NAPAs - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

NAPAs

Description:

... the LDCF, including from Bangladesh, Bhutan, Malawi, Mauritania, Niger and Samoa ... of the priority NAPA projects in Bhutan, one of the criteria was to assess ... – PowerPoint PPT presentation

Number of Views:63
Avg rating:3.0/5.0
Slides: 19
Provided by: unf9
Category:

less

Transcript and Presenter's Notes

Title: NAPAs


1
NAPAs and National Communications Cairo,
Egypt 20 - 22 September 2007 Mr. Bubu Pateh
Jallow CHAIR OF THE LEG
2
OUTLINE OF PRESENTATION
  • Context of NAPA Process under the Convention
  • Status of Preparation
  • Status of Implementation
  • Barriers and Constraints
  • Lessons learned
  • Conclusions and Recommendation


3
CONTEXT OF THE NAPA PROCESS
  • By its Decision 5 CP.7, Section II, the COP
    decided
  • to establish a work programme for the
    implementation of Article 4.9 of the Convention,
    which would include activities, among many others
    Supporting the preparation of national
    adaptation programmes of action (NAPAs) Para
    11(c)
  • and in Para 15 the Decision relates the NAPAs to
    NATCOMs as the information contained in NAPAs
    may constitute the first step in the preparation
    of initial national communications

4
CONTEXT OF THE NAPA PROCESS
  • By Decision 7CP.7, COP decided to establish the
    LDC Fund to support the work programme for the
    least developed countries
  • By Decision 27CP.7, COP adopted the initial
    guidance to GEF for the operation of the LDC Fund
    to support the work programme for the least
    developed countries and requested GEF to provide
    funding from the LDC Fund to meet the agreed full
    cost of preparing the NAPAs, given that the
    preparation of NAPAs will help to build capacity
    for the preparation of national communications.
  • By Decision 28CP.7, paragraph 1 COP adopted the
    guidelines for the preparation of NAPAs
  • By Decision 29 CP.7, paragraph 1. COP established
    the least developed countries expert group (LEG)
    with its terms of reference

5
STATUS OF NAPA PREPARATION
  • As of 31 July 2007, the following 21 LDCs have
    completed and officially submitted their NAPAs
    Bangladesh, Bhutan, Burundi, Cambodia, Comoros,
    Democratic Republic of Congo, Djibouti, Eritrea,
    Haiti, Kiribati, Lesotho, Madagascar, Malawi,
    Mauritania, Niger, Rwanda, Samoa, Sénégal, São
    Tomé e Príncipe, Sudan and Tuvalu.
  • The officially submitted NAPAs can be accessed on
    the UNFCCC website http//unfccc.int/2679.php

6
STATUS OF NAPA IMPLEMENTATION
  • Out of the 21 submitted NAPAs, six NAPA
    implementation projects have been officially
    submitted by 21 May 2007 to the GEF for funding
    under the LDCF, including from Bangladesh,
    Bhutan, Malawi, Mauritania, Niger and Samoa
  • These projects have been PIF-approved, which
    means that the early- stage submissions have been
    identified as consistent with the LDCF
    eligibility criteria and that they have been
    entered into the LDCF pipeline
  • Since May an additional three NAPA implementation
    projects from Cambodia, Eritrea and Sudan have
    been officially submitted by UNDP to be included
    in the November 2007 LDCF Work Programme

7
Barriers and Constraints
  • Change of Accounting System at the UNDP Country
    Offices coinciding with the start of NAPA process
  • Opening of Special Government Accounts for the
    depositing and managing NAPA Funds
  • Inadequate critical mass outside of Government
    and private Consultants not available when needed
  • NAPA endorsement process considered a bit longer
    than expected in some countries
  • Inadequate national capacity to translate NAPA
    Project Profiles to full fundable Projects
  • More data and information needed for the
    preparation of Project Identification Forms
    (PIFs) which is found inadequately presented in
    the current completed NAPAs

8
LESSONS LEARNED UNDER THE NAPA PROCESS
  • The total cost for priority adaptation projects
    identified in the submitted NAPAs so far amounts
    to USD 341,289 million
  • Current deposit in the LDC Fund is about US
    150,000 leaving a funding gap of US 191,289
    million.
  • Financial contributions from Annex II Parties
    were vital for the success register under the
    NAPA Process and the Parties and the LEG are
    highly appreciative of this support and
    recognizes that any future mandate of the LEG
    should have the endorsement of and continued
    support from Parties to carry out the activities
    entrusted to the group.

9
LESSONS LEARNED UNDER THE NAPA PROCESS
  • Through the establishment of NAPA Teams and
    Working Groups, the NAPA process has improved
    coordination and dialogue at the national and
    regional levels. The Ministries of Environment,
    Finance, Planning and Development, and Civil
    Society have been driving the process.
  • The National Communication process should benefit
    from this broadened and bottom-up institutional
    framework.
  • The NAPA Stakeholder Consultation process
    particularly at the grassroots levels has
    generated a lot more data and information for
    climate change studies. The data and information
    includes traditional knowledge and coping
    strategies.
  • This additional level of information will
    particularly be useful for the process of
    preparation of Second National Communications by
    Parties.

10
LESSONS LEARNED UNDER THE NAPA PROCESS
  • Mainstreaming is a process and has been initiated
    under the NAPA Process through the establishment
    of appropriate institutional framework.
  • All NAPA Teams are multi-sectoral and
    multi-disciplinary with membership drawn from
    research institutions, agriculture, environment,
    forestry, fisheries, academia, media and civil
    society and private sector (Comoros) with some
    international consultants (Gambia and Uganda).
  • NAPA Teams are guided by a Project Steering
    Committee, which is more policy oriented and
    oversees the progress of the NAPA development
    process
  • The NAPA Project Steering Committee of The Gambia
    is chaired by a Permanent Secretary and includes
    National Focal Points of the Desertification and
    Biodiversity Conventions and the GEF Focal Point,
    National Assembly and Civil Society.
  • Comoros established a NAPA Island Committees to
    coordinate the NAPA process at the island level.

11
LESSONS LEARNED UNDER THE NAPA PROCESS
  • Mainstreaming through the PRSP, other National
    Plans and Programmes and the MDGs
  • In the selection of the priority NAPA projects in
    Bhutan, one of the criteria was to assess whether
    the projects complement national goals such as
    overcoming poverty, enhancing the adaptive
    capacity or other multilateral environmental
    agreements.
  • In Bangladesh the "Policy Matrix 18, integration
    of climate change adaptation in all policies,
    programmes and projects is one of the key targets
    and recognises that NAPA is closely related to
    the other environmental policies or programmes in
    particular the National Action Plan on
    biodiversity and the National Environmental
    Management Action Plan (NEMAD).

12
LESSONS LEARNED UNDER THE NAPA PROCESS
  • Reduction of the vulnerabilities of the rural
    communities to the adverse impacts of extreme
    weather events, enabling the rural communities to
    adapt to climate change, attainance of food
    security, resettlement of population, provision
    of fresh water, rational use of coastal
    structures, effective land-uses, utilisation of
    marine resources, reduction of poverty and
    environmental degradation and achievement of
    sustainable rural livelihood are all elements of
    poverty reduction strategy that are common to the
    NAPA and the PRSP in Malawi and Samoa.
  • Key activities laid out in Mozambiques PRSP
    include measures to manage its vulnerability to
    and strengthening its capacity to respond to
    natural disasters. This resulted to disaster risk
    management and reduction being the highest
    priority in the Mozambique NAPA.

13
LESSONS LEARNED UNDER THE NAPA PROCESS
  • The NAPA process is entering a transition from
    NAPA preparation to NAPA implementation. Six
    countries have already received approval for
    funding implementation from the LDC Fund under
    the GEF.
  • The implementation of these projects and others
    to come will provided practical knowledge and
    experience on climate change adaptation in
    addition to whatever study outcomes will be
    coming out of the technical institutions and
    Universities. This Learning by doing is a
    concrete and fast way of gaining knowledge and
    the NAPA Implementation process will provide this
    to the global climate change process and in
    particular the experiences and knowledge gained
    will be good input to the National Communications
    process.

14
SUMMARY AND CONCLUSIONS
  • The National Communications Process should adopt
    and maintain the institutional framework sutup
    under the NAPA process
  • NAPA process is at a juncture implementation
    phase is starting for about half of the LDCs that
    have completed their NAPAs, while the other half
    of LDC Parties are still at various stages of
    preparation - some of whom (East Timor,
    Afghanistan, Equatorial Guinea) are at incipient
    stages
  • There is continuing need for the LEG to provide
    technical guidance and advice on the preparation
    of NAPAs, to advise on capacity-building, to
    facilitate the exchange of information, and to
    advise on efforts to mainstream adaptation into
    development planning

15
SUMMARY AND CONCLUSIONS
  • Closer collaboration is needed to support LDC
    Parties to prepare NAPA proposals for funding,
    and to support NAPA teams that are in various
    stages of NAPA preparation
  • Need to continue monitoring bottlenecks and
    constraints in the preparation of NAPAs through
    targeted questionnaires
  • Variety of effective partnerships have been built
    which involve a number of support organizations
    at the international level as well as in-country
    institutions at the level of the individual NAPA

16
SUMMARY AND CONCLUSIONS
  • Contributed to raising awareness of adaptation
    among stakeholders, integrating climate change
    concerns across agencies represented in NAPA
    teams, and raising the importance of adaptation
    to the highest decision-making level through the
    NAPA endorsement process
  • NAPA preparation process has itself generated
    benefits beyond serving as a vulnerability and
    adaptation assessment. The challenge will be to
    maintain the momentum and awareness generated
    into the implementation phase

17
SUMMARY AND CONCLUSIONS
  • The COP should extend the mandate of the LEG at
    COP 13 for the continuation of the provision of
    advisory services to meet the special
    circumstances and needs of the LEAST DEVELOPED
    COUNTRIES (LDCs) and implementation of the
    remaining elements of the LDC Work Programme
    adopted by COP 7 in 2001

18
  • THANK YOU
Write a Comment
User Comments (0)
About PowerShow.com