC), or decide if
alternate action is needed - Post- Acoustic Test Activities
- Fill chamber with air (may be done automatically
following final low-level run) - Connect EGSE and perform LPT
- Visually inspect plastic sheet under LAT
- If everything looks okay, give okay to break
configuration - Disconnect all electrical connections
- Move LAT out of chamber
44Acoustic Test Configurations Deviations From
Flight
- The LAT is mounted to STE, which is intended to
simulate the influence of the SC volume and
geometric proximity on acoustic pressures
immediately adjacent to significant LAT surfaces,
such as the Radiators and XLAT plate - The SC top deck and lower radiator strut mounts
were identified as the critical regions for SC
simulation - The top deck simulator will be of the same
construction as the SC top deck and will be
attached to the TIP MGSE - The lower radiator strut mounts will have a
similar interface with the radiators and the
stiffnesses will be approximated, but
cross-coupling and stiffness differences will not
be captured in this test - SC-LAT cabling is not connected for this test, so
these connections, the cable harnesses, and the
attachment methods are not verified as part of
this test - These will be verified at the Observatory
acoustic test
45Acoustic Test Document List and Status
- LAT-MD-00408 LAT Instrument Performance
Verification Plan - LAT-MD-02717 LAT Environmental Test Sequence
- LAT-MD-01196 LAT Dynamics Test Plan
- LAT-MD-01533 LAT EGSE Plan
- LAT-MD-00649 LAT Transportation and Handling
Plan - LAT-MD-00404 LAT Contamination Control Plan
- LAT-SS-00778 LAT Environmental Spec
- LAT-TD-00890 LAT Instrumentation Plan
46Acoustic Test Test Logistics
- Test Personnel
- Test support personnel have been identified (to
be verified) - Test Director John Ku (SLAC)
- Test Conductor Bob Haynes (NRL)
- Discipline Lead Jim Haughton (NRL)
- Facility ManagerBill Raynor (NRL)
- MGSE Lead Martin Nordby (SLAC)
- EGSE Lead Mike Huffer (SLAC)
- Test Script Lead Rich Baun (SLAC)
- High-bay operations Paul Dizon (NRL)
- Quality Assurance Joe Cullinan (or Doug
Bartholomew) (SLAC) - IT Ken Fouts (SLAC)
- Subcommittees will be assembled from the
appropriate personnel above, with expert
consultation brought in if needed - Potential Vibration Experts Paul Baird Chris
Fransen Bill Haile
47Acoustic Test Open Issues
- Many logistics have been closed already the
logistics that still need consideration are - Lip at threshold (how to transport into room)
- Accommodation for moving Test Stand over ½ door
sill - Use pneumatic wheels or air bearings?
- Cleanliness (need blanket?) is rating worse
than 100K? - Instrumentation feedthrough and cable supports
- Is a dust tent needed around LAT in acoustic
chamber - What type of panels are needed in/around LAT to
simulate SC response - Complete structural analysis of MSGE
- Complete pre-test analysis
- Verify top plate simulator attached to TIP MGSE
adequately replicates SC response - 5 action items are open and being tracked.
- All actions have clear closure paths and are
actively being worked on
48Weight and CG Test Test Plan Overview
- Objectives
- The primary objective of this test is to measure
and/or calculate the overall mass and CG of the
fully integrated LAT, to verify that it meets the
IRD 433-IRD-0001 requirements of - Mass is less than 3000 kg
- Z-cg is a maximum of 185mm above the LAT
Interface Plane (LIP) - Because of the difficult involved in measuring
Zcg, this requirement will be verified through
calculations, based on measurements of all LAT
constituents. - From the Xcg and Ycg measurements and comparison
with calculated values, an appropriate confidence
level can be established and applied to the Zcg
calculations. - X-cg and Y-cg are within 20mm of LAT Coordinate
System (LCS) Z-axis - A secondary objective is to verify measured mass
properties match well when compared with the math
model mass matrix. - Due to the complexity of measuring moments of
inertia, only mass and CG properties will be
validated. Differences will be reconciled by
updating the math model to reflect measured
values - Since structural dynamics is intimately tied with
mass and stiffness, mass property updates are
important to preserve the true dynamic behavior
of the LAT. - Test Plan
- This is a new addition to the test plan draft 3
- Many technical details have been addressed in
previous meetings the current draft is very
mature and should be released in 1-2 weeks - All needed instrumentation has been identified,
but MGSE design is still needed
49Weight and CG Test Test Plan Overview
- Test Plan (Continued)
- Entrance/Exit Criteria from the test plan
- The LAT mass properties test is performed
following the LAT thermal vacuum test and the
subsequent CPT and removal of the radiators.
Criteria which must be met before this test can
be executed are - LAT Radiators have been removed and the LAT,
Flexures and TIP have been moved into the mass
properties test areavisual inspection verifies
that all the LAT has been re-configured
correctly. All travelers verified to be
complete. The LAT is in its flight
configuration, except as detailed in Section
10.3, below. - All subsystem units/modules functioneach
subsystem has passed its CPT following TVAC. Any
performance discrepancies have been clearly
documented. - All non-fly-away accelerometers and other test
instrumentation, cables and harnesses are
removed. - Following the mass properties test, an aliveness
will be performed. The criteria for declaring a
successful completion of the mass properties test
are - Visual inspection of the LATindicating that
there is no visible damage to the LAT - Successful completion of the aliveness
testverifying that all components and subsystems
are still properly interconnected. - Preliminary analysis of test dataverify that all
recorded data is useable for analysis purposes
50Weight and CG Test Test Plan Constraints
- MGSE Constraints
- Platform to distribute weight into three load
cells - Must be stiff enough to carry load from TIP (four
points) to load cells (three points), i.e. to
evenly distribute load from the four flexures - Must be light enough to not affect load cell
accuracy (use load cells with highest possible
accuracy and precision load cell precision
generally goes down with increased capacity) - Must have a way to precicely locate the LAT and
TIP with respect to some arbitrary reference
coordinate system - Must be able to accommodate the LAT in 0 and 90
degree orientations - EGSE Constraints
- Cables
- Disconnected during vibration
- Cart with EGSE Hardware
- Portable, can be rolled out of the way
- Power interface to lab?
51Weight and CG Test Test Configuration
- Mechanical Configuration
- Radiators not attached
- MGSE to hold DSHP and XLHP attached
- Mounted to GD/Spectrum Astro-provided test
flexures - Test flexures will be proof tested at SLAC prior
to GRID static test - TIP to interface test flexures and weight and CG
test platform - LAT Z-axis is always vertical
- All unnecessary instrumentation removed (such as
removable accels) - Electrical Configuration
- No electrical connections to the LAT
- 16 Strain gauges and 3 load cells are the only
instrumentation needed - EGSE needed to verify aliveness after weight
and CG test
52Weight and CG Test Test Configuration
Instrumentation
- Test instrumentation by intrument type Load
cells installed by NRL Strain gauges installed
by SLAC IT
53Weight and CG Test Planning Detailed Sequence
- Weight and CG Run
- Instrumentation checkuse dummy masses to verify
that all instrumentation is operational and
taking useful data - Align LAT on test platform
- Measure overall mass and centers of gravity
- Rotate LAT 90 degrees and align to test platform
- Measure overall mass and centers of gravity
- Aliveness Testexecute aliveness test after LAT
has been packed in shipping container
54Weight and CG Test Configurations Deviations
From Flight
- The LAT is mounted to STE (flexures and TIP),
which is not part of the flight LAT structure. - Radiators not attached
- Radiator mass will be added to the LAT math model
- MGSE to hold DSHP and XLHP attached
- The added weight will be subtracted from the LAT
math model - The added weight is insignificant and within the
measurement precision of the load cells - SC-LAT connector savers are attached during this
test - The added weight will be subtracted from the LAT
math model - The added weight is insignificant and within the
measurement precision of the load cells
55Weight and CG Test Document List and Status
- LAT-MD-00408 LAT Instrument Performance
Verification Plan - LAT-MD-02717 LAT Environmental Test Sequence
- LAT-MD-01196 LAT Dynamics Test Plan
- LAT-MD-01533 LAT EGSE Plan
- LAT-MD-00649 LAT Transportation and Handling
Plan - LAT-MD-00404 LAT Contamination Control Plan
- LAT-SS-00778 LAT Environmental Spec
- LAT-TD-00890 LAT Instrumentation Plan
56Weight and CG Test Test Logistics
- Test Personnel
- Test support personnel have been identified (to
be verified) - Test Director John Ku (SLAC)
- Test Conductor Bob Haynes (NRL)
- Discipline Lead Jim Haughton (NRL)
- Facility ManagerBill Raynor (NRL)
- MGSE Lead Martin Nordby (SLAC)
- EGSE Lead Mike Huffer (SLAC)
- Test Script Lead Rich Baun (SLAC)
- High-bay operations Paul Dizon (NRL)
- Quality Assurance Joe Cullinan (or Doug
Bartholomew) (SLAC) - IT Ken Fouts (SLAC)
- Subcommittees will be assembled from the
appropriate personnel above, with expert
consultation brought in if needed - Potential Vibration Experts Paul Baird Chris
Fransen Bill Haile
57Weight and CG Test Test Logistics
- Many logistics have been worked out already the
remaining logistical issues are - Where to perform this test
- How to precisely align the LAT with respect to
the load cells - Finalize load cell selection
- Ensure load cells availability
- Ensure load cells meet precision requirements
- Provide load cell ICD to SLAC for MGSE design
- Other work to be performed
- Design the weight and CG Test platform to the
requirements - Perform structural analysis of MGSE and test
platform - A/I Closure plans
- Currently NO OPEN ACTION ITEMS!!!