Title: Diapositiva 1
1Update on Installation Planning
Technical Board 12.4. 2007
- Update on installation
- New TOF/TRD installation procedure
- Updated schedule
2Installation Logbook
Daily Meeting at P2, 1700 Installation logbook
and minutes of daily meeting on
http//riegler.home.cern.ch/riegler/installation
/home.htm
3ITS (SSDSDD) Lowering to the Cavern
15.3. 2007
4ITS (SSDSDD) Lowering to the Cavern
15.3. 2007
5ITS (SSDSDD) Lowering to the Cavern
15.3. 2007
6ITS (SSDSDD) Lowering to the Cavern
15.3. 2007
7Beampipe Installation and Bakeout
16.3. 2007
8Beampipe Installation and Bakeout
19.3. 2007
9Beampipe Installation and Bakeout
19.3. 2007
10Beampipe Installation and Bakeout
19.3. 2007
11Beampipe Installation and Bakeout
19.3. 2007
12Beampipe Installation and Bakeout
19.3. 2007
13Beampipe Installation and Bakeout
20.3. 2007
14Beampipe Installation and Bakeout
22.3. 2007
15Beampipe Installation and Bakeout
22.3. 2007
16V0 Installation
2.4.-4.4. 2007
17T0 Installation
5.4.-4.4. 2007
18Conclusion on installation progress
ITS transport and installation without
problems. Beampipe installation and bakeout
without any problems. Big effort from VAC group.
Optimized planning foresaw 19 working days.
Entire job was performed in 12 working days.
! Big thank you to VAC group for being
efficient, flexible and accepting our continuous
delays ! V0 detector installed and tested. FMD
detector installation starts tomorrow 13.4. ?
Currently we are one week ahead of the February
TB planning.
19Current Planning
20Current Planning
21Current Planning
22- SPD 23. April ? 25.June
- 2 Months delay on the sequence
- Decoupling TOF/TRD installation from Miniframe we
can reduce the delay to one month
23Dec 2006 1 TRD, 2 TOF
1
2
1
2
24July 2007 1 PHOS, 3 TRD, 7 TOF
5
7
1
1
2
3
2
3
4
6
PHOS Free HMPIDTRDTOF HMPIDTOF HMPID
1
252008 3 PHOS, 7 TRD, 18 TOF
17
15
11
14
9
5
7
7
5
1
1
2
3
2
3
4
4
6
8
6
10
12
16
13
18
3
2
1
26? 2009 5 PHOS, 18 TRD, 18 TOF
17
16
11
17
14
15
9
13
11
9
5
7
7
5
1
1
2
3
2
3
4
4
8
6
8
6
12
10
10
12
16
18
14
16
13
18
3
5
2
4
1
27New Procedure for TOF/TRD Installation
- TOF/TRD Installation window is locked in the
detector installation sequence because DF must be
removed and Miniframe must not yet be there. - No Flexibility
- Miniframe must be removed whenever we want to
install TOF/TRD (V0/T0/PMD/ALL ITS cables ) - Can we install TOF/TRD with the Miniframe in
place ? - Idea Use shielding wall elements together with
simple bars to construct an installation platform
with the miniframe in place. This installation
platform should have the same size as the yellow
platform surface. - For the lower 5 sectors one has to remove the
compensator platform and hold the miniframe by
bars attached to the A-side machine shieding.
28TRD
29TRD
30TRD
31TRD
32SIDE VIEW
TRD
S01
33TRD
34TRD
35TRD
36TOF
37TOF
38TOF
39TOF
40Conclusion on TOF/TRD Installation
- TOF/TRD Installation with miniframe in place
seems possible. An installation platform with an
area equal to the yellow platform can be
provided. - Great advantage we can keep ITS cabled while
installtion TOF/TRD. - Compensator platform must be removed for the
lower 5 modules. Miniframe is fixed to the
shielding wall during this procedure.
41Delayed Planning
42Delayed Planning
43Delayed Planning