Title: Grid Interconnection


1
Grid Interconnection
  • SCE Efforts To Expedite Interconnection Of
    Additional Generation

2
Interconnection Process
  • Complete Application
  • Execute System Impact Study Agreement
  • System Impact Study
  • Execute Facility Study Agreement
  • Facility Study
  • Interconnection Agreement
  • Assigned Project Coordinator for Each Project

3
Interconnection Request
  • Letter to SCE with the following information
  • Identity, address, telephone number and facsimile
    number of applicant
  • Interconnection point
  • Maximum amount of interconnection capacity
  • Proposed interconnection date
  • Electrical location of generator and ultimate
    load, if known
  • Deposit, if required
  • Provide technical data for project (blank data
    sheets available upon request)

4
Executive Order D-26-01
  • For peaking and renewable power plants on-line by
    September 30, 2001
  • Complete Interconnection Study within 7 business
    days after complete request and signed study
    agreement
  • Identify general electric system impacts and
    possible mitigation measures
  • Based on power flow and fault current studies
  • Additional studies may also be required after
    completion of 7-day study
  • Interconnection Agreement can be signed after
    7-day study
  • Generator assumes responsibility for additional
    impacts if identified

5
Additional Efforts to Expedite Interconnection
  • Initiation of engineering, design and procurement
    in parallel with System Impact and Facilities
    Studies
  • Consolidation of System Impact and Facilities
    Studies under one agreement
  • Use of SCE equipment inventory or reserved
    manufacturing space (if available)
  • Allow early connection of generators where
    problems not expected
  • Allow early operation prior to other projects
    with earlier queue but later operating date

6
Ways Generator Can Help Expedite Interconnection
  • Submit complete information with application
  • Including technical machine data
  • Submit applications as early as feasible
  • Sign and return all agreements and other items in
    less than allowed times
  • Reduce or eliminate project changes
  • Although limited changes are accommodated,
    changes may delay or require re-work of studies
  • Changes may also impact subsequent generators in
    the queue

7
Interconnection Request Status
  • 61 active requests, totaling over 20,000 MW
  • 20 requests for operation by Summer 2001,
    totaling 1665 MW
  • Interconnection agreements completed with 11
    generators, totaling 634 MW

8
Additional Information / Contacts
  • Interconnection Requests (Wholesale Generation)
  • Wes Williams
  • Project Manager, Grid Interconnection and
    Contract Development
  • Phone (626) 302-9615
  • Fax (626) 302-1152
  • E-mail Weston.Williams_at_sce.com
  • SCEs FERC Interconnection Tariffs