Title: NAPAs
1NAPAs and National Communications Cairo,
Egypt 20 - 22 September 2007 Mr. Bubu Pateh
Jallow CHAIR OF THE LEG
2OUTLINE OF PRESENTATION
- Context of NAPA Process under the Convention
- Status of Preparation
- Status of Implementation
- Barriers and Constraints
- Lessons learned
- Conclusions and Recommendation
3CONTEXT OF THE NAPA PROCESS
- By its Decision 5 CP.7, Section II, the COP
decided - to establish a work programme for the
implementation of Article 4.9 of the Convention,
which would include activities, among many others
Supporting the preparation of national
adaptation programmes of action (NAPAs) Para
11(c) - and in Para 15 the Decision relates the NAPAs to
NATCOMs as the information contained in NAPAs
may constitute the first step in the preparation
of initial national communications
4CONTEXT OF THE NAPA PROCESS
- By Decision 7CP.7, COP decided to establish the
LDC Fund to support the work programme for the
least developed countries - By Decision 27CP.7, COP adopted the initial
guidance to GEF for the operation of the LDC Fund
to support the work programme for the least
developed countries and requested GEF to provide
funding from the LDC Fund to meet the agreed full
cost of preparing the NAPAs, given that the
preparation of NAPAs will help to build capacity
for the preparation of national communications. - By Decision 28CP.7, paragraph 1 COP adopted the
guidelines for the preparation of NAPAs - By Decision 29 CP.7, paragraph 1. COP established
the least developed countries expert group (LEG)
with its terms of reference
5STATUS OF NAPA PREPARATION
- As of 31 July 2007, the following 21 LDCs have
completed and officially submitted their NAPAs
Bangladesh, Bhutan, Burundi, Cambodia, Comoros,
Democratic Republic of Congo, Djibouti, Eritrea,
Haiti, Kiribati, Lesotho, Madagascar, Malawi,
Mauritania, Niger, Rwanda, Samoa, Sénégal, São
Tomé e Príncipe, Sudan and Tuvalu. - The officially submitted NAPAs can be accessed on
the UNFCCC website http//unfccc.int/2679.php
6STATUS OF NAPA IMPLEMENTATION
- Out of the 21 submitted NAPAs, six NAPA
implementation projects have been officially
submitted by 21 May 2007 to the GEF for funding
under the LDCF, including from Bangladesh,
Bhutan, Malawi, Mauritania, Niger and Samoa - These projects have been PIF-approved, which
means that the early- stage submissions have been
identified as consistent with the LDCF
eligibility criteria and that they have been
entered into the LDCF pipeline - Since May an additional three NAPA implementation
projects from Cambodia, Eritrea and Sudan have
been officially submitted by UNDP to be included
in the November 2007 LDCF Work Programme
7Barriers and Constraints
- Change of Accounting System at the UNDP Country
Offices coinciding with the start of NAPA process - Opening of Special Government Accounts for the
depositing and managing NAPA Funds - Inadequate critical mass outside of Government
and private Consultants not available when needed - NAPA endorsement process considered a bit longer
than expected in some countries - Inadequate national capacity to translate NAPA
Project Profiles to full fundable Projects - More data and information needed for the
preparation of Project Identification Forms
(PIFs) which is found inadequately presented in
the current completed NAPAs
8LESSONS LEARNED UNDER THE NAPA PROCESS
- The total cost for priority adaptation projects
identified in the submitted NAPAs so far amounts
to USD 341,289 million - Current deposit in the LDC Fund is about US
150,000 leaving a funding gap of US 191,289
million. -
- Financial contributions from Annex II Parties
were vital for the success register under the
NAPA Process and the Parties and the LEG are
highly appreciative of this support and
recognizes that any future mandate of the LEG
should have the endorsement of and continued
support from Parties to carry out the activities
entrusted to the group.
9LESSONS LEARNED UNDER THE NAPA PROCESS
- Through the establishment of NAPA Teams and
Working Groups, the NAPA process has improved
coordination and dialogue at the national and
regional levels. The Ministries of Environment,
Finance, Planning and Development, and Civil
Society have been driving the process. - The National Communication process should benefit
from this broadened and bottom-up institutional
framework. - The NAPA Stakeholder Consultation process
particularly at the grassroots levels has
generated a lot more data and information for
climate change studies. The data and information
includes traditional knowledge and coping
strategies. - This additional level of information will
particularly be useful for the process of
preparation of Second National Communications by
Parties.
10LESSONS LEARNED UNDER THE NAPA PROCESS
- Mainstreaming is a process and has been initiated
under the NAPA Process through the establishment
of appropriate institutional framework. - All NAPA Teams are multi-sectoral and
multi-disciplinary with membership drawn from
research institutions, agriculture, environment,
forestry, fisheries, academia, media and civil
society and private sector (Comoros) with some
international consultants (Gambia and Uganda). - NAPA Teams are guided by a Project Steering
Committee, which is more policy oriented and
oversees the progress of the NAPA development
process - The NAPA Project Steering Committee of The Gambia
is chaired by a Permanent Secretary and includes
National Focal Points of the Desertification and
Biodiversity Conventions and the GEF Focal Point,
National Assembly and Civil Society. - Comoros established a NAPA Island Committees to
coordinate the NAPA process at the island level.
11LESSONS LEARNED UNDER THE NAPA PROCESS
- Mainstreaming through the PRSP, other National
Plans and Programmes and the MDGs - In the selection of the priority NAPA projects in
Bhutan, one of the criteria was to assess whether
the projects complement national goals such as
overcoming poverty, enhancing the adaptive
capacity or other multilateral environmental
agreements. - In Bangladesh the "Policy Matrix 18, integration
of climate change adaptation in all policies,
programmes and projects is one of the key targets
and recognises that NAPA is closely related to
the other environmental policies or programmes in
particular the National Action Plan on
biodiversity and the National Environmental
Management Action Plan (NEMAD).
12LESSONS LEARNED UNDER THE NAPA PROCESS
- Reduction of the vulnerabilities of the rural
communities to the adverse impacts of extreme
weather events, enabling the rural communities to
adapt to climate change, attainance of food
security, resettlement of population, provision
of fresh water, rational use of coastal
structures, effective land-uses, utilisation of
marine resources, reduction of poverty and
environmental degradation and achievement of
sustainable rural livelihood are all elements of
poverty reduction strategy that are common to the
NAPA and the PRSP in Malawi and Samoa. - Key activities laid out in Mozambiques PRSP
include measures to manage its vulnerability to
and strengthening its capacity to respond to
natural disasters. This resulted to disaster risk
management and reduction being the highest
priority in the Mozambique NAPA.
13LESSONS LEARNED UNDER THE NAPA PROCESS
- The NAPA process is entering a transition from
NAPA preparation to NAPA implementation. Six
countries have already received approval for
funding implementation from the LDC Fund under
the GEF. - The implementation of these projects and others
to come will provided practical knowledge and
experience on climate change adaptation in
addition to whatever study outcomes will be
coming out of the technical institutions and
Universities. This Learning by doing is a
concrete and fast way of gaining knowledge and
the NAPA Implementation process will provide this
to the global climate change process and in
particular the experiences and knowledge gained
will be good input to the National Communications
process.
14SUMMARY AND CONCLUSIONS
- The National Communications Process should adopt
and maintain the institutional framework sutup
under the NAPA process - NAPA process is at a juncture implementation
phase is starting for about half of the LDCs that
have completed their NAPAs, while the other half
of LDC Parties are still at various stages of
preparation - some of whom (East Timor,
Afghanistan, Equatorial Guinea) are at incipient
stages - There is continuing need for the LEG to provide
technical guidance and advice on the preparation
of NAPAs, to advise on capacity-building, to
facilitate the exchange of information, and to
advise on efforts to mainstream adaptation into
development planning
15SUMMARY AND CONCLUSIONS
- Closer collaboration is needed to support LDC
Parties to prepare NAPA proposals for funding,
and to support NAPA teams that are in various
stages of NAPA preparation - Need to continue monitoring bottlenecks and
constraints in the preparation of NAPAs through
targeted questionnaires -
- Variety of effective partnerships have been built
which involve a number of support organizations
at the international level as well as in-country
institutions at the level of the individual NAPA
16SUMMARY AND CONCLUSIONS
- Contributed to raising awareness of adaptation
among stakeholders, integrating climate change
concerns across agencies represented in NAPA
teams, and raising the importance of adaptation
to the highest decision-making level through the
NAPA endorsement process - NAPA preparation process has itself generated
benefits beyond serving as a vulnerability and
adaptation assessment. The challenge will be to
maintain the momentum and awareness generated
into the implementation phase
17SUMMARY AND CONCLUSIONS
- The COP should extend the mandate of the LEG at
COP 13 for the continuation of the provision of
advisory services to meet the special
circumstances and needs of the LEAST DEVELOPED
COUNTRIES (LDCs) and implementation of the
remaining elements of the LDC Work Programme
adopted by COP 7 in 2001
18