Workshop F Managing the contract - PowerPoint PPT Presentation

1 / 14
About This Presentation
Title:

Workshop F Managing the contract

Description:

Case Study One. The Provider is late in the delivery of a key monthly ... The Clinical Quality Review meeting should supply minutes to the Monthly Service ... – PowerPoint PPT presentation

Number of Views:39
Avg rating:3.0/5.0
Slides: 15
Provided by: amne
Category:

less

Transcript and Presenter's Notes

Title: Workshop F Managing the contract


1
Workshop FManaging the contract
2
New NHS Contract For 2008 and beyond
  • Workshop F
  • Managing the Contract

3
Key Parts of Contract
  • Clause 8 Review
  • Clause 29 Information Requirements (Schedule 5)
  • Clause 32 Performance
  • Clause 33 Clinical Quality Review
  • Schedule 3, Part 1, paragraph 9 C.difficile
  • Schedule 3, Part 4 Quality Standards
  • Part 4A Clinical Quality Performance Indicators
  • Part 4B Performance Indicators
  • Guidance particularly figures 1,2 3

4
Partnership Co-operation
  • The most successful contracts are managed through
    partnership co-operation win-win works.
  • The contract management tools built into this
    contract are designed to encourage partnership
  • The tools, in general, do not result directly in
    penalty but focus on remedy
  • Knowledge and understanding of the contract is
    vital for both parties
  • Effective contract management will rely on
  • Relationships
  • Information
  • Communication internally and between parties
  • Holistic solutions
  • Report Review - React

5
Case Study One
  • The Provider is late in the delivery of a key
    monthly performance report
  • The Provider has not told the Co-ordinating
    Commissioner that the report will be late
  • The information is needed for the monthly review
  • There is evidence that key Performance Indicators
    will be breached
  • What do you do the manage the situation ?

6

Case Study One - pointers
  • Prior to resorting to the contract
  • Provider and Co-ordinating Commissioner should
    co-operate so the Provider is remiss in not
    telling the Co-ordinating Commissioner
  • If the Provider is able to issue a partial report
    that would help
  • Using the contract
  • This should only happen once the day-to-day
    working arrangements have failed to resolve the
    issue
  • Clause 29 (Information) can be enacted
    flowchart, fig 1
  • If a Commissioner is causing the delay the
    Provider is off the hook
  • During negotiations
  • It is key to have agreed the format, content and
    timeliness of all important information.
  • Parties should be realistic in their expectations
  • If a party cannot comply today with a reasonable
    request then a plan should be agreed to get the
    party to an acceptable position

7
Case Study Two
  • The New to Follow-up ratio in ENT is 17 compared
    with the planned level of 13
  • The Provider agreed the ratio reeluctantly during
    the negotiations
  • Achievement of the ratio relies on GPs
    undertaking some of the follow ups
  • The Commissioners have plans which they are
    relying on in order that the ratio can be
    achieved
  • The issue comes to light in the Monthly Service
    and Performance Review Meeting.
  • How should this be managed?

8
Case Study Two - pointers
  • Prior to resorting to the contract
  • Parties should check that they are delivering
    their commitments
  • If the parties are complying with their
    commitments but the Provider is unable to reach
    the ratio for good clinical reasons then the
    ratio may be wrong and should be reviewed.
  • A solution can be agreed without relying on the
    contract to manage it but to enable the next
    stages of the contract to kick in in the event of
    non-compliance it is sensible to use the
    Performance Notice.
  • Resorting to the contract
  • This should only happen once the day-to-day
    working arrangements have failed to resolve the
    issue subject to the above
  • Clause 32 (General Performance Controls) can be
    enacted flowchart, fig 2
  • If the other party is causing the breach then an
    Excusing Notice can be issued to mitigate against
    risk of consequence
  • During negotiations
  • The Providers reluctance to accept the ratio
    should have triggered a phased approach and a
    plan encompassing the relevant parts of the
    health economy (Provider, Commissioner, Referrer
    etc).
  • The ratio should be set as a Performance
    Indicator in Schedule 3, Part 4B

9
Linking contract management processes
  • Different parts of the organisation will have
    different pressures and different demands on the
    contract
  • It is unreasonable to expect one meeting to be
    able to embrace all issues
  • Meetings should provide short notes to one
    another highlighting key actions and events for
    example
  • The Clinical Quality Review meeting should supply
    minutes to the Monthly Service and Performance
    Review meeting and vice versa.
  • Any sub-group that is working on improvements
    (e.g. information upload to SUS) should send a
    report to the Monthly Service and Performance
    Review meeting.
  • In some instances it may be sensible to have a
    member of one meeting present at the other.
  • For example a member of the Clinical Quality
    Review meeting may also be a standing member of
    the Monthly Service and Performance Review
    meeting
  • Inviting relevant people to attend on an as
    required basis may be useful.

10
Case Study Three
  • The Provider has exceeded the agreed level of
    activity and the annual review is going to take
    place to determine whether the Provider should be
    paid or not for the activity.
  • During the year the provider has requested
    Activity Management Plans to try to return
    activity to plan
  • Not all Activity Management Plans have been
    complied with
  • Not all Activity has been subject to an Activity
    Management Plan
  • Some Activity came about through breached Prior
    Approval schemes
  • The Commissioners have not complied with all
    their obligations
  • What should happen?

11
Case Study Three - pointers
  • Prior to resorting to the contract
  • In this instance the contract rules should apply
    but the final part of the process (not paying) is
    discretionary so the parties can agree other
    actions if they want
  • Resorting to the contract
  • Schedule 3, Part 1, Paragraph 6 can be enacted
    flowchart, fig 5
  • The Provider may not be paid (at CCs discretion)
    where
  • Prior Approval schemes have been breached
  • The excess Activity was not subject to an
    Activity Management Plan
  • The Provider has breached an Activity Management
    Plan
  • The Provider must be paid where
  • The excess activity was caused by a Commissioner
    not complying with its obligations
  • During negotiations
  • Both parties should make sure that they are
    confident that, together, they can deliver all of
    their obligations be it activity, ratios,
    performance indicators, UM schemes.
  • If they cant deliver on day one then agree a
    plan to achieve it think win win

12
Case Study Four
  • The Provider is not going to achieve the 18 Week
    Referral-to-Treatment Target
  • The Provider has not delivered all the Activity
    required (it has underperformed against the
    Activity Plan)
  • The Commissioner has not managed all of its
    obligations and delayed discharge has resulted in
    some of the Providers under-performance
  • The Provider has a capacity constraint but
    accepts that it has not done everything it can.
  • What should happen?

13
Case Study Four - pointers
  • Schedule 3, Part 1, Paragraph 7 (flowchart, fig
    6) potentially mitigating the Provider from risk
    of fine CANNOT be enacted because the Provider
    has not exhausted its capacity to flex
  • However the failure of the Co-ordinating
    Commissioner to perform in terms of delayed
    discharge does mitigate the Provider from some of
    the risk.
  • The parties should plan together to achieve the
    target (which affects them both)
  • In this instance the Provider has admitted it is
    failing and it is not all due to delayed
    discharge. The effect of delayed discharge
    should be analysed.
  • If correcting it would prevent the 18w RTT breach
    then no action should be taken until the delayed
    discharge issue is rectified
  • If correcting it would still leave the Provider
    in breach (albeit a lesser breach) the breach
    should be calculated and the Provider is at risk
    for the lesser amount.
  • The Co-ordinating Commissioner should consider
    whether implementing the fine will benefit the
    health economy. In this instance the Provider
    seems honest and open if a decent plan to
    achieve 18 week RTT compliance is agreed the fine
    could be waived or stayed against compliance with
    the plan.
  • During Negotiations
  • Agree appropriate Capacity Review Criteria

14
  • Any group case studies to be considered ?
Write a Comment
User Comments (0)
About PowerShow.com