Title: Project Overview


1
Project Overview
  • John N. Galayda Director of LCLS Construction
  • March 30, 2009

2
90 complete on TEC 1.5 XTOD 87 complete 1.6
XES 46 complete 1.9 CF 90 complete ANL 99
complete LLNL 90 complete
3
(No Transcript)
4
Observation of 3rd Harmonic, 1st Undulator
5
21 Undulators Installed
Enough to saturate at 1.5 A
6
X-Ray Transport/Optics/Diagnostics
  • WBS 1.5 is gt87 complete
  • LLNL scope gt90 complete
  • Mask, Slits, Attenuator, Imager at SLAC
  • K-mono tested at SSRL, in assy at LLNL
  • Mirrors coated
  • X-ray diagnostics online in May
  • X-rays into Near Hall in July

5 mm collimator
Soft X-Ray Offset mirror system
Hard x-ray Monochromator (K Spectrometer)
Gas Detector
Solid Attenuator
Direct Imager
Pulse Energy Thermal Detector
Slit
Hard X-Ray Offset mirror system
Gas Attenuator
e-
Gas Detector
Start of Experimental Hutches
Muon Shield
7
LLNL Hardware Prepared for Delivery to SLAC
Gas Attenuator
8
Gas Attenuator Installation
9
XR Beam Path to Far Hall
  • Hardware procurements underway at LLNL
  • Stands for vacuum system
  • Scope transfer from LLNL to SLAC
  • Same design as Beam Transport Hall
  • Bids received, 15 lower price
  • Cabling bid package in preparation

10
Issues for the Summer
  • Must get ready for experiment program
  • John Arthur leading this effort
  • Must get XR diagnostics and AMO installed
  • Geoff Pile (ANL) spending the summer with us
  • Must Commission XR systems in near hall
  • Lining up reinforcements for this too.

11
Summer Look-Ahead
  • Re-start linac 1 April
  • Additional testing time for Personnel Protection
  • Re-commission undulator e-beam systems
  • Look for gain at 13.6 GeV
  • Commission Front End XR Diagnostics 1 May
  • Continue installation of Front End (mirrors, etc)
  • Get AMO on the floor in July
  • Commission AMO in August
  • Users in September

12
PROJECT SAFETY EXPERIENCEThrough February 2009
DART Rate
  • Total Project Hours
  • 2.14 M Hours worked
  • DART Rate 1.03
  • SubContractors
  • 594 K Hours worked
  • DART Rate 3.03 (9 Incidents)
  • TRC Rate 4.04 (3 Incidents)
  • LCLS Collaboration
  • 1,546 K Hours worked
  • DART Rate 0.26 (2 Incidents)

Injury rates based on 200 K hours (100 man years)
of effort. DOE/SC Goal is a Reportable Case (TRC)
rate of lt 0.25 and a Days Away, Restricted, or
Transferred (DART) rate lt 0.65 per 100 FTEs.
13
From AMO to End of Project
  • Build Far Hall Hutches
  • Get ready for accelerated LUSI activities
  • Execute Space Renovation
  • Detect X-Rays in Far Hall
  • Endgame

14
End of Presentation