LOAD FLOW STUDIES ON THE GUYANA POWER - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

LOAD FLOW STUDIES ON THE GUYANA POWER

Description:

A load flow study is done on a power system to ensure that ... Generation operates within specified real and reactive power limits ... – PowerPoint PPT presentation

Number of Views:1195
Avg rating:3.0/5.0
Slides: 49
Provided by: V256
Category:

less

Transcript and Presenter's Notes

Title: LOAD FLOW STUDIES ON THE GUYANA POWER


1
LOAD FLOW STUDIES ON THEGUYANA POWER LIGHTS
(GPL) DEMERARA SYSTEM
  • Verlyn Klass
  • Senior Lecturer Head
  • Department of Electrical Engineering
  • University of Guyana
  • October 2006

2
What is a Load Flow Study
  • A load flow study is done on a power system to
    ensure that
  • Generation supplies the demand (load) plus
    losses.
  • Bus voltage magnitudes remain close to rated
    values
  • Generation operates within specified real and
    reactive power limits
  • Transmission lines and transformers are not
    overloaded.

3
A Load Flow Study Specifically Investigates the
Following
  • Busbar voltages
  • Effect of rearranging circuits and incorporating
    new circuits on system loading.
  • Effect of injecting in-phase and quadrature boost
    voltages on system loading.
  • Optimum system running conditions and load
    distribution.
  • Optimum system losses.
  • Optimum rating and tap range of transformers.

4
The Load Flow Problem
  • The starting point of a load flow problem is a
    single line diagram of the power system, from
    which input data for computer solutions can be
    obtained. Input data consist of bus data,
    transmission line data and transformer data.

5
The Load Flow Problem
  • The following four variables are associated with
    each bus k - voltage magnitude Vk, phase angle
    dk, net real power Pk and reactive power Qk
    supplied to the bus.

6
The Load Flow Problem
  • Each bus k is categorized into one of the
    following bus types
  • Swing bus - There is only one swing bus which
    for convenience is normally numbered as bus 1,
    and is a reference bus for which V1 and d1 are 1
    and 0o respectively
  • Load Bus or PQ bus- Most buses in a typical load
    flow program are load buses. Pk and Qk are
    specified and the program computes Vk and dk.
  • Voltage Controlled bus or PV bus - These are
    generally generator buses where Pk and Vk are
    specified and Qk and dk are computed.

7
The Load Flow Problem
  • There are two methods of solving the load flow
    problem.
  • A) The Gauss Seidel Method
  • B) The Newton Raphson Method

8
The Gauss-Seidel Method
  • This method solves, by an iterative process, the
    following equation that represents a power system
    having N buses

9
GPLS POWER SYSTEM
  • GPLS power system, with an installed capacity of
    105 MW, consists of the following
  • Demerara Interconnected System
  • Berbice Interconnected System
  • Anna Regina System
  • Bartica System
  • Wakenaam System
  • Leguan System

10
THE OBJECTIVES OF THIS STUDY WERE AS FOLLOWS
  • To model the (GPLS) Demerara system for load
    flow studies.
  • To perform load flow studies on GPLs present
    Demerara 60 Hz system.
  • To use a static model of the frequency converters
    and perform studies on the Demerara 50 and 60 Hz
    system.
  • To perform load flow studies on GPLs future
    Demerara power system (all load converted to 60
    Hz.).
  • To analyse the results of the load flow studies.

11
Demerara Interconnected System Data
  • Installed Capacity 76 MW
  • Peak Load - 67 MW
  • Three power stations, two at Garden of Eden and
    one at Versailles, generating at 13.8 kV, 60Hz
  • Two power stations at Kingston generating at 11
    kV, 50 Hz

12
Demerara Interconnected System Data
  • Demerara Power, an Independent Power Producer,
    owns and operates two power stations at Garden of
    Eden and Kingston
  • All other power stations are owned by GPL

13
Demerara Interconnected System Data
  • The 25 MVA rotary frequency converter station at
    Sophia has machines rated at 13.8 kV, 60 Hz and
    11 kV, 50 Hz which operate as motors or
    generators depending on the flow of power

14
Demerara Interconnected System Data
  • A 69 kV transmission system connects the Garden
    of Eden stations and the Sophia frequency
    converter station

15
The Newton-Raphson Method
  • The Newton-Raphson method solves the nonlinear
    equation y f(x) where the x, y and f vectors
    for the power flow problem are defined as

16
Single Line Diagram of the Demerara
Interconnected System
17
Methodology of Study
  • Data Collection
  • Data Analysis
  • Load Flow Study

18
Data Collection
  • The following data was collected
  • Single line diagram of the GPL Demerara system.
  • Reactances of all generators at the Demerara
    Power stations, and GPLs Garden of Eden and
    Versailles power stations and the Sophia
    frequency converters.
  • Impedances of all transmission and distribution
    lines and transformers.

19
Data Collection
  • Hourly operations data for the system for
    weekdays (2) and Saturday and Sunday
  • Data from recent power analyser recordings giving
    feeders power factor and voltages

20
Analysis of Data
  • The loads (MW and MVar) for the various busbars
    were calculated using hourly feeder current and
    voltages from the log sheets and the
    corresponding hourly power factor data recorded
    on a power demand analyser.

21
Analysis of Data
  • Sophia was found to be the major load centre for
    the Demerara system with an evening peak of
    nearly 30 MW
  • The peak 60 Hz load is about 45 MW and is
    primarily residential
  • The 50 Hz load is mainly industrial /commercial
    and has a day peak of around 20 MW.

22
(No Transcript)
23
Analysis of Data
  • 50 Hz system hourly power factors range from 0.79
    to 0.89 and the 60 Hz system power factors are
    from 0.81 to 0.85.
  • The frequency converters produce between 20 to 30
    of the MVar requirement of the Demerara system.

24
Analysis of Data
  • Comparison of power analyzer data and station
    logs revealed that the Sophia panel meters were
    overstating the Sophia 13.8 kV voltages.

25
(No Transcript)
26
Analysis of Data
  • The Demerara Power generators are used as the
    base load generators for the system, with GPLs
    Garden of Eden and Versailles stations being used
    to maintain bus voltages levels and for peaking
    purposes.

27
(No Transcript)
28
Load Flow Studies
  • The 60 Hz machine of the frequency converters
    were modeled as generators and when they operated
    as motors the generators were deemed to be
    supplying negative power.

29
Load Flow Studies
  • The various busbars were designated as follows
  • Garden of Eden 13.8 kV busbar - Slack Bus
  • Demerara Power GOE busbars - PV Bus
  • Sophia Station 13.8 kV busbar - PV bus
  • Versailles Power Station busbar - PV bus

30
Load Flow Studies
  • Transformer taps were set as per system
  • 1.0 for Garden of Eden transformers
  • 0.955 for Sophia transformers.

31
Load Flow Studies
  • Hourly load flow runs were carried out for three
    of the days from which hourly data had been
    collected, that is, two weekdays and Saturday.
  • Transformer taps were changed to determine the
    best tap position

32
Load Flow Studies
  • The frequency converters were represented as an
    13.8/11 kV autotransformer in combination with a
    capacitor. Load flow runs were carried out on
    the combined Demerara 50 and 60 Hz systems for
    system peak load.

33
Load Flow Studies
  • The frequency converters were removed from the
    system and the 60Hz system was extended to cater
    for the present 50 Hz load.
  • Load flow runs were carried out for day and night
    peaks.

34
Analysis of Results
  • The following abbreviations apply
  • DPGOE - Demerara Power station at Garden of
    Eden
  • GPLGOE - GPLs Garden of Eden Station
  • LFR - The hourly load flow run

35
Analysis of Results
  • As GPLGOE was the slack busbar comparison was
    made between its generation during GPL operations
    and the load flow runs. For the GPL operations
    GPLGOE generation was higher than that of the LFR
    by 70 during the off peak periods and up to 120
    during evening peaks.

36
Analysis of Results
  • The LFR showed an average of 2 system losses
  • GPL operations showed losses as much as 18 and
    averaged 11 over the period of analysis.

37
(No Transcript)
38
Analysis of Results
  • The LFR consistently generated around 3 MVars at
    DPGOE. GPL operations show MVAR generation
    between 8 and 13 MVars at this location.

39
Analysis of Results
  • The LFR generation of MVars at Sophia was
    consistently higher than that of GPL operations.
    This was as high as 15 MVar at peak load whereas
    GPL operations generate just around 10 MVars at
    the same period

40
Analysis of Results
  • MVar generation at GPLGOE and Versailles were
    quite similar for both GPL operations and the LFR

41
(No Transcript)
42
Analysis of Results
  • Changing of transformer taps
  • The present tap positions of the GPL transformers
    proved to be the optimum positions to maintain
    bus voltages and minimise losses.

43
Analysis of Results
  • Static Representation of the Frequency Converters
  • The results achieved from the load flow run for
    system peak suggest that this model could be
    acceptable if separate representation is made for
    the mechanical losses of the frequency converters.

44
Analysis of Results
  • Total Demerara Load at 60 Hz
  • The frequency converters would not be required so
    capacitors would be needed at all locations to
    provide the MVar injection presently done by the
    frequency converters
  • Switched capacitors would have to be used as
    different values would be required for the day
    and night peaks

45
Conclusions
  • The usefulness of load flow studies in the
    investigation of the following were demonstrated
  • Optimum system running conditions and load
    distribution.
  • Optimum system losses.
  • Optimum tap range of transformers.
  • Effect of incorporating new circuits on system
    loading.

46
Conclusions
  • The data collection and analysis highlighted
    problems with GPLs system operations which were
    confirmed by the load flow study.
  • The difference in GPLs calculated loads and
    generation show a high level of losses in GPLs
    generation and transmission system which require
    further investigation.
  • The Sophia 13.8 kV bus voltages are lower than
    the other bus voltages and need to be increased
    for proper system operation.

47
Conclusions
  • The static representation of the frequency
    converters by a transformer and a variable
    capacitor is an adequate model for load flow
    studies. Converter mechanical losses can be
    added subsequently to the total system losses.

48
Conclusions
  • The availability of load flow studies would be
    helpful to small utilities as they seek to
    integrate their power system with different types
    of generation
Write a Comment
User Comments (0)
About PowerShow.com