Title: NEPA and FHWA Project Development
1NEPA and FHWA Project Development
- Lamar S. Smith, Team Leader
- Project Development Environmental Review
2How Has the Process Evolved?
SAFETEA ?
1966 DOT Act
1998 TEA-21
1990 ISTEA
1971 FaHA
1956 FaHA
2000
1950
1960
1990
1970
1980
1978 CEQ
1990 CAAA
1969 NEPA
1966 NHPA
1987 FHWA/FTA
1971 CWA
1973 ESA
3Federal Environmental Laws and Executive Orders
Affecting Transportation
4NEPA
- Declare a national policy to encourage productive
and enjoyable harmony between man and his
environment - prevent or eliminate damage to the environment,
- stimulate the health and welfare of man,
- enrich understanding of natural resources
important to the nation - Use all practical means and measures to
- foster and promote the general welfare
- create and maintain conditions under which man
and nature exist in productive harmony - fulfill social, economic, and other
requirements of present and future generations of
Americans
5Federal Responsibility
- Trustees of the environment
- Assure safe, healthful, productive, esthetically
and culturally pleasing surroundings - Attain widest range of benefit without
degradation or undesirable and unintended
consequences - Preserve important historic, cultural, and
natural aspects - Achieve balance between population and resource
use - Enhance the quality of the environment
6Decisionmaking Framework
- Systematic and interdisciplinary approach
- Environment given appropriate consideration with
economic and technical considerations - Include in proposals, a detailed statement on
- environmental impacts of the action
- adverse impacts which cannot be avoided
- alternatives to the proposed action
- consequences of taking the proposed action
- Consult with Federal agencies and involve the
public
7NEPA Implementation
CEQ Regulations 40 CFR 1500-1508
NEPA
CEQ Implementation
8Elements of the NEPA Process
- Federal Decisionmaking
- Alternatives analysis
- Impacts evaluation
- Mitigation avoid, minimize, and compensate
- Public involvement
- Interagency coordination
- Process and documentation
- Inform decisions of non-Federal entities
9CEQ Regulations
- Implement action forcing provisions of NEPA
- Comply with procedures and achieve goals
- Better decisions not just better documents
- Integrate NEPA with planning other processes
- Encourage and facilitate public involvement in
decisionmaking - Reasonable alternatives
- Avoidance and minimization of adverse impacts
- Reduce paperwork and delay
40 CFR 1500 - 1508
10NEPA Jurisprudence
- Procedural not substantive - process not decision
- Considerable deference given to the lead agency
- Hard look" at significant environmental impacts
- Inform decisionmakers
- Reasoned decision
- Inform the public
11NEPA Implementation
12FHWA Project Decisionmaking
- Project Development Process
- 23 USC 109(h) Standards
- Project decisionmaking
- NEPA implementation
- 23 CFR 771
- Transportation planning process provides
essential information
1323 USC 109 (h)
- Standards
- (h) assure that possible adverse economic,
social, and environmental effects have been fully
considered - final decisions on the project are made in the
best overall public interest - taking into consideration the need for fast,
safe and efficient transportation, public
services, and the costs of eliminating or
minimizing such adverse effects and
14FHWA Regulations
- Environmental investigations, reviews, and
consultations be coordinated as a single process - Compliance with all applicable requirements be
reflected in the environmental document - Alternatives be evaluated and decisions be made
in the best overall public interest considering - Public involvement, systematic and
interdisciplinary approach essential to project
development - Incorporate measures to mitigate adverse effects
15Project Development
- Early and continuous interagency coordination
- Meaningful evaluation of alternatives
- avoidance of commitments before improvement
is fully evaluated - logical termini, independent utility, not
restrict consideration of alternatives - State public involvement and hearing procedures
- Final design, property acquisition, construction
- shall not proceed prior to CE, FONSI or ROD
- NEPA approval constitutes acceptance of the
general project location and concepts
16- Endangered Species Act Section 7
- Civil Rights Act
- Executive Order 12898 (Environmental Justice)
- Section 4(f) of USDOT Act (49 USC 303) - Parks,
recreation, etc - Clean Air Act
- Safe Water Drinking Act
- Clean Water Act 404(b)(1)
- Farmland Protection Policy Act
- National Historic Preservation Act
- Floodplains
- Economic, Social, and Environmental Effects (23
USC 109(h)) analysis - Public involvement, interagency coordination
- Tribal consultation
- Location, design, and engineering
- Uniform Relocation Assistance and Real Property
Acquisition Policies Act of 1970 - Noise Standards
- Public Hearing Requirements
- Americans with Disabilities Act
17Applicants Responsibility
- Detailed statements for a major Federal action
funded under a program of grants to States shall
not be deemed legally insufficient solely by
reason of having been prepared by a State agency
or official, if - agency or official has statewide jurisdiction and
has the responsibility for such action - Federal official furnishes guidance and
participates in such preparation - official independently evaluates statement prior
to its approval adoption
NEPA 102(d) Amended
18Transportation Project Development
System, coordination, conformity, project
purpose, need and alternatives
Planning
Needs, alternatives, impacts, public / agency
coordination, documentation
NEPA
NEPA Approval Location, design concept
acceptance and environmental decisions
Final Design
Post NEPA Project Development Activities
Right-of-Way
Construction
19Elements of the NEPA Process
- Alternatives analysis based on Purpose and Need
- Impact analysis
- Mitigation
- Public involvement
- Interagency coordination
- Documentation
20NEPA Process
Planning / pre-NEPA
Proposed Action
Coordination and Analysis
YES
NO
Significant Impact ?
Unknown
Significant impact
Listed CE
Documented CE
Environmental Assessment
Notice of Intent Scoping Process
Draft EIS
Coordination and analysis as needed
No significant impacts
Public Comment
Document appropriately
Final EIS
Finding of No Significant Impact (FONSI)
Record of Decision (ROD)
Agency Action
Agency Action
Agency Action
21Purpose and Need
- Inform decisions
- Provides critical foundation for alternative
decisions - Basis for reasonable alternatives, evaluations,
and comparisons - Validates reasons for going forward with Federal
action - Basis for dismissal of no-action
22Alternatives Analysis
- Varies with Class of Action CE, EA, EIS
- Rigorous and objective evaluation in the EIS
- Reasonable range of alternatives
- Reasonable number of alternatives
- Must include no-action or no-build
- Build alternatives representative number
- improve existing
- new location
- Modal and operational (where appropriate)
- TSM alternatives, transit
- Avoidance and minimization
23FHWA Policy on Alternatives
- Alternatives be evaluated and decisions made in
the best overall public interest considering - the need for safe and efficient transportation
- social, economic, and environmental impacts
- National, state, and local environmental goals
- Ensure meaningful evaluation of alternatives
- Logical termini
- Independent utility
- Restrict consideration of alternatives for
reasonably foreseeable improvement
23 CFR 771.105(b) and 23 CFR 771.111(f)
24Environment
- NEPA
- Natural and physical environment and
- relationship of people with that environment
- 40 CFR 1508.14
- 23 U.S.C 109 (h)
- Social, economic, and environmental effects
- manmade and natural resources
- public facilities and services
25Resources
- Communities, housing, businesses
- Land use
- Wildlife, habitat, endangered species
- Waters of the U.S. including wetlands
- Historic properties and districts
- Parklands and recreation areas
- Agricultural land
- Air quality (local and air basin)
26Direct Impacts
- Caused by the action and occur at the same time
and place. - (40 CFR 1508.8)
Direct Environmental Impacts
Project Action
27Indirect Impacts
- Caused by the action and are later in time or
farther removed in distance, but are still
reasonably foreseeable - Growth inducing and other effects on air and
water and other natural systems, including
ecosystems, related to induced changes - in the pattern of land use, and
- population density or growth rate
- (40 CFR 1508.8)
28Indirect Impacts
Indirect Environmental Impacts
Project Action
Related Actions
- Alter behavior and function of affected
environment caused by encroachment - Project-influenced effects
- Effects related to project-influenced development
29Cumulative Impacts
- Result from incremental impacts of the action
when added to other past, present, and reasonably
foreseeable future actions, regardless of agency
or person that undertakes other actions - Can result from individually minor but
collectively significant actions taking place
over a period of time - 40 CFR 1508.7
30Cumulative Impacts
31Resource Impact Continuum
Past, present and future cumulative affects
Project Impacts
Indirect Impacts
Resource size, function, quality, and condition
over time
Present
Past
Future
32Reasonably Foreseeable
- Not required to engage in speculation or
contemplation - Possible but not probable effects may be excluded
from NEPA analysis - Reasonably foreseeable events, although
uncertain, must be probable or likely - Consider the likelihood of impacts
- Based on informed judgment
33Context
Intensity
Significant Impact
34 Context
Context
35Mitigation of Impacts
- CEQ defines mitigation as
- avoidance, minimization, and compensation
Direct Environmental Impacts
Project Action
Avoid and minimize
compensate
36FHWA Mitigation Policy
- 23 CFR 771.105(d)
- Measures necessary to mitigate adverse impacts
will be incorporated into the action and are
eligible for Federal funding when the
Administration determines that - (1)Â The impacts actually result from the
Administration action and - (2)Â The proposed mitigation represents a
reasonable public expenditure after considering
the impacts of the action and the benefits of the
proposed mitigation measures.
37Considerations
- Modifying the proposed project
- Adding additional avoidance or minimization
measures - Providing compensatory mitigation for affected
resources - Identifying mitigation measures other parties can
implement
38Alternatives, Impact and Mitigation Analysis
Floodplains
Neighborhood
Industrial Site
Route 104
Wetland
Historic Site
Route 100
Route 200
39Implementation Responsibility
- Implement mitigation measures stated as
commitments in environmental documents - Responsibility of the Applicant
- FHWA will ensure compliance through project
management - Formal monitoring plan may be established
(recommended where sensitive resources are
impacted)
40Coordination and Involvement
- Prior to concluding an EIS, the responsible
Federal official must - consult with and obtain the comments of any
Federal agency with jurisdiction by law or
special expertise with the impacted resources - provide copies of statement to Federal, State
and local agencies and the public
41Public Involvement - FHWA
- Coordination of public involvement activities and
hearings with entire NEPA process - ... Early and continuous opportunities for the
public to be involved in the identification of
social, economic, and environmental impacts - via State public involvement procedures and
requirements for public hearings
23 CFR 771.111
42Interagency Coordination
- Early and continuous participation in the NEPA
process - Special expertise and information
- Scoping agreements and understanding
- Establish timeframes
- Consultation and permitting
- Adoption of NEPA documents
43(No Transcript)
44Scoping
- Continuation of early involvement with affected
agencies and interested public - Formally associated with EIS process
- Invite participation
- Determine the scope of the study
- Determine important vs minor issues
- Allocate assignments if appropriate
- Identify other studies in area
- Agree on timing of activities
40 CFR 1501.7 CEQ Scoping Guidance
45NEPA Process
Planning / pre-NEPA
Proposed Action
Coordination and Analysis
YES
NO
Significant Impact ?
Unknown
Significant impact
Listed CE
Documented CE
Environmental Assessment
Notice of Intent Scoping Process
Draft EIS
Coordination and analysis as needed
No significant impacts
Public Comment
Document appropriately
Final EIS
Finding of No Significant Impact (FONSI)
Record of Decision (ROD)
Agency Action
Agency Action
Agency Action
46Categorical Exclusion
- CEQ - actions which do not individually or
cumulatively have a significant effect on the
human environment - FHWA - actions which meet the CEQ definition and,
based on past experience with similar actions, do
not involve significant environmental impacts - Neither an EA nor EIS is required
- 40 CFR 1508.4
- 23 CFR 771.117(a)
47Categorical Exclusions
- 23 CFR 771.117(c) - actions that meet the
criteria for CEs - - Normally require no further approvals
- Notify FHWA project is a c-list action
- Reference the regulation
- 23 CFR 771.117(d) - additional actions that meet
the criteria for a CE may be designated as CEs
only after Administration approval - FHWA individual project approval required based
on submitted documentation
48Environmental Assessment
- Document prepared for an action
- where the significance of the social, economic,
and environmental impacts are not clearly
established - Concise public document
- Briefly provide evidence and analysis
- Include brief discussions of
- Not contain long descriptions or detailed data
- Not mini EISs
23 CFR 771.115(c) 40 CFR 1508.9
49FONSI
- Finding Of No Significant Impact
- Document that briefly presents why the action
does not have a significant impact - Includes and references the EA
- Approved by FHWA Division
- Need not be circulated
- Notice of availability
- sent to affected agencies
- sent to Statewide clearinghouse (EO 12372)
- published in local newspaper (recommended)
- Available upon request by the public
50NEPA Process
Planning / pre-NEPA
Proposed Action
Coordination and Analysis
YES
NO
Significant Impact ?
Unknown
Significant impact
Listed CE
Documented CE
Environmental Assessment
Notice of Intent Scoping Process
Draft EIS
Coordination and analysis as needed
No significant impacts
Public Comment
Document appropriately
Final EIS
Finding of No Significant Impact (FONSI)
Record of Decision (ROD)
Agency Action
Agency Action
Agency Action
51EIS
- Environmental impacts of the proposed action
- Unavoidable adverse environmental impacts
- Alternatives to the proposed action
- Irreversible and irretrievable commitments of
resources - Relationship between short term uses and
maintenance and enhancement of long term
productivity
52Adequate Evaluation
- More than a list of resources and potential
project impacts - Examine resources over time - past, present, and
future - Determine growth associated with project
- Consider the indirect reasonably foreseeable
impacts of the project - Reasonable analysis
- Hard look
53EIS Document Contents
- Summary
- Purpose and Need
- Alternatives
- Affected Environment - Existing Setting
- Social, economic and natural environmental
- Environmentally Sensitive Features
- Environmental Consequences
- Probable Environmental Impacts and Mitigation
- Comments and coordination
54Final EIS Additions
- Preferred alternative and basis for decision
- Alternatives not preferred and reason why
- Mitigation and enhancement measures
- Major unresolved issues and approach to resolve
them - Coordination, comments, and responses
- Final 4(f) and other findings
23 CFR 771.125(a)(1)
55HQs Prior Concurrence
- Inadequate coordination w/government agencies
- Inadequate discussion of social, economic, and
environmental impacts - Impacts are unusually great
- National policy issues
- Major unresolved issues
- Agency opposition on environmental grounds
23 CFR 771.125(c)
56FHWA Legal Sufficiency
- Review
- Legal requirements have been met
- Document and process is defensible
- Document was properly developed
- Answers questions that can be reasonably asked
- FEIS discussion is adequate
23 CFR 771.125(b)
57EPA 309 Review
- Rating environmental impacts
- LO - lack of objections
- EC - environmental concerns
- EO - environmental objections
- EU - environmental unsatisfactory
- Rating adequacy of the impact statement
- 1 - adequate
- 2 - insufficient information
- 3 - inadequate
58CEQ Referral Procedure
- When a Federal agency determines the project is
environmentally unsatisfactory - CEQ acts as arbitrator or otherwise rules on the
dispute - Specific time periods are mandated
- Referral must occur within 25 days of FEIS
availability notice - 40 CFR 1504
59Record of Decision
- Incorporate by reference and cross reference FEIS
- Decision - identify selected alternative
- Alternatives considered
- Discuss values considered and basis of decision
- Identify environmentally preferred
alternative(s) - Section 4(f) - summarize basis of approval
- Measures to minimize harm - describe mitigation
- Monitoring or enforcement program included
- Comments on FEIS - substantive comments and
responses
40 CFR 1506.9 23 CFR 771.125(g)