Monthly Status Reporte-Payroll
  • Ona Elliott, Project Manager
  • 256-544-7342
  • Month Ending May 2004

2
Table of Contents
  • Summary Status
  • Accomplishments
  • Activities in Progress
  • Project Key Schedule/Activities Metrics
  • Cost Estimate
  • Top 5 Issues
  • Backup

3
Summary Status
Interface Priority Categories - (1) critical
for payroll processing, (2) critical for business
operations, and (3) necessary but not critical
for business continuity
4

Accomplishments
  • Simulated Testing
  • Completed Simulation Parallel Test 3 (May 17
    21)
  • Successfully loaded and validated the Time and
    Attendance data from WebTADs
  • Validated approximately 90 of the bi-weekly pay
    processing functions with the remaining 10 due
    to Change Request that will be tested during the
    formal parallel stage
  • Successfully produced and distributed labor files
    to labor distribution systems at all centers
  • Conducted Formal Parallel 1 Center Test
    Readiness Reviews (May 26-29, 2004)
  • Legacy System Interface Development
  • Application (EAI) Connectivity
  • IT Readiness
  • User Accounts/FPPS Security
  • Communications
  • Steering Committee Meeting Authority to
    Proceed/Status meeting held on May 27, 2004 
  • Provided e-Payroll status briefing to the HR
    Directors May 13, 2004
  • Submitted budgetary guidance to centers
    concerning e-Payroll cost estimates and funding
    responsibilities


5

Accomplishments
  • Formal Parallel Test 1
  • Completed Formal Parallel Test 1 Entry and Pay
    Calculate (June 7 17)
  • Successfully produced and distributed labor files
    to labor distribution systems at all centers
  • Successfully completed First Runs for all
    interfaces and scheduled via Control-M
  •  Change Management
  • Developed an extensive online job aid for
    Requesting Office users managers and
    administrative staff who will develop SF-52s
    online in FPPS
  • Participated in teleconferences with HR Directors
    and Deputy CFOs to brief them on e-Payroll
    changes
  • Briefed local unions on detailed changes
  • Advertized Employee Express changes at the
    centers
  • Interface Control Documents (ICD) Status 100
    Complete


6
Activities In Progress
  • Validation of Formal Parallel 1 Information
  • All centers reviewing labor and other interface
    files
  • Posting of labor files to SAP scheduled for
    completion by June 25, 2004
  • Reviewing time and attendance data for possible
    conversion enhancements
  • Verifying Parallel 1 change request
  • Continued data validation
  • Preparation for Key Milestone Events
  • Center Test Readiness Reviews scheduled for week
    of June 28,2004
  • Formal Parallel 2 Test Readiness Review
    scheduled for July 7, 2004
  • Steering Committee Authority to Proceed meeting
    scheduled for July 9, 2004
  • Formal Parallel 2 Begins July 19, 2004
  • Report Control Documents (RCD) Status 73
    Complete (19 of 26 Completed)
  • 4 RCDs awaiting final approval
  • 3 RCD under development
  • 10 reports published in datamart and available
    for review by centers
  • Remaining completed reports have been forwarded
    to DOI to be published for Parallel 2

7
Activities In Progress
  • Documentation
  • Finalizing operations plan
  • Center Operational Level Agreement (OLA) to be
    distributed to centers on July 2, 2004
  • Revising Service Level Agreement (SLA)
  • Security services agreement
  • Security plan update
  • Cutover Plan
  • Operations Readiness Review
  • Establishing checklist and draft presentation
  • Technical
  • Evaluating application performance monitoring
    tool
  • System connectivity and acceptance testing 95
    complete
  • Change Management
  • Finalize agency communication plan
  • Complete customization of the DOI Requesting
    Office Web Based Training (WBT) to NASA's needs
  • Develop a job aids for Brio users and testers
  • Develop a fact sheet that managers can use to
    brief their employees on e-Payroll changes
  • Begin briefings with managers and administrative
    personnel at the centers

8
Project Key Schedule Activities Metrics
  • Agency Report Development 19 of 26 reports
    complete
  • Legacy System Development Complete
  • Majority of centers 90-95 completed with
    development
  • KSC Labor delayed until week of 6/25/2004

9
e-Payroll Cost Estimate
10
Key e-Payroll Issues
11
Reference / Backup
BACKUP
12
e-Payroll Budget Information
  • Total Agency Cost 7,500K
  • Estimated Cost To Date (2,575K)
  • Amount Received To Date 5,700K
  • ----------
  • Balance 1,800K
  • Project Reserve Funding Allocation
  • Possible Increase in DOI estimates for CR
    development
  • Post Implementation Activities
  • Implementation Contingency Plans