Title: FEE Installation


1
FEE Installation Commissioning TPC Meeting, 17
February 2006 L. Musa
  • Content
  • Status of FEE Installation
  • Installation and Commissioning Schedule

2
FE Cards Installation 1/4
  • Installation Team Schedule
  • Roberto Campagnolo, Antoine Junique, Luciano
    Musa, Lennart Osterman,
  • Bjorn Halvor Straume (? Gunnar Lovhoiden)
  • 2 x 7-hours shifts per day, 6 days / week
  • Installation started on the 30th January (17
    working days)
  • Status
  • 16 Sectors of A side are complete, 17th Sector
    almost complete (12 cards to be installed) ? 2043
    FECs installed
  • the 18th sector (Sector 13) can only be
    installed on next Wednesday after the
    installation of the new I-bars on the A side

3
FE Cards Installation 2/4
TPC A Side (17th February 06)
4
FE Cards Installation 3/4
17th February 06
10
11
12
5
FE Cards Installation 4/4
During the installation, the FECs are tested
individually (stand-alone) by means of a
dedicated mounting test tool, U2F (USB to FEC
interface)
  • Readout of trigger related data (pulser)
  • Connection to the pad plane
  • Measurement of VCCA, VCCD, IA, ID and T
  • Test of all CSRs, Control Readout path

U2F Card
6
Installation Test Software 1/2
7
Installation Test Software 2/2
8
Installation Summary Results
List of pads that do not have a proper connection
to the transfer connector
9
Installation and Commissioning Schedule 1/2
  • FECs Mass test
  • completed in January 06
  • RCU Production (240 units including 10 spares)
  • completed in November 05
  • RCU Mass Test
  • completed in December 05
  • Delivery of tested DCS cards January 06
  • Delivery of tested SIU cards April 06
  • Assembly and final test of RCU SIU DCS May
    06

10
Installation and Commissioning Schedule 2/2
PHASE I
  • Installation of FECs and Backplanes Jan 05 -
    Mar 06
  • functional and electrical test of each FEC
  • test of the connection between FECs and pad plane
  • test of the connection between FECs and readout
    backplane

PHASE II
  • Inspection of the system with RCUs Mar Sep 06
  • Inspection of up to 12 readout partitions (2
    Sectors) concurrently
  • Comprehensive test FEE, DAQ, DCS, TRIGGER, HLT,
    ECS (power bars and cooling required)

PHASE III
  • Installation of RCUs May Jun 06
  • thorough test of all (216) readout partitions