Title: Project Overview
1Project Overview
- John N. Galayda Director of LCLS Construction
- March 30, 2009
290 complete on TEC 1.5 XTOD 87 complete 1.6
XES 46 complete 1.9 CF 90 complete ANL 99
complete LLNL 90 complete
3(No Transcript)
4Observation of 3rd Harmonic, 1st Undulator
521 Undulators Installed
Enough to saturate at 1.5 A
6X-Ray Transport/Optics/Diagnostics
- WBS 1.5 is gt87 complete
- LLNL scope gt90 complete
- Mask, Slits, Attenuator, Imager at SLAC
- K-mono tested at SSRL, in assy at LLNL
- Mirrors coated
- X-ray diagnostics online in May
- X-rays into Near Hall in July
5 mm collimator
Soft X-Ray Offset mirror system
Hard x-ray Monochromator (K Spectrometer)
Gas Detector
Solid Attenuator
Direct Imager
Pulse Energy Thermal Detector
Slit
Hard X-Ray Offset mirror system
Gas Attenuator
e-
Gas Detector
Start of Experimental Hutches
Muon Shield
7LLNL Hardware Prepared for Delivery to SLAC
Gas Attenuator
8Gas Attenuator Installation
9XR Beam Path to Far Hall
- Hardware procurements underway at LLNL
- Stands for vacuum system
- Scope transfer from LLNL to SLAC
- Same design as Beam Transport Hall
- Bids received, 15 lower price
- Cabling bid package in preparation
10Issues for the Summer
- Must get ready for experiment program
- John Arthur leading this effort
- Must get XR diagnostics and AMO installed
- Geoff Pile (ANL) spending the summer with us
- Must Commission XR systems in near hall
- Lining up reinforcements for this too.
11Summer Look-Ahead
- Re-start linac 1 April
- Additional testing time for Personnel Protection
- Re-commission undulator e-beam systems
- Look for gain at 13.6 GeV
- Commission Front End XR Diagnostics 1 May
- Continue installation of Front End (mirrors, etc)
- Get AMO on the floor in July
- Commission AMO in August
- Users in September
12PROJECT SAFETY EXPERIENCEThrough February 2009
DART Rate
- Total Project Hours
- 2.14 M Hours worked
- DART Rate 1.03
-
- SubContractors
- 594 K Hours worked
- DART Rate 3.03 (9 Incidents)
- TRC Rate 4.04 (3 Incidents)
- LCLS Collaboration
- 1,546 K Hours worked
- DART Rate 0.26 (2 Incidents)
Injury rates based on 200 K hours (100 man years)
of effort. DOE/SC Goal is a Reportable Case (TRC)
rate of lt 0.25 and a Days Away, Restricted, or
Transferred (DART) rate lt 0.65 per 100 FTEs.
13From AMO to End of Project
- Build Far Hall Hutches
- Get ready for accelerated LUSI activities
- Execute Space Renovation
- Detect X-Rays in Far Hall
- Endgame
14End of Presentation