Title: CMS Cathode Strip Chambers


1
CMS Cathode Strip Chambers
  • Status Report
  • and
  • Schedule Update
  • as of
  • 6/22/99
  • by N. Chester

2
ME234/2
  • Design Changed due to low resistance measurements
    found on Aging Chamber
  • - Deleted Isolation Strip, replaced with 200
    micron wire, Redesigned Spacer Bars.
  • - Frame Drawings in process Drawing updates
    for design changes to follow.
  • P2(ME234/2 pre-production)Panel Production in
    Progress
  • - Cathode panels glued and ready for component
    assembly
  • - Anode panel gluing to start 6/22/99
  • - Frame available from Wisc. to be delivered
    this week
  • - Hope to complete assembly mid July, schedule
    is tight.
  • Production Status
  • - Panels 1428 panels received 200 yet due
    from initial production order Expect about 28
    per week to come in. Order for balance (1800)
    of panels in process.
  • - Lab 8 Some problem obtaining accuracy
    between Axxiom and Gerber Machines on initial 14
    panels. Improved registration process on Gerber
    to be tried on next 28 panels beginning 6/22/99.
  • -MP9 Production planned to start in October
    Clean room being assembled Vacuum and Gas
    supply system to follow Most tooling is
    available.

3
ME1/2, ME1/3, ME2/1, ME3/1
  • ME1/2
  • - Chamber Design in final stages To complete
    by 7/1/99.
  • - P4 prototype to be built by October, 1999.
  • ME2/1
  • - P3 and P3 - Design drawings complete
    Drawings presently being converted to Production
    Drawings Some changes to be made based on Aging
    chamber experience.
  • - P3 prototype being readied to send to UCLA for
    testing Crate is now available.
  • P3 Chamber Kit parts and Tooling are on order
    and being accumulated Expect to have all
    available and ready for shipment to PNPI by
    September, 1999.
  • ME1/3 ME3/1
  • - Designs previously started and set aside each
    about 50 complete Will be revisited once above
    designs completed. Expect to finish designs by
    October, 1999

4
Prototype Schedule
  • 01 Nov. 98 Aging CSC Dwgs. Comp Parts Ordered
  • 20 Nov. 98 P2 Proto. Assembled (ME2/2)
  • 20 Dec. 98 ME 2, 3 /2 Chamber Design Complete
  • 01 Jan. 99 P3 Proto. Assembled _at_ FNAL (ME2/1)
  • 15 Jan. 99 ME 2, 3 /2 Chamber Design Review
  • 01 Feb. 99 Aging CSC Proto. Assembled
  • 01 Feb. 99 ME 2, 3/2 All Drawings Released
  • 01 Mar. 99 P2 All Parts Ordered (ME 2, 3 /2)
  • 15 Mar. 99 Panel Production Site Readiness
    Review
  • 01 Apr. 99 7/1 P4 Proto. Drawings Complete
    (ME 1/2)
  • 01 Jun. 99 7/15 P2 Proto. Assembled (ME2/2)
  • 01 Jul. 99 9/99 P3 Proto. Sent to PNPI
    w/Tooling (ME 2/1)
  • 15 Sep. 99 Chamber Assembly Site Readiness
    Review
  • 01 Oct. 99 P5 Proto. Drawings Complete (ME
    3/1) P6 Proto. Drawings Complete (ME 1/3)
  • P4 Proto. Assembled _at_ FNAL (ME 1/2)
  • 01/07/00 P4 Proto. Sent to IHEP w/Tooling (ME
    1/2)
  • 01/09/00 P5 Proto. Sent to PNPI w/Tooling (ME
    3/1)
  • P6 Proto. Sent to IHEP w/Tooling (ME 1/3)

5
Production Milestones
  • April, 1999 - ME2, 3 / 2 Design
    Finalized Panel Production Begins
  • October, 1999 - Production of ME 2,
    3/2
  • Chambers
    begin
  • October, 2000 - Complete Assembly and
    Test of 23 Chambers -
    Begin Production of Smaller
    Panels forForeign Site
    Assembly
  • January, 2001 - Begin Chamber
    Production
  • at
    Foreign Sites
  • October, 2003 - All 148 ME2, 3 / 2
    Chambers Assembled and Tested
    All Parts Kits Shipped