LCLS Linac Overview E' Bong Lehman Review August 10, 2004 PowerPoint PPT Presentation

presentation player overlay
1 / 25
About This Presentation
Transcript and Presenter's Notes

Title: LCLS Linac Overview E' Bong Lehman Review August 10, 2004


1
LCLS Linac OverviewE. Bong Lehman Review
August 10, 2004
LCLS
2
LCLS Linac Overview
  • Technical Scope and Status
  • Linac Functional Areas
  • Long Lead Procurement Items
  • Schedule and Organization
  • Linac Challenges

3
Nominal LCLS Linac Parameters for 1.5-Å FEL
Single bunch, 1-nC charge, 1.2-mm slice
emittance, 120-Hz repetition rate
250 MeV ?z ? 0.19 mm ?? ? 1.6
14.1 GeV ?z ? 0.022 mm ?? ? 0.01
135 MeV ?z ? 0.83 mm ?? ? 0.10
Linac-X L 0.6 m ?rf -160?
4.54 GeV ?z ? 0.022 mm ?? ? 0.71
E-Dump
LCLS INJ
Linac-1 L ?9 m ?rf ? -25
Linac-2 L ?330 m ?rf ? -41
Linac-3 L ?550 m ?rf ? -10
undulator L 130 m
21-1b 21-1d
X
21-3b 24-6d
25-1a 30-8c
SLAC linac
BC-1 L ?6 m R56? -39 mm
BC-2 L ?22 m R56? -25 mm
DL-1 L ?12 m R56 ?0
LTU L 275 m R56 ? 0
research yard
SLAC linac tunnel
(RF phase frf 0 is at accelerating crest)
4
Baseline System Design
  • 1.5-Å SASE FEL Linac
  • Requirements
  • Acceleration to 14.3 GeV (4.5 GeV min.)
  • Bunch compression to 3.4 kA (gex,y ? 1.2 mm)
  • Emittance preservation (lt20 slice, lt100
    projected)
  • Final energy spread (lt0.02 slice, lt0.1
    projected)
  • Minimal sensitivity to system jitter
  • Diagnostics integrated into design
  • Flexible operations (1.5 to 15 Å, low-charge,
    chirp, etc.)
  • Compatibility with other SLAC programs

use 2 compressors, 3 linacs
  • Linac Physics Requirement Document PRD 1.3-001

5
LCLS/SLAC Program Compatibility
  • Program Changeover Time
  • 15 minutes from LCLS to damped SLAC beam
  • 24 hours from LCLS to undamped ESA beam
  • Moving Chicanes
  • Articulates collinear with linac axis for
    straight-ahead
  • X-Band Structure Aperture
  • 7mm, smaller than linac scrapers (16.5mm)
  • Smaller than undamped beam
  • Moves off-axis, temporary pipe installed
  • BPM Module Design
  • Charge Range. LCLS 0.2nC to 1nC. Full ESA beam
  • Two Beam e- e Running

6
L1 BC1 Subsystem
Linac 1 (L1)
Bunch Compressor 1 (BC1)
Treaty Point LCLS Injector/LCLS Linac
Two short accelerator structures, refurbished
QuadsBPMs,XYCOR
X-Band Structure (NLC)
Quad BPM, YCOR,XCOR, QE, Toroid
Emittance Diagnostics.
Bunch Compressor Diagnostics
LCLS Injector
LCLS Linac
Remove 4 S-Band Structures
Electrons
  • L1 Requirements PRD 1.3-002
  • BC1 Requirements PRD 1.3-003
  • Installation 06 shutdown

7
X-Band System Design
  • X-Band located in L1 just up-stream of BC1 bunch
    compressor
  • Linearizes energy gradient prior to bunch
    compression to minimize CSR instability
  • 1 x XL-4 klystron feeding 1 X-Band accelerating
    structure obtained from NLC
  • Long Lead Procurement Item
  • Installation Summer 06 and 06 shutdown
  • Requirements PRD 1.3-009

8
BC1 System Design Status
  • Articulated bunch compressor layout
  • Dynamic solid modeling
  • Bend Magnets LLP
  • Install FY 06 shutdown
  • BC1 inter-bend diagnostics package
  • BPM, collimator, OTR

9
LCLS Linac L2 Subsystem
  • Linac Sector 21-3b to 24-6d. Largely unmodified
    SLAC Linac.
  • Energy chirps the bunch to allow compression in
    BC2
  • RF stability critical
  • Four wire scanners added for emittance
    measurement
  • Requirements PRD 1.3-004

10
LCLS Linac BC2 Subsystem
  • Linac Sector 24-7a to 24-8d, Remove eight S-Band
    structures
  • compress a single 1-nC, 195-mm long (rms)
    electron bunch, at a repetition rate of 120 Hz,
    at 4.54 GeV to an rms length of 22 mm
  • BC2 Bends, Long Lead Procurement Item
  • Requirements PRD 1.3-005

11
LCLS Linac L3 Subsystem
  • Linac Sector 25 to 30 largely unmodified.
  • Two accelerator structures added, two structures
    moved, two wire scanners moved, transverse cavity
    moved, new OTR screen.
  • Requirements PRD 1.3-006

12
LCLS Linac LTU Subsystem
  • New Beamline extending from FFTB muon plug wall
    in SLAC BSY, across research yard in new housing
    to FEL undulator
  • Transports a 1-nC, 20-mm long (rms) electron
    bunch, at a repetition rate of 120 Hz, at 14 GeV
    to the LCLS FEL undulator
  • Includes energy and emittance diagnostics, energy
    collimation, bunch length diagnostics and
    undulator launch feedback
  • Requirements PRD 1.3-007

13
LCLS Linac LTU Subsystem Schematic
3-D solid automated layout generated from
MAD also done
14
Multiple Undulator Expansion Capability
LTU
  • Multiple beamlines NOT in LCLS baseline scope
  • Baseline design not to exclude possibility of
    expansion

15
LCLS Linac E-Dump Subsystem
  • New Beamline located between exit of Undulator
    and Near Experimental Hall in new underground
    housing.
  • Separates electron beam from X-Ray FEL beam
    directs beam to dump.
  • Includes energy and energy spread measurement
    capability to 10-4
  • Requirements PRD 1.3-008

16
Safety Dump Concept
  • Safety dump permanent magnets deflect e-beam on
    BYD failure
  • Ray traces show no beam transported through wall
    in any failure condition
  • Working with SLAC Radiation Safety for approval
    of design
  • Specification ESD 1.3-117

17
LCLS Linac Challenges
  • RF Stability (RF/Timing Design, R. Akre Linac
    Long-lead Procurement P. McIntosh)
  • Existing system phase and amplitude stable to
    requirements over several seconds
  • Stability achievable over longer time scales
    using bunch length and energy feedback
  • Bunch Length Measurement Feedback (E-Beam
    Diagnostics , P. Krejcik)
  • Bunch length measurement in RD at SPPS
  • Epics/SLAC Controls System Compatibility
    (Controls System breakouts)
  • Require Epics system to access SLC control system
    in order to operate existing equipment required
    for LCLS
  • SLC control system needs to access EPICS system
    to operate LCLS upgraded equipment required in
    high power beam operations
  • Articulated Bunch Compressors (Physics
    Requirements for Linac, P. Emma)
  • Articulation required for R56 tuning for full
    range of beam charge
  • Simplification of LEUTL design to reduce design
    challenge
  • BPM Module Design (Controls System Breakouts)
  • Measurement of full range of beam charge required
  • Two beam e e- beam operations place additional
    challenge on module design

18
LCLS Linac Work Plan by AreaDesign, Long Lead
Procurement, Construction, Installation, FEL
Commissioning
LLP X-Band
LLP BC1 BC2 Bends
  • L1, BC1, L2, BC2 and L3 must be installed during
    SLAC Linac downtimes.

SLAC Linac Downtimes
19
Budgeted Cost of Work Scheduled (BCWS)
FY04 to FY05 increase in funding - X-Band System
LLP FY05 to FY06 increase in funding
Construction
20
LCLS Linac Organizational Chart
  • Resources obtained through both direct hire and
    matrixed from SLAC departments
  • Resources within groups distributed based on
    project demands
  • Communication between systems managed through
    Interface Control Documents

21
Linac System Progress Summary
  • SC Wiggler removed from Linac baseline
  • Conducted Linac Technical Design Review
  • Linac status to Facility Advisory Committee
  • Linac baseline presented to EIR
  • Linac area schematics complete
  • L1, BC1 and X-Band modeling underway
  • Conducted L1 BC1 preliminary design review
  • E-Dump Safety Dump design ready for Radiations
    Safety Committee review
  • Jitter model developed and feedback simulations
    conducted, presented at XFEL conference J. Wu

22
Work Plan Next 6 Months
  • Matrix in Klystron Dept. engineering and design
    support for X-Band LLRF design
  • Begin procurement of X-Band system
  • Begin procurement of BC1 BC2 dipoles
  • Complete L1 BC1 design details
  • Complete BC1 diagnostics design details
  • Begin L2 L3 system design
  • Obtain Radiation Physics approval of safety dump
    design
  • Continue jitter and feedback modeling
  • Develop commissioning plans

23
LCLS Linac System Conclusions
  • L1 and BC1 design progress on schedule
  • Linac system baseline established
  • X-Band system BC Magnets ready for FY05 LLP
    funding
  • RF stability achievable with feedback
  • Bunch length measurement RD in progress

24
End
25
BC 1 X-Band Compressor
Write a Comment
User Comments (0)
About PowerShow.com