Title: FEE Installation
1FEE Installation Commissioning TPC Meeting, 17
February 2006 L. Musa
- Content
- Status of FEE Installation
- Installation and Commissioning Schedule
2FE Cards Installation 1/4
- Installation Team Schedule
- Roberto Campagnolo, Antoine Junique, Luciano
Musa, Lennart Osterman, - Bjorn Halvor Straume (? Gunnar Lovhoiden)
- 2 x 7-hours shifts per day, 6 days / week
- Installation started on the 30th January (17
working days) - Status
-
- 16 Sectors of A side are complete, 17th Sector
almost complete (12 cards to be installed) ? 2043
FECs installed - the 18th sector (Sector 13) can only be
installed on next Wednesday after the
installation of the new I-bars on the A side
3FE Cards Installation 2/4
TPC A Side (17th February 06)
4FE Cards Installation 3/4
17th February 06
10
11
12
5FE Cards Installation 4/4
During the installation, the FECs are tested
individually (stand-alone) by means of a
dedicated mounting test tool, U2F (USB to FEC
interface)
- Readout of trigger related data (pulser)
- Connection to the pad plane
- Measurement of VCCA, VCCD, IA, ID and T
- Test of all CSRs, Control Readout path
U2F Card
6Installation Test Software 1/2
7Installation Test Software 2/2
8Installation Summary Results
List of pads that do not have a proper connection
to the transfer connector
9Installation and Commissioning Schedule 1/2
- FECs Mass test
- completed in January 06
- RCU Production (240 units including 10 spares)
- completed in November 05
- RCU Mass Test
- completed in December 05
- Delivery of tested DCS cards January 06
- Delivery of tested SIU cards April 06
- Assembly and final test of RCU SIU DCS May
06
10Installation and Commissioning Schedule 2/2
PHASE I
- Installation of FECs and Backplanes Jan 05 -
Mar 06 - functional and electrical test of each FEC
- test of the connection between FECs and pad plane
- test of the connection between FECs and readout
backplane
PHASE II
- Inspection of the system with RCUs Mar Sep 06
- Inspection of up to 12 readout partitions (2
Sectors) concurrently - Comprehensive test FEE, DAQ, DCS, TRIGGER, HLT,
ECS (power bars and cooling required)
PHASE III
- Installation of RCUs May Jun 06
- thorough test of all (216) readout partitions