Title: LCLS Linac Overview E' Bong Lehman Review August 10, 2004
1LCLS Linac OverviewE. Bong Lehman Review
August 10, 2004
LCLS
2LCLS Linac Overview
- Technical Scope and Status
- Linac Functional Areas
- Long Lead Procurement Items
- Schedule and Organization
- Linac Challenges
3Nominal LCLS Linac Parameters for 1.5-Å FEL
Single bunch, 1-nC charge, 1.2-mm slice
emittance, 120-Hz repetition rate
250 MeV ?z ? 0.19 mm ?? ? 1.6
14.1 GeV ?z ? 0.022 mm ?? ? 0.01
135 MeV ?z ? 0.83 mm ?? ? 0.10
Linac-X L 0.6 m ?rf -160?
4.54 GeV ?z ? 0.022 mm ?? ? 0.71
E-Dump
LCLS INJ
Linac-1 L ?9 m ?rf ? -25
Linac-2 L ?330 m ?rf ? -41
Linac-3 L ?550 m ?rf ? -10
undulator L 130 m
21-1b 21-1d
X
21-3b 24-6d
25-1a 30-8c
SLAC linac
BC-1 L ?6 m R56? -39 mm
BC-2 L ?22 m R56? -25 mm
DL-1 L ?12 m R56 ?0
LTU L 275 m R56 ? 0
research yard
SLAC linac tunnel
(RF phase frf 0 is at accelerating crest)
4Baseline System Design
- 1.5-Å SASE FEL Linac
- Requirements
- Acceleration to 14.3 GeV (4.5 GeV min.)
- Bunch compression to 3.4 kA (gex,y ? 1.2 mm)
- Emittance preservation (lt20 slice, lt100
projected) - Final energy spread (lt0.02 slice, lt0.1
projected) - Minimal sensitivity to system jitter
- Diagnostics integrated into design
- Flexible operations (1.5 to 15 Å, low-charge,
chirp, etc.) - Compatibility with other SLAC programs
use 2 compressors, 3 linacs
- Linac Physics Requirement Document PRD 1.3-001
5LCLS/SLAC Program Compatibility
- Program Changeover Time
- 15 minutes from LCLS to damped SLAC beam
- 24 hours from LCLS to undamped ESA beam
- Moving Chicanes
- Articulates collinear with linac axis for
straight-ahead - X-Band Structure Aperture
- 7mm, smaller than linac scrapers (16.5mm)
- Smaller than undamped beam
- Moves off-axis, temporary pipe installed
- BPM Module Design
- Charge Range. LCLS 0.2nC to 1nC. Full ESA beam
- Two Beam e- e Running
6L1 BC1 Subsystem
Linac 1 (L1)
Bunch Compressor 1 (BC1)
Treaty Point LCLS Injector/LCLS Linac
Two short accelerator structures, refurbished
QuadsBPMs,XYCOR
X-Band Structure (NLC)
Quad BPM, YCOR,XCOR, QE, Toroid
Emittance Diagnostics.
Bunch Compressor Diagnostics
LCLS Injector
LCLS Linac
Remove 4 S-Band Structures
Electrons
- L1 Requirements PRD 1.3-002
- BC1 Requirements PRD 1.3-003
- Installation 06 shutdown
7X-Band System Design
- X-Band located in L1 just up-stream of BC1 bunch
compressor - Linearizes energy gradient prior to bunch
compression to minimize CSR instability - 1 x XL-4 klystron feeding 1 X-Band accelerating
structure obtained from NLC - Long Lead Procurement Item
- Installation Summer 06 and 06 shutdown
- Requirements PRD 1.3-009
8BC1 System Design Status
- Articulated bunch compressor layout
- Dynamic solid modeling
- Bend Magnets LLP
- Install FY 06 shutdown
- BC1 inter-bend diagnostics package
- BPM, collimator, OTR
9LCLS Linac L2 Subsystem
- Linac Sector 21-3b to 24-6d. Largely unmodified
SLAC Linac. - Energy chirps the bunch to allow compression in
BC2 - RF stability critical
- Four wire scanners added for emittance
measurement - Requirements PRD 1.3-004
10LCLS Linac BC2 Subsystem
- Linac Sector 24-7a to 24-8d, Remove eight S-Band
structures - compress a single 1-nC, 195-mm long (rms)
electron bunch, at a repetition rate of 120 Hz,
at 4.54 GeV to an rms length of 22 mm - BC2 Bends, Long Lead Procurement Item
- Requirements PRD 1.3-005
11LCLS Linac L3 Subsystem
- Linac Sector 25 to 30 largely unmodified.
- Two accelerator structures added, two structures
moved, two wire scanners moved, transverse cavity
moved, new OTR screen. - Requirements PRD 1.3-006
12LCLS Linac LTU Subsystem
- New Beamline extending from FFTB muon plug wall
in SLAC BSY, across research yard in new housing
to FEL undulator - Transports a 1-nC, 20-mm long (rms) electron
bunch, at a repetition rate of 120 Hz, at 14 GeV
to the LCLS FEL undulator - Includes energy and emittance diagnostics, energy
collimation, bunch length diagnostics and
undulator launch feedback - Requirements PRD 1.3-007
13LCLS Linac LTU Subsystem Schematic
3-D solid automated layout generated from
MAD also done
14Multiple Undulator Expansion Capability
LTU
- Multiple beamlines NOT in LCLS baseline scope
- Baseline design not to exclude possibility of
expansion
15LCLS Linac E-Dump Subsystem
- New Beamline located between exit of Undulator
and Near Experimental Hall in new underground
housing. - Separates electron beam from X-Ray FEL beam
directs beam to dump. - Includes energy and energy spread measurement
capability to 10-4 - Requirements PRD 1.3-008
16Safety Dump Concept
- Safety dump permanent magnets deflect e-beam on
BYD failure - Ray traces show no beam transported through wall
in any failure condition - Working with SLAC Radiation Safety for approval
of design - Specification ESD 1.3-117
17LCLS Linac Challenges
- RF Stability (RF/Timing Design, R. Akre Linac
Long-lead Procurement P. McIntosh) - Existing system phase and amplitude stable to
requirements over several seconds - Stability achievable over longer time scales
using bunch length and energy feedback - Bunch Length Measurement Feedback (E-Beam
Diagnostics , P. Krejcik) - Bunch length measurement in RD at SPPS
- Epics/SLAC Controls System Compatibility
(Controls System breakouts) - Require Epics system to access SLC control system
in order to operate existing equipment required
for LCLS - SLC control system needs to access EPICS system
to operate LCLS upgraded equipment required in
high power beam operations - Articulated Bunch Compressors (Physics
Requirements for Linac, P. Emma) - Articulation required for R56 tuning for full
range of beam charge - Simplification of LEUTL design to reduce design
challenge - BPM Module Design (Controls System Breakouts)
- Measurement of full range of beam charge required
- Two beam e e- beam operations place additional
challenge on module design
18LCLS Linac Work Plan by AreaDesign, Long Lead
Procurement, Construction, Installation, FEL
Commissioning
LLP X-Band
LLP BC1 BC2 Bends
- L1, BC1, L2, BC2 and L3 must be installed during
SLAC Linac downtimes.
SLAC Linac Downtimes
19Budgeted Cost of Work Scheduled (BCWS)
FY04 to FY05 increase in funding - X-Band System
LLP FY05 to FY06 increase in funding
Construction
20LCLS Linac Organizational Chart
- Resources obtained through both direct hire and
matrixed from SLAC departments - Resources within groups distributed based on
project demands - Communication between systems managed through
Interface Control Documents
21Linac System Progress Summary
- SC Wiggler removed from Linac baseline
- Conducted Linac Technical Design Review
- Linac status to Facility Advisory Committee
- Linac baseline presented to EIR
- Linac area schematics complete
- L1, BC1 and X-Band modeling underway
- Conducted L1 BC1 preliminary design review
- E-Dump Safety Dump design ready for Radiations
Safety Committee review - Jitter model developed and feedback simulations
conducted, presented at XFEL conference J. Wu
22Work Plan Next 6 Months
- Matrix in Klystron Dept. engineering and design
support for X-Band LLRF design - Begin procurement of X-Band system
- Begin procurement of BC1 BC2 dipoles
- Complete L1 BC1 design details
- Complete BC1 diagnostics design details
- Begin L2 L3 system design
- Obtain Radiation Physics approval of safety dump
design - Continue jitter and feedback modeling
- Develop commissioning plans
23LCLS Linac System Conclusions
- L1 and BC1 design progress on schedule
- Linac system baseline established
- X-Band system BC Magnets ready for FY05 LLP
funding - RF stability achievable with feedback
- Bunch length measurement RD in progress
24End
25BC 1 X-Band Compressor