2APEX stats Run-8 (so far)
Stats Run-7 APEX availability 72 Time at store
for physics 49 Stats Run-8 (so far) APEX
availability 77.5 Physics, last FIVE weeks is
101.55hr 60.4 Physics, last SIX weeks is 98.3
hr 58.5Physics, last SEVEN weeks (all of Run8)
94.8 hr 56.4 So far we meet our goals for
Run-7 (mid 50) for the entire run, and for the
last 5 weeks we meet our ERTAF goals (better
reliability of the PS system)
3Uptime PS system
Compare first 9 weeks of operations Run-7 vs.
Run-8
4APEX d-Au Run-8 - status
- Completed
- 08-36 0A IBS with decoupling ? transverse
stochastic cooling - 08-17 0A Test of ramp and operations with
betalt0.8m (with d-Au) 26h total - Beta measurements 2 techniques test of IP
knobs - ? 30 luminosity
- 06-31 0A ORM Measurements ? beta beat correction
- 08-01 1A Electron cloud location ? performance
limits - 08-18 1A Stability threshold at transition ?
performance limits - 08-07 1B Energy Loss of Debunched Beam
- Running
- 07-33 A0 Tune and chromatic drift correction at
injection ? operations - 08-14 A0 Collimation on the ramp ? performance
limits - 08-02 1B Au31 in AGS
5APEX Run-8 d-Au To Do
- 08-03 A0 Transition crossing longitudinal
matching as a function of RF - 08-06 A0 Measuring and modeling linear and
nonlinear chromaticities - 07-19 A0 Common Mode Noise Measurement
- 08-12 A0 Development of IBS-suppression lattice
(100 or 110 deg) - 08-25 A0 Transition instability as function of
chromaticity jump - 08-27 A0 Measure and localize gradient errors
- 08-34 A0 Beta-Dispersion Beating Correction
- 08-29 A0 Beam profile measurement with CNI
polarimeter - 08-16 A0 Using phasing of two RF cavities at
transition - 08-28 B0 Hybrid Tune Tracker
- 08-31 A1 Transition Instability Modes
- 08-24 B2 Study of possible Cooling of Au_77 in
AGS (in parallel) - 08-37 A0 Anomalous BTF at injection
- 08-38 A0 Yellow radial feedback measurements
6APEX D-Au summary
- We devoted considerable time (30) on issues that
are in the gray area between APEX and
developments (beta squeeze, knobs, etc). This is
a flexible model that works well, however - To complete even the A0 studies approved we would
need 4 sessions of APEX until the end of d-Au, 5
sessions with contingency (assuming present APEX
uptime) - We really need the 3 planned sessions (January
16,23,27) at the end of d-Au
7APEX Schedule January 15-16 2008
Injection
Ramps
Store 6-12 bunches
Store BBQ
Injection BBQ
Ramps
08-29 Profile with polarimeter Huang, Sivertz,
team
08-25 Chrom Jump _at_inj Montag
08-03 Longitudinal matching _at_transition Abreu Bai
Blaskiewicz
06-31 8-27 ORM Corrections. Optics Satogata Bai
08-17 IP Knobs Ptitsyn Malitsky
08-14 Collimation on the ramp Drees
08-28 Hybrid Tune Tracker Cameron team
08-24 Au77 Trbojevic team
6am
2am
8am
12am
8pm
10pm
4am
700 am Injectors OFF
8APEX in the PP run
- The plans for PP advocates a (relatively)
conservative beta of 90 cm for operation with
development for lower beta (lt70cm) in APEX - At the same time we need to make sure that high
priority studies with polarized beams and
beam-beam studies get done as well - At the moment we have 3 APEX sessions planned
with one possible more at the end of the PP run.
If we do beta in APEX we will need the extra
time to do the rest of the program.
9Approved studies with PP
- Polarized Protons
- 07-03 0A Measure driven coherent spin precession
- 08-09 0A Polarization profile using the RHIC
Carbon Polarimeter - 08-10 0A Rate dependence of the RHIC Carbon
Polarimeter - 08-23 0A RHIC Polarization variation with time
- 08-19 0B Spin tune and decoherence measurements
- 08-05 1A Spin Echo and Resonance Interference
- Protons
- 08-17 0A Test of ramp and operations with
betalt0.7m - 08-08 1A Long-range beam-beam interactions
- 08-11 1A Lifetimes of non-colliding proton
bunches - 08-35 1A 3Qy resonance measurement and correction
- 08-33 0B Chromaticity Feedback
- studies from d-Au that could be done with
protons too