Texas NodalEDS Market Trials ApproachWednesday,
November 29, 2006
2
Agenda
  • Market Trials Objectives
  • High Level Schedule
  • EDS Phases
  • EDS Timeline / Detailed Drill Down
  • EDS Detailed Planning
  • Define Business Process to Requirements
    Traceability Matrix
  • Detail Market Trial Phases and Test Areas
  • Create Entrance / Exit Criteria Checklists
  • Define Test Cycles, MP Segmentation, and Test
    Calendars
  • Outline Market Trials reporting requirements
  • Next Steps
  • Detail out specific sections and review with TPTF
  • 2 Drafts and Final
  • Tentative Schedule

3
Objective of market trials
  • The objective of market trials is to confirm
    through a series of structure and unstructured
    tests that
  • stable and accurate operations of the SCADA,
    Network Security Analysis, Transmission
    Constraint Management, SCED, LFC, DAM, RUC, and
    real time settlement system can be declared
  • as outlined in the Nodal Transition Plan.

4
Approach aligns with the Nodal Timeline
5
Market Trials Phases
  • EDS 1 Data and Telemetry
  • EDS 2 State Estimator, Network Security
    Analysis
  • EDS 3 Real Time Market Operations
  • EDS 4 Day Ahead Market Operations

6
Market trials timeline
7
Market Trials Timeline and the detailed Market
Trials Plan
8
EDS Detailed Planning Overview
  • Define Business Process to Requirements
    Traceability Matrix
  • Detail Market Trial Phases and Test Areas
  • Create Entrance / Exit Criteria Checklists
  • Define test cycles, MP segmentation, and test
    calendar
  • Additional Areas

9
EDS Detailed Planning
Define business process to requirements
traceability matrix
Example
10
EDS Detailed Planning
  • Detail Market Trial Phases and Test Areas
  • Define the set of functionality for each EDS
    phase based on the detailed requirements
    documentation.
  • Identify EDS phase for all functionality based on
    comprehensive release plan and project schedule.
  • Tie overall business process area to
    functionality for EDS phase.
  • Define testing scenarios and test plan outlines

11
EDS Detailed Planning
  • Create Entrance / Exit Criteria Checklists

12
EDS Detailed Planning
  • Define test cycles, MP segmentation, and test
    calendar
  • Testing cycles will be used to optimize the
    trials schedule and reduce resource conflicts by
    focusing on specific market areas with a reduced
    number of participants.
  • Participants will be logically segmented into
    appropriate cycles.
  • A weekly test calendar will be used to focus
    weekly activities. Multiple cycles may be
    scheduled in a single week or over multiple
    weeks.

13
EDS Detailed Planning
  • Additional Areas
  • Outline Market Trials reporting requirements
  • Define Market Trials data requirements
  • Finalize Market Trial Phase critical inputs
  • Interface documentation
  • Requirements signoff
  • Design signoff
  • Market Operations Sandbox timelines

14
Next Steps
  • Obtain approval for Market Trials Approach -
    today
  • Begin EDS Detailed Planning providing
    opportunities for comments as follows
  • EDS 1 to 4 Detailed Plan Drafts for comment TBD
  • EDS 1 Detailed Plan Final Signoff TBD
  • EDS 2 Detailed Plan Final Signoff TBD
  • EDS 3 Detailed Plan Final Signoff 3/30/2007
  • EDS 3 Market Trials Handbook Final
    Signoff 6/29/2007
  • EDS 4 Detailed Plan Final Signoff 9/28/2007
  • EDS 4 Market Trials Handbook Final
    Signoff 12/31/2007