Title: AMS Tracker Thermal Control System TTCS
1AMS Tracker Thermal Control System (TTCS) TTCS
Progress, Planning Routing, Integration in AMS
NLR-team J. van Es, P. Dieleman, B. Verlaat
(NIKHEF), A. Pauw, G. van Donk, T. Zwartbol, SM.
Bardet, M. BsibsiSun Yat-Sen University team
ZH. He, KH. Guo, JQ. Ni, SS. Lu, XZ. Wang, XM.
Qi, TX. Li, YH Huang, X. Huang, Mo, Xiao et al
INFN-AMS-team R. Battiston, M. Menichelli, C.
Gargiulo, A. Alvino, E. Laudi, et al.CAST-team
M. Jianyin, J. Cao, G. Lin et al. MIT-team V.
Koutsenko, Cai, A. Lebedev AIDC-team B. Hong,
N.J. Lin, B.C.Y. Hsu, W.M. Hsu, A.J.M. Shue,
Chun-Ching Yeh. K.M. Sun, D. Dai, M. Tsang, YT
Ho, Grand Jiang , Tsung-Cheng Lin , David Dai,
Y.T. Ho , Chung Lai, Robert Kuo, Mark Chen,
Bill C.Y. Hsu, N.J. Lin
2TTCS presentations
- TTCS Progress, Planning Routing AMS, J. van Es
(NLR) - SYSU activities TTCS EM testing, Accu APS/DPS
progress, Filling system, Zhenhui He (SYSU) - Condenser, Heat Exchanger, tubing design, Elisa
Laudi (INFN/AIDC) - TTCE progress, Mauro Menichelli, Vladimir
Koutsenko (INFN/MIT) - Box Manufacturing Integration activities, DrJ
(AIDC)(will be presented in Thermal System part)
3Contents
- TTCS progress and planning/routing of major
components to AMS - NLR activities
- Condenser design finalisation
- Box design and procurement (last but important
issues) - Pump testing (pumps arrived in the Netherlands
31-01-2008) - Embedded S/W requirements definition
- TTCS beam testing GSTTCS
4TTCS Progress Overview
- Major components
- Evaporators
- Transport tubing (details by INFN)
- Condensers (details by INFN/AIDC)
- TTCE (details and planning by INFN/MIT)
- TTCB Component boxes (Design finalisation NLR,
integration AIDC) - Other important tasks
- TTCS EM testing (see presentation Zhenhui He)
- Embedded S/W development (Vladimir Koutsenko and
Teun Zwartbol) and dynamic modelling (INFN,
Giuseppe di Mauro, ZC Huang and DC Mo)
5(No Transcript)
6TTCS Planning
Remark QM Vibration testing will be performed
after TTCS delivery to CERN
7Routing delivery of major components
- Evaporator
- All delivered to CERN waiting for integration of
bottom Tracker - Implementation of hydraulic connectors
- Cleaning of tubing
- Potentially use of evaporator for beam test
cooling
8Routing delivery of major components
Transport tubes
2 x VSB TTCS transport tubes AIDC
Integration _at_ SCL England
Bending tools
Clean tubes
Integration of tubes _at_ SCL England
9Routing delivery of major components
- Transport tubes (details see presentation INFN)
- Models ready 30-01-2008
- Manufacturing drawings on-going at AIDC
- Manufacturing support beam tubing and brackets
part ready 10-04-2008 - Manufacturing of bending tools for non-beam parts
ready 10-04-2008 - Integration of tubes at SCL
- Bending on site of transport tubes with AIDC
tools - Contract with welding company can be done by SCL
(all equipment available contract to be
arranged). Alternative is welding at CERN.
10Routing delivery of major components
- Condenser
- Condenser progress is presented by INFN/AIDC
- Major milestones
- QM delivery and TV-testing complete at Terni
14-04-2008 - FM delivery to CERN 19-06-2008
- Remark Condensers can only be integrated after
TRD-integration
1 x
QM manufacturing _at_ AIDC
Env. Testing Terni
4 x
FM integration at CERN
FM manufacturing _at_ AIDC
11Routing delivery of major components
- TTCE
- Delivery TTCE to be integrated on Main Wake
radiator(for planning see Mauro
Menichelli/Vladimir Koutsenko)
12Routing delivery of major components
TTCS boxes
FM primary
FM primary
FM primary
Primary ready 15-06-2008
Integration at AIDC
Integration on AMS at CERN
Env. testing at Terni
FM secondary
FM secondary
FM secondary
Secondary ready 22-07-2008
Integration at AIDC
Integration on AMS at CERN
Env. testing at Terni
QM primary
QM primary
QM primary
QM box ready 14-08-2008
Integration at AIDC
Performance testing at SYSU
Env. testing at Terni
13NLR tasks
- TTCS condenser design
- Update condenser design (manufacturing QM and FM
started) - Manifold adaptations for brazing
- Brazing plate design
- Gluing plate design
- Manifold design update
- Definition condenser integration sequence
14NLR tasks
- TTCS mechanical box design
- Box components
- Update HX manufacturing (to avoid impossible
welding) - Update cold orbit heaters manufacturing drawings
(FM upto completion) - Update pre-heater manufacturing drawings (FM upto
completion) - Box design
- Change sheet metal bending radius
- Box tubing design adaptation (to avoid impossible
welding) - Add box bracket design (unsupported length too
big) - Add strain relief support bracket for vibration
testing
15NLR tasks
TTCS boxes
HX and Tube lay-out update to avoid impossible
welding
HX simplification
Cover update
16NLR tasks
TTCS boxes
added bracket
Vibration support jig
TTCB on USS jig with strain relief support
structure for vibration tests
17NLR tasks
- TTCS box design
- Design upto finalisation
- Manufacturing drawings FM QM Primary box to be
approved - Manufacturing drawings FM Secondary box ready
22-02-2008 - TTCS Pump testing and preparations
- Test set-up ready (including filling system)
- Test procedure ready (including vapour start-up)
- Pumps arrive 5 February at NLR
- TTCE dynamic modelling (used to test TTCE)
- CGS/INFN student G. di Mauro has started
- Bi-weekly videoconference with CGS
- Update S/W requirements document and
discussion/agreement with Vladimir Koutsenko
18TTCS and beam testing
- Tracker needs cooling during beam testing
- But....TTCS condensers/radiators do not operate
with air cooling without high risk of
condensation - To cool the tracker it is proposed to use
theevaporator with a GScooling system
Ground Support TTCS by B. Verlaat
19TTCS and beam testing
- Possible options to use the GSTTCS
- As proposed by Bart
- Disadvantages
- No access of at evaporator inlet
- Clean pump (high static pressure) to be procured
- Install one TTCS box after beam testing and use
evaporator inlets at that TTCS box locations.
Further use GSTTCS - Disadvantages
- Clean pump (high static pressure) to be procured
- Install both boxes except for connections to
condensersfor one box. Connect GSTTCS HX to
that point. - Advantage Use FM (clean pump)
- Disadvantage Possible contamination flight pump
Ground Support TTCS by B. Verlaat