Tehachapi Renewable Transmission Project - PowerPoint PPT Presentation

1 / 27
About This Presentation
Title:

Tehachapi Renewable Transmission Project

Description:

... to avoid impacts of overhead T/Ls to residential areas in the City of ... Two aboveground transition stations (one at each end of the underground segment) ... – PowerPoint PPT presentation

Number of Views:262
Avg rating:3.0/5.0
Slides: 28
Provided by: aub79
Category:

less

Transcript and Presenter's Notes

Title: Tehachapi Renewable Transmission Project


1
Tehachapi Renewable Transmission Project
Public Draft EIR/EIS
  • Web Seminar
  • March 12, 2009
  • Aspen Environmental Group
  • Lead Agencies
  • California Public Utilities Commission (CPUC)
  • USDA Forest Service, Angeles National Forest
    (ANF)

2
Dial-in Number 800-550-8104Participant ID
2345678
  • Web Seminar
  • Host Jon Davidson, Aspen Environmental Group
  • Schedule This web seminar is scheduled for one
    hour the PowerPoint presentation is 45 minutes
  • Q A Questions will be answered after the
    presentation in the order received.
  • Please submit questions during the presentation
    using the Instant Messaging feature in the
    toolbar.
  • For questions that cannot be answered in the
    time allotted, we will follow up with you
    individually.

3
Agenda
  • Overview of the Project and Alternatives
  • Organization of the Draft EIR/EIS
  • Major Conclusions
  • How to Submit Comments

4
Agenda
  • Overview of the Project and Alternatives
  • Organization of the Draft EIR/EIS
  • Major Conclusions
  • How to Submit Comments

5
Overview of the Project and Alternatives
  • Southern California Edisons (SCE) proposed
    Tehachapi Renewable Transmission Project (TRTP)
    includes new and upgraded transmission line and
    substation infrastructure along approximately 173
    miles of new and existing rights-of-way (ROW) in
    portions of Kern County, Los Angeles County, and
    San Bernardino County.
  • Project Alternatives include
  • Alternative 1 No Project/Action Alternative
  • Alternative 2 Proposed Project
  • Alternative 3 West Lancaster Alternative
  • Alternative 4 Chino Hills Alternative Routes A
    D
  • Alternative 5 Partial Underground Alternative
  • Alternative 6 Maximum Helicopter Construction in
    the ANF Alternative and
  • Alternative 7 66-kV Subtransmission Alternative.

6
Overview of the Project and Alternatives
  • Purpose and Need
  • California Renewables Portfolio Standard (RPS)
    goal
  • Tehachapi Wind Resource Area (TWRA) in southern
    Kern County expected to provide up to 4,500 MW of
    new wind generation
  • Antelope Transmission Project (ATP) previously
    approved to provide 700 MW of transmission
    capacity
  • Project Purpose
  • Provide transmission capacity for planned wind
    energy projects in the Tehachapi/Mojave area of
    southern Kern County.
  • Eliminate transmission constraints when
    transmission lines need to be shut down in the
    Cajon Pass.
  • Enhance the reliability of the transmission grid
    in the Antelope Valley where power load is
    growing.
  • Executive Order 13212
  • Expedite the completion of energy-related projects

7
Overview of the Project and Alternatives
  • Alternative 2 Proposed Project
  • Project Segments in Geographical Order, from
    North to South
  • Segment 10 (North Region Kern County)
  • New 500-kV single-circuit transmission line (T/L)
    in new ROW for 17 miles between Windhub and
    Whirlwind Substations
  • Segment 4 (North Region Kern County, Los Angeles
    County City of Lancaster)
  • Two new 220-kV single-circuit T/Ls in new ROW for
    4 miles between Cottonwind and Whirlwind
    Substations
  • New 500-kV single-circuit T/L in new ROW for 16
    miles between Whirlwind and Antelope Substations
  • Segment 5 (North Region Los Angeles County City
    of Lancaster, City of Palmdale)
  • Rebuild existing 220-kV T/Ls (two) to 500-kV
    standards for 18 miles between Antelope and
    Vincent Substations

8
Overview of the Project and Alternatives
  • Alternative 2 (continued)
  • Segment 11 (Central Region Los Angeles County
    Angeles National Forest)
  • Rebuild existing 220-kV T/L to 500-kV standards
    for 19 miles between Vincent and Gould
    Substations, traversing USDA Forest Service lands
    in the Angeles National Forest (ANF)
  • Segment 6 (Central Region Los Angeles County
    Angeles National Forest )
  • Rebuild existing 220-kV T/L to 500-kV standards
    for 32 miles between Vincent Substation and the
    southern boundary of the ANF
  • Segment 11 (South Region Los Angeles County
    Cities of La Cañada Flintridge, Pasadena,
    Temple City, Rosemead, Monterey Park)
  • New 220-kV circuit on the vacant side of existing
    220-kV double-circuit structures between Gould
    and Mesa Substations
  • Segment 7 (South Region Los Angeles County
    Cities of Duarte, Irwindale, Baldwin Park,
    City of Industry, South El Monte,
    Montebello, Monterey Park)
  • Rebuild existing 220-kV T/L to 500-kV standards
    for 16 miles between the southern boundary of the
    ANF and Mesa Substation

9
Overview of the Project and Alternatives
  • Alternative 2 (continued)
  • Segment 8 (South Region)
  • Rebuild existing 220-kV T/L to 500-kV standards
    for 33 miles between the San Gabriel Junction
    and Mira Loma Substation
  • Rebuild existing 220-kV T/L from single-circuit
    to double-circuit structures for 7 miles
  • Segment 9 (Substations)
  • New Whirlwind Substation (500/220-kV), located 4
    - 5 miles south of Cottonwind Substation in Kern
    County
  • Upgrade five existing substations to accommodate
    new T/L construction and system compensation
    elements
  • Antelope Substation (Segments 4 and 5)
  • Vincent Substation (Segments 5, 11, and 6)
  • Mesa Substation (Segments 11 and 7)
  • Gould Substation (Segment 11)
  • Mira Loma Substation (Segments 8)

10
Overview of the Project and Alternatives
  • Alternative 3 West Lancaster Alternative
  • Suggested by members of the public prior to the
    scoping period, due to potential land use
    conflicts in west Lancaster
  • Deviates from the Alternative 2 alignment for 3.4
    miles along Segment 4
  • At Segment 4, Mile 14.9, the Alternative 3
    alignment turns south down 115th Street West,
    versus 110th Street West under Alternative 2
  • The new 500-kV T/L continues for 2.9 miles then
    turns east for 0.5 mile
  • Alternative 3 rejoins the Alternative 2 alignment
    at Segment 4, Mile 17.9
  • Increases the overall length of Segment 4 by 0.4
    mile
  • Requires one less transmission structure due to
    greater spacing between towers along Segment 4

11
Overview of the Project and Alternatives
  • Alternative 4 Chino Hills Route Alternatives
  • Suggested by the City of Chino Hills during the
    scoping period to avoid the proximity of T/L
    infrastructure to existing residences
  • Avoids the construction of 16 miles of Segments
    8A, 8B, and 8C through Chino Hills
  • Includes four routing options that deviate from
    the Alternative 2 alignment at Segment 8, Mile
    19.2 and continue southeast, terminating within
    or near Chino Hills State Park

12
Overview of the Project and Alternatives
  • Alternative 5 Partial Underground Alternative
  • Developed to avoid impacts of overhead T/Ls to
    residential areas in the City of Chino Hills
  • Follows the same alignment of Alternative 2, with
    3.5 miles of the T/L installed underground along
    Segment 8 between Mile 21.8 and Mile 25.4
  • Primary components of the underground segment
    include
  • An underground tunnel with vertical access shafts
  • Circular tunnel with a 16-foot internal diameter
    and 18-foot external diameter
  • Monitoring systems, ventilation systems, lighting
    system, communication system, power source,
    electrical distribution system, and telemetry
    will be included during tunnel construction
  • Western access shaft is 420 feet deep, 75 feet
    long, 20 feet wide eastern access shaft is 100
    feet deep, 75 feet long, 20 feet wide
  • Two aboveground transition stations (one at each
    end of the underground segment)
  • Gas Insulated Line (GIL) system infrastructure

13
Overview of the Project and Alternatives
  • Alternative 6 Maximum Helicopter Construction
  • Requested by the Forest Service to reduce ground
    disturbance within the ANF by minimizing new road
    construction through use of helicopters during
    construction
  • Requires the construction of eleven 4-acre
    helicopter staging areas throughout the ANF
  • Avoids the need to construct or improve 42 miles
    of access and spur roads in the ANF that are
    required under Alternative 2

14
Overview of the Project and Alternatives
  • Alternative 7 66-kV Subtransmission Alternative
  • This alternative re-routes and/or places the
    existing 66-kV subtransmission line underground
    in three locations to avoid or minimize Project
    impacts
  • Segment 7, Mile 8.9 9.9
  • 66-kV line is placed underground
  • Requested by the Los Angeles County Board of
    Supervisors
  • Minimizes impacts to passive recreation
    opportunities in the planned River Commons at the
    Duck Farm Project
  • Segment 7, Mile 11.4 12.0
  • 66-kV line is re-routed and placed underground,
    as identified by SCE
  • Provides habitat enhancement for least Bells
    vireos in the Whittier Narrows Recreation area
  • Segment 8 Mile 2.2 3.8
  • 66-kV line is re-routed, as identified by SCE
  • Provides habitat enhancement for least Bells
    vireos in the Whittier Narrows Recreation area

15
Agenda
  • Overview of the Project and Alternatives
  • Organization of the Draft EIR/EIS
  • Major Conclusions
  • How to Submit Comments

16
Organization of the Draft EIR/EIS
  • Organization of the Draft EIR/EIS
  • Executive Summary
  • Chapters
  • 1 Introduction
  • 2 Alternatives, including the Proposed
    Project ROW cross sections
  • 3 Affected Environment and Environmental
    Consequences
  • 4 Comparison of Alternatives
  • 5 Other Required NEPA and CEQA Considerations
  • 6 Development of the Tehachapi Wind Resource
    Area (TWRA)
  • 7 Consultation and Coordination
  • 8 References
  • 9 Glossary and Acronyms
  • 10 Index
  • Technical Appendices
  • A Alternatives Screening Report
  • B Notice of Preparation, Notice of Intent, and
    Federal Register Notice
  • C Air Pollutant Emissions Calculations
  • D Project Road Crossings
  • E Summary of the PdV Wind Energy Project EIR

17
Organization of the Draft EIR/EIS
  • Chapter 3 Affected Environment and Environmental
    Consequences
  • Section 3.X-1 Introduction
  • Describes the resource/issue area addressed and
    identifies issues raised during scoping
  • Section 3.X-2 Affected Environment
  • Includes an in-depth description of existing
    conditions relevant to the identified
    resource/issue area
  • Section 3.X-3 Applicable Laws, Regulations, and
    Standards
  • Section 3.X-4 Impact Analysis Approach
  • Presents the Applicant-Proposed Measures (APMs)
    identified by SCE for the resource/issue area
  • Lists the Significance Criteria that will be used
    to determine environmental impacts
  • Section 3.X-5 3.X-11 Analysis of Alternatives
  • Includes full environmental impact analyses for
    the proposed Project and all alternatives, as
    determined by the resource/issue area-specific
    Significance Criteria. Also includes discussion
    of cumulative effects.
  • Section 3.X-12 Impact Significance Summary
  • Provides a summary of all identified
    environmental impacts, including direct,
    indirect, and cumulative impacts, as relevant to
    the resource/issue area

18
Organization of the Draft EIR/EIS
  • Chapter 3 (continued)
  • Significance Criteria
  • Environmental impacts of the Project would be
    significant if they meet any of the identified
    Significance Criteria for the applicable
    resource/issue area
  • CEQA Guidelines (Appendix G, Environmental
    Checklist Form, Section IX) are commonly used to
    identify Significance Criteria
  • Impact Statements
  • For each resource/issue area, each identified
    impact has a unique number and title, followed by
    a full discussion/analysis of the impact
  • For example, the first impact identified in the
    Agricultural Resources analysis is
  • Impact AG-1 Construction activities would
    temporarily preclude the agricultural use of some
    Farmland
  • Many impact discussions address the north,
    central, and south regions of the Project Area
    separately due to substantial differences in how
    impacts occur within each region

19
Organization of the Draft EIR/EIS
  • Chapter 3 (continued)
  • Mitigation Measures
  • As feasible and applicable, mitigation is
    identified following each impact discussion
  • For each resource/issue area, each identified
    mitigation measure has a unique number and title,
    followed by a full discussion of the required
    action(s)
  • For example, the first mitigation measure for
    Impact AG-1 is, Mitigation Measure AG-1
    Coordinate construction activities with
    agricultural landowners.
  • Mitigation measures would be applied in addition
    to Applicant-Proposed Measures (APMs) and Best
    Management Practices (BMPs) included as part of
    the Project
  • CEQA Significance Conclusions
  • Provided for each identified impact, following
    the presentation of all applicable mitigation
  • Class I Significant and unavoidable impact
  • Class II Less than significant impact with
    implementation of mitigation
  • Class III Less than significant impact with no
    mitigation required
  • Class IV Beneficial impact

20
Agenda
  • Overview of the Project and Alternatives
  • Organization of the Draft EIR/EIS
  • Major Conclusions
  • How to Submit Comments

21
Major Conclusions
  • Impact Overview
  • Most impacts of the proposed Project and
    Alternatives would be construction related and
    temporary in nature
  • Significant long-term impacts include
  • Adverse visual changes associated with new
    transmission infrastructure
  • Increased corona noise levels
  • Constraints to aerial suppression of wildfires
  • Land disturbance in the ANF, particularly as
    related to road construction, would result in
    temporary impacts that would be of longer
    duration than most
  • Implementation of a multi-year mitigation and
    monitoring plan would be required to facilitate
    re-vegetation and prevent the establishment of
    invasive species
  • Visual scars from hillside road improvements
    would be apparent until Forest Service standards
    associated with relevant Operation Maintenance
    Levels (OMLs) are restored

22
Major Conclusions
  • Significant and Unavoidable Impacts (Class I)
  • Air Quality
  • Class I impacts would occur under Alternatives 2
    - 7
  • Construction emissions exceed daily significance
    thresholds in the South Coast Air Quality
    Management District and the Antelope Valley Air
    Quality Management District
  • Biological Resources
  • Class I impacts would occur under Alternatives 2
    - 7
  • Construction activities would disrupt vegetation
    and wildlife in a variety of ways
  • Cultural Resources
  • Class I impacts would occur under Alternative 2 -
    7
  • Construction may have direct effects to National
    Register of Historic Places (NRHP) properties, or
    to NRHP-eligible properties
  • Land Use
  • Class I impacts would occur under Alternative 4
    (Chino Hills Route Alternatives) and Alternative
    5 (Partial Underground Alternative)
  • Alternative 4 would not be consistent with the
    Chino Hills State Park General Plan
  • Alternative 5 would require the take of property
    and businesses through eminent domain

23
Major Conclusions
  • Significant and Unavoidable Impacts (continued)
  • Noise
  • Class I impacts would occur under Alternatives 2
    7
  • Construction activities would substantially
    increase ambient noise conditions for sensitive
    receptors within 200 feet of construction
    activities
  • Permanent noise levels along the ROW would
    increase due to corona noise from operation of
    the transmission lines and substations in the
    vicinity of sensitive receptors
  • Corona noise would not be in compliance with
    noise standards of Los Angeles County or the
    Cities of Chino, Monterey Park, and Whittier
  • Visual Resources
  • Class I impacts would occur under Alternatives 2
    7
  • Construction would result in visual impacts on
    landscape character and visual quality of
    landscape views as seen from various vantage
    points
  • Wildfire Prevention and Suppression
  • Class I impacts would occur under Alternatives 2
    7
  • Potential failure of Project components could
    result in wildfire ignitions and damage to homes
    from Project-related wildfires

24
Agenda
  • Overview of the Project and Alternatives
  • Organization of the Draft EIR/EIS
  • Major Conclusions
  • How to Submit Comments

25
How to Submit Comments
  • Submit Comments on the Public Draft EIR/EIS
  • Email
  • TRTP_at_AspenEG.com
  • Voicemail/Fax
  • (888) 331-9897
  • Postal Service
  • John Boccio / Justin Seastrand
  • CPUC / USDA Forest Service
  • c/o Aspen Environmental Group
  • 30423 Canwood Street, Suite 215
  • Agoura Hills, CA 91301
  • Attend a Public Meeting

26
How to Submit Comments
27
Questions / Comments
Write a Comment
User Comments (0)
About PowerShow.com