Wind Turbine Installation

1 / 19
About This Presentation
Title:

Wind Turbine Installation

Description:

During Summer 2005, started to review additional environmental options ... Inverters 2 X 2500W. Turbine Input. 2 X 16 Amp Trips. Total Turbine output meter (ROC Meter) ... – PowerPoint PPT presentation

Number of Views:167
Avg rating:3.0/5.0

less

Transcript and Presenter's Notes

Title: Wind Turbine Installation


1
Wind Turbine Installation
  • Little Henham

2
Why and Wind Turbine ? During Summer 2005,
started to review additional environmental
options Always been looking at new ways to
manage the environment Open to Prevailing wind
- South Westerly Located at 103 meters above sea
level
3
Initial Concerns- Rural Location Noise Stanste
d Airport Planning permission
What did we do ? Research Internet Magazines
Papers Government info
Result of Research- Why did we want a wind
turbine ?
4
SAVE THE ENVIRONMENT MAKE LOTS OF MONEY FREE
ELECTRICITY WAY OF LIFE / GREEN IMAGE GUARANTEED
POWER SUPPLY
Use an untapped resources to supply power without
increasing environmental impact. Giving long term
environmental and cost benefit
There is NO single technology What is best for
your location and situation ?
Would we have undertaken the project if no grant
was available.
YES
5
  • Criteria for the turbine
  • Wind turbine to supply power
  • Must be large enough to supply meaningful power
  • Export excess back to grid
  • Must be able to supply power if mains failure.
  • No batteries / storage
  • Situated close to own buildings
  • Limited or no change in the current supply
    equipment

Discounted all turbines below 3 kW
output Selected 5 - 10 kW as the best option for
our site
6
  • Selection of companies
  • All achieved from the internet searches.
  • No contact with any previous installations.
  • Visited presentation evenings on renewables.
  • Wanted a company that would
  • Be prepared to work together to develop the
    project
  • Provide details for the planning application
  • Give guidance for the electrical installation
  • Supply guidance on the import / export
    requirements
  • Could supply good after sales service
  • Two companies selected to obtain information
  • Proven
  • Segen

7
  • Electricity Buy Back
  • Most supply companies advertise green energy.
  • All want to sell you electricity.
  • Tell them you want a buy back agreement and
  • Who is the District Network Operator ?
  • No commitment to buy back from anyone but EDF
  • Our local DNO
  • What is required
  • A buy back agreement.
  • An Independent Export Meter.
  • Correct Supply from turbine.

8
  • Wind Speed Data
  • Information from the DTI website
  • Enter Map reference
  • Wind effected by
  • Trees / Buildings / Turbulent air

9
(No Transcript)
10
11th April 2006 Sworders Agricultural Submitted
Planning Application 15th May 2006 Letter from
Stansted airport indicating they wish to
investigate the effect on navigational aids 7th
June 2006 UDC Application Approved. Subject to
approvals on Colour and materials.
11
11th July 2006 NATS objection to the development
pending fuller investigation. Required to delay
any installation until report from NATS. 31st
August 2006 Letter form NATS indicating that the
development is likely to impact the electronic
infrastructure but it has no safeguarding
objection to the proposal.
14th September 2006 DTI Energy Saving Trust
Low Carbon Buildings program Grant
Approved. Very easy online application
process Grant offer is time restricted, could
loose entitlement if outside dates. Must get
information correct and turbine certificates when
claiming 21st September 2006 Approval for
materials and colour from UDC
12
9th November 2006 Foundation concrete poured.
Groundwork's Foundation kit supplied 4 X
foundation holes Setup foundation anchors 1 X
Cable trench Install Cable Pour concrete and
backfill
13
20th December 2006 Turbine delivered, and
erected.
Turbine delivered in kit form. MUST BE
INSTALLED BY ACCREDITED INSTALLERS FOR GRANT
APPROVAL Assembled on site 1 day (minimum) for
external work
14
(No Transcript)
15
(No Transcript)
16
21st December 2006 Electrical installation.
17
Costings
18
(No Transcript)
19
http//www.bwea.com/about/index.html http//www.se
gen.co.uk http//www.ofgem.gov.uk/Pages/OfgemHome.
aspx http//www.sworders.ag/ http//www.edfenergy.
com http//www.dti.gov.uk http//www.lowcarbonbuil
dings.org.uk/home/ http//www.nfpa.co.uk
Write a Comment
User Comments (0)