1
ICCP Quality Codes
  • Bill Blevins/Frank Kendall

2
History
  • In the Zonal Market, there were four key
    documents providing important communication
    information to market participants. They were
  • Network Interface Control Document (NICD)
  • Communicating with ERCOT
  • TAC Approved Telemetry Standards
  • ERCOT Operating Guide Section 8
  • The information contained in the above documents
    is equally important to market participants under
    the Nodal Market.

3
History
  • Nodal Documents
  • A review of the four Zonal documents shows a
    considerable amount of information duplication.
    An example is the data exchange tables they
    appear in both Communicating with ERCOT and the
    ERCOT Operating Guide Section 8.
  • Under consideration is the creation of the
    following documents
  • ERCOT Communication Handbook ERCOT Operating
    Guide Section 8
  • The ERCOT Communication Handbook will generally
    combine the information in the following
    documents
  • Network Interface Control Document (NICD)
    Communicating with ERCOT
  • The ERCOT Operating Guide Section 8 revision for
    Nodal will incorporate the TAC Approved Telemetry
    Standards.
  • Revising these documents for Nodal presents the
    opportunity to reduce the number of documents and
    also eliminate duplication of information across
    them.

4
Issues
  • The quality and availability of telemetry
    provided to ERCOT are important to the
    performance of the ERCOT State Estimator.
  • The TAC approved Telemetry Standards do not
    provide quality code mapping.
  • During Business Requirements phase in developing
    SCADA TPTF requested that ERCOT include quality
    code mapping as part of the SCADA requirements
    document.
  • Additionally TPTF requested ERCOT discuss
    internally and externally means to provide
    mapping standards as part of the Telemetry
    Standard.

5
TAC approved Nodal Telemetry Standard
requirements
  • ICCP Links
  • Data Quality Codes
  • Market Participants shall provide documentation
    to ERCOT describing their native system quality
    codes and defining the conversion of their
    quality codes into the ERCOT defined quality
    codes.
  • Status analogs telemetered to ERCOT will be
    identified with the following quality codes
  •     Valid represents analog or status the TSP
    considers valid
  •     Manual represents a analog or status
    entered manually at the market participant (not
    received from the field electronically)
  •     Suspect - Represents a analog or status in
    which the TSP is unsure of the validity
  •     Invalid Represents a analog or status
    which the market participant has identified as
    out of reasonability limits.
  • Com_fail informs ERCOT that due to
    communications failure, the analog or status
    provided ERCOT is not current

6
Problems with the Current TAC approved Telemetry
Standard
  • ICCP supports a richer set of quality codes than
    the current standard reflects.
  • Extended ICCP attributes (Current Source, Normal
    Value) convey important information to ERCOT.
    These extended attributes are not addressed in
    the Telemetry Standards.
  • Com_fail is not supported by ICCP.

7
TPTF request
  • TPTF requested that the EMS team work to
    incorporate the SCADA requirements Quality Codes
    as part of the telemetry standards.
  • Actions
  • Met with IRT-John Webb to discuss Quality Codes.
  • Informed Operations of the effort we are
    undertaking to revise the TAC approved Telemetry
    Standards.
  • Confirmed with NMMS the Quality Codes do not
    impact them.
  • Confirmed with MMS the codes that ABB require.

8
Operating Guides Revision Task Force (OGRTF)
  • OGRTF Posted the Operating Guide Section 8 for
    comments
  • ERCOT submitted comments proposing the Quality
    code mapping as proposed in the ERCOT
    requirements document be incorporated as part of
    the Operating Guides Section 8.
  • This should allow for Market participants to
    submit their feedback on the proposed Quality
    Code mapping.

9
Proposed ERCOT ICCP Quality Code Requirements
  • ICCP Quality Codes from Market Participants to
    ERCOT
  • The following table describes the ICCP quality
    codes to be provided to ERCOT by the Market
    Participant, the conditions under which each ICCP
    quality code is to be set, and the translation
    from the Market Participants ICCP quality code
    to the related local ERCOT real-time database
    quality code.

10
Table 1 ICCP Quality Codes from Market
Participants to ERCOT
11
Table 1 ICCP Quality Codes from Market
Participants to ERCOT
12
Proposed ERCOT ICCP Quality Code Requirements
  • ICCP Quality Codes from ERCOT to Market
    Participants
  • The following table describes the ICCP quality
    codes to be provided to the Market Participant by
    the ERCOT, the conditions under which each ICCP
    quality code is set, and the translation from the
    local ERCOT real-time database quality codes to
    the related ICCP quality code.

13
Table 2 ICCP Quality Codes from ERCOT to Market
Participants
14
Table 2 ICCP Quality Codes from ERCOT to Market
Participants
15
RTU and ICCP Cutover
  • Can ERCOT cut over ICCP under Zonal?
  • ERCOT is evaluating the scope of any Zonal cut
    over of QSEs.
  • It looks like the work would involve about ½ a
    man year.
  • Vendor has provided input that Database changes
    would be required and the scope would be more
    than just mapping RTU points to ICCP.
  • ERCOT is going to work with a volunteer QSE to
    performed a more detailed evaluation before
    proposing any Zonal changes.