Title: SAP Capital Investment Process Integration at SCA Packaging
1SAP Capital Investment Process Integration at
SCA Packaging
- Marc Moons, SAP Controller, SCA Packaging
- Olivier Van Gompel, Executive Partner, Opteon
- SAP Lounge, BrusselsOctober 8-9, 2008
2Agenda
- Introduction
- 1.1. SCA Packaging Corporate Highlights
- 1.2. Opteon Corporate Highlights
- SCA Capital Wheel concept
- 2.1 Capital Wheel before SAP Integration
- 2.2 Challenges regarding CAPEX follow up
- 2.2 Capital Wheel after SAP integration
- Project Scope
- 3.1. Phase 1 Scope Implementation - challenges
- 3.2. Phase 2 Scope Implementation - challenges
- Capital Wheel Further Improvements
- Cost savings efficiencies reached
- Lessons learned
3SCA Packaging Corporate Highlights
- Second largest producer in the European
Corrugated market with over 200 producing units
in 25 countries - Second largest European producer of
containerboard paper with 7 mills situated in 5
countries - Leading global supplier of customized protective
packaging and high-visibility thermoformed
plastic packaging - More than 250 packaging designer engineers
across Europe - Worldwide sales in 2007 exceeded SEK 33 billion
( 3.6 billion) - 17,263 employees
4SCA Packaging as part of SCA Group
- Publication paper
- Solid-wood products
- Pulp and timber
- Transport and consumer packaging
- Containerboard
- Toilet paper, kitchen rolls, facial tissue and
napkins - Hygiene concepts
- Incontinence care
- Baby diapers
- Feminine care
5Opteon Corporate HighlightsAchieving Optimal
Use of Your Business Systems
- SAP Life Cycle Align To Strategy
- Necessary framework to achieve and maintain
optimal use of the system - Addressing the ongoing need for changes, coming
from both internal and external triggers within
the business environment - Strengths
- SAP ERP functional and business process knowledge
- Project Management Methodology based on PMI/PMBOK
Best Practices - Service Management Methodology based on ITIL Best
Practices
6SCA Packaging SAP Landscape before CAPEX
Integration
- 58 of turnover generated within SAP
- 156 companies with FI/CO
- 47 companies with full SAP FI/CO/SD/MM
- 11 companies with PP
- Number of SAP users 2400
- SAP IM 262 users
- Use of BI (7.0) and Portal (7.0)
SAP R/3
PP
WM
7Capital Wheel before SAP Integration
- ICT based investment processes
- eCapex web application
- Investment approval process
- New request introduction reduces
- allocated budget
- Other processes were Excel based
8CAPEX Processes Challenges
- ICT based investment processes
- Investment approval process
- Approval of new request reduces allocated budget
- Revision of CAPEX approval processes in a changed
environment different needs and requirements - One investment, one system
-
- eCapex application
- Complex support maintenance
- Lack of stability
- Ending support
- Alternatives to eCapex
- SAP Investment Management
- Build upon existing SAP experience
- SAP IM allowed stand alone implementation,
without necessary integration with costing and
finances
9Capital Wheel after SAP Integration
10Capex Integration Project Scope Phase 1
- Quick replacement of eCapex
- Required for all entities (SAP and non SAP
entities) - Upload historical information (closed ongoing
investment requests) - Harmonize SCA Capex approval procedures
throughout region, but allow differences - Automated approval process through workflow
- Tracing of approved and rejected requests
- Activate Document Management System
SAP R/3
PP
DMS
WF
WM
HR
11Phase 1 Process Flow
Check Target - Plan
HR
WF
IM
Update IM Plan
Approved
No
Yes
IM
IM
DMS
12Phase 1 Implementation (April 05-July 05)
- SAP Investment Management
- Investment program (controlling area level)
- Activation of appropriation requests
- Activation of appropriation request approval
workflow - Usage of partner determination schemes for
approval hierarchy - Usage of standard field selection and tab layout
to customize layout for end user - Foresee appropriation request entry for non-SAP
legal entities - Implementation of phase 1, with phase 2 in mind
- Appropriation request numbering coding masks
identical to project WBS coding masks - P-XXXX-YY-NNN
13SAP Portal Approval
14Phase 1 Challenges
- Timing eCapex would be decommissioned 3 months
after decision - Solution Activate SAP IM and custom made
workflow in 2 months time. - Multiple controlling areas, require multiple
investment programs - Solution Merge controlling areas into one
controlling area - Performed by SAP Services Waldorf
- Multiple currencies per region
- Solution SAP version 4.7 allows budgeting and
planning in object currency - Controlling area currency for reporting in EUR
- Quick approval process by management
- Solution Activate SAP Portal for approval
process
15Capex Integration Project Scope Phase 2
- Integrate SAP IM with commitments and actuals in
SAP plan budget- actual - Integrate FI-AA-PM-MM into Capex processes
- Replacement of internal orders and plant
maintenance orders with projects and WBS elements - Build solid basis for further improvements
- - Capital Budgeting
- - Capex Forecasting Processes
- - Asset Disposals
SAP R/3
PS
PP
DMS
WF
WM
HR
16Phase 2 Process Flow
Mail to project responsible
WF
Release WBS
WF
PS
WF
Create WBS element
Transfer plan data Assign Budget
Assign WBS Master data
PS
PS
WF
WF
IM
17Phase 2 Implementation (April 06 July 08)
- SAP Project Systems
- Set up PS and link to IM appropriation request
- Cut over from existing SAP PM/CO environment to
SAP PS/IM for Capex - Improve workflow to automate transactional steps
project creation budget distribution - Roll out of Phase 2 solution
- Limited to full SAP run legal entities
- After pilot in Obbola, Sweden
- implementation in 5 other plants in Europe in
Sweden, Netherlands, Great-Britain, Italy (2
months total) - Implementation in 20 plants in Germany (big bang
roll out) - Handover to central SCA IT department München for
further support and roll out (July 2008)
18Phase 2 Challenges
- Change over from PM / CO order budget process to
IM-PS process, whilst integrating IM - Solution Pilot roll out in Obbola, Sweden
- Roll out in Europe
- Solution Phased roll out region by region.
Knowledge transfer to central IT services - Change management for end users in all plants
- Solution Detailed procedures and training
required for decentralized controllers and
engineers
19Procedural guidelines examples
20Procedural guidelines examples
21Procedural guidelines examples
22Capital Wheel Further Improvements
- Capital Budgeting process
- Usage of request and WBS plan values and plan
version 5x for capital budgets - Update plan values in investment program for SAP
based reporting - Extract to data warehouse (BI 7.0) for aggregated
reporting and for input to SCA consolidation
system (ABS) - Replacement of Excel based reporting
- Replace manual and duplicate entries by automated
data flows, based on single entry - Capital Forecasting process
- Extend capital budget process for quarterly
capital forecasting processes - Project Systems Cash Flow Management
23Further improvements Capital Budgeting /
Forecasting
IM
Non SAP
24Cost savings Efficiencies reached
- Cost Savings
- Decommissioning of eCapex
- Avoid duplication of data in multiple systems /
Excel sheets (less errors, and more reliable,
timely information) - Centralized support possible due to process
harmonization - Time consuming reconciliations between various
systems can be avoided - Efficiencies
- Harmonize Capex approval process via system
driven process - Allow operational audit on Capex processes
tracking plan-actual-budget - Accurate consolidation and analysis
- Improve traceability
25Lessons learned
- Change Management
- Difficult to get users away from Excel sheets
- Multiple currency environment build new reports
in IM/PS for object currency reporting - Phased approach get people used to massive
changes in processes - Get customer buy-in for further improvements let
the customer benefit from an integrated system - Usage of SAP Portal in approval process generated
easier end user acceptance - Workflow development
- Embedded controls in workflow proved to be more
difficult than foreseen - Pilot roll out concept
- Use same project team for implementation and
initial support. - Improve system before further roll out
- Project Management
- Project Life Cycle Approach
- Manage deliverables
- Manage various stakeholders Business, IT,
functional and technical consultants